  1. Slide 1: Hamilton Works Community Liaison Committee (CLC) Meeting

    Hamilton Works Community Liaison Committee (CLC) Meeting October 9, 2024 1

  2. Slide 2: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 31 July 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. CLC Meeting Dates 7. Adjournment 2

  3. Slide 3: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 31 July 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. CLC Meeting Dates 7. Adjournment 3

  4. Slide 4: Coke Battery Performance – Method 303 – Daily (Q3 2024)

    Coke Battery Performance – Method 303 Performance Review – Daily (Q3 2024) Doors Lids Off-takes Date (% Leaks) (% Leaks) (% Leaks) 2015 Thresholds 54% 2% NA (July 2 start) 2016 Thresholds 32% 2% NA 2017-2019 Thresholds 10% 2% 5% 2020 - 2024 Thresholds 5% 1% 4% July - Sept 2024 Range 0 – 4.44% 0 – 0.

  5. Slide 5: Coke Battery Performance – Method 303 – 30-Day Rolling Avg. (Q3 2024)

    Coke Battery Performance – Method 303 Performance Review – 30-Day Rolling Avg. (Q3 2024) Doors Lids Off-takes Charging (sec) Date (% Leaks) (% Leaks) (% Leaks) (log avg) 2015 Limits (July 2 start) 38% 0.8% 25% 12 sec 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 - 2024 Limi

  6. Slide 6: Coke Battery Performance – Daily Observations (Q3 2024)

    Coke Battery Performance – Method 303 Performance Review – Daily Observations (Q3 2024) Pushing Emission Date (opacity %) 2015 Threshold (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 - 2024 ≥ 30% July - Sept 2024 0 – 27.5% Range (6.66%) (Average) July - September Operational Adjustments • N

  7. Slide 7: Coke Battery Performance: Additional Items, Community Feedback

    Coke Battery Performance Additional Items Community Feedback • No community feedback was received by Stelco in Q3 2024 • MECP invited to provide verbal comments 7

  8. Slide 8: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 31 July 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. CLC Meeting Dates 7. Adjournment 8

  9. Slide 9: Community Feedback

    Community Feedback Additional Questions? • Please contact us with concerns or questions about our operations - environment@stelco.com 9

  10. Slide 10: CLC Meeting Dates

    CLC Meeting Dates • The next meeting is proposed for Wed. Jan. 15, 2025 • Meeting schedule for remainder of year 2025 to be presented at the next meeting 10

  11. Slide 11: Agenda

    Agenda 1. Welcome 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 31 July 2024 Meeting 4. Coke Battery Performance 5. Community Feedback 6. CLC Meeting Dates 7. Adjournment 11

  12. Slide 12: Stelco – The Steel Company of Canada

    STELCO 7 The Steel Company of Canada