Grange Resources Limited · ASX:GRR

Grange Resources — AMEC Conference 2008

41 slides from Grange Resources's conference presentation, Aug 23, 2008

  1. Slide 1: Pursuing the most attractive niche in iron ore

    Pursuing the most attractive niche in iron ore Southdown Magnetite and Kemaman Pellet Project AMEC Conference 23 August 2008 Russell Clark Managing Director and CEO Grange Resources Limited (GRR) Level 11, 200 St Georges Terrace Perth, WA 6000, Australia Phone + 618 9321 1118 Fax + 618 9321 1523 www

  2. Slide 2: Disclaimer

    Disclaimer • The material in this presentation (“material”) is not and does not constitute an offer, invitation or recommendation to subscribe for, or purchase, any security in Grange Resources Limited (“GRR”) nor does it form the basis of any contract or commitment. GRR makes no representation or w

  3. Slide 3: Pursuing the most attractive niche in iron ore

    Pursuing the most attractive niche in iron ore  The niche…..DR pellets  Steelmaking 101: Integrated vs Electric Arc Furnace  Supply & Demand  DR pellet price and premium  Grange - positioned to capture the DR Pellet opportunity  Southdown magnetite project in Australia  Kemaman pellet plant i

  4. Slide 4: The most attractive niche in the iron ore industry: DR Pellets

    The most attractive niche in the iron ore industry: DR Pellets  We all understand the China boom – massive, growing demand for iron ore to China.  In Australia that demand is being met by Rio, BHP, FMG and some Juniors primarily with DSO.  Less understood is an iron ore opportunity that Grange co

  5. Slide 5: Steelmaking 101

    Steelmaking 101 • As pricey as it’s become, iron ore has no inherent value: it is only valuable as a feedstock for steelmaking • So, the attractiveness of supplying iron feedstocks to the steel industry starts with the competitiveness of the steelmaking process to which they contribute • There are 2

  6. Slide 6: Integrated Steelmaking process

    Integrated Steelmaking process • End-to-end, the Integrated Steelmaking route (the traditional and still dominant route for steel) is both capital intensive and environmentally unattractive Feeds for standard (carbon) steel: DSO Mining Sintering Ironmaking Steelmaking • Fines Sinter plant Iron • Lum

  7. Slide 7: Electric Arc Furnace process

    Electric Arc Furnace process • In contrast to integrated steelmaking, the Electric Arc Furnace steelmaking route is less capital-intensive and more environmentally attractive Feeds for standard (carbon) steel: Mining/ DR pellet production Ironmaking Steelmaking concentrating Grange Direct-reduced ir

  8. Slide 8: Feedstock for DRI and EAF

    Feedstock for DRI and EAF 72% 71% 70% Cumulative content 69% 68% 67% CaO+Mgo 66% SiO2+Al2O3 65% Fe 64% 63% 62% Southdown Carajas DR Carajas BF Typical HG Typical HG DR Pellet Pellet Pellet Lump Fines Source: CVRD, Grange Resources EAFs require suitable high grade pellets (pre-processed to DRI) or sc

  9. Slide 9: Scrap steel vs DRI for the EAF steelmaker

    Scrap steel vs DRI for the EAF steelmaker • Historically, scrap steel < US$200/t. • The price of scrap steel has increased hugely, due to overwhelming steel demand from China and other emerging economies: SCRAP STEEL PRICE HISTORY Source: Iron Age Scrap Price Bulletin • The demand and price implicat

  10. Slide 10: Growing shortage of DR pellets

    Growing shortage of DR pellets Credit Suisse Brazil─in the heartland of world DR pellet supply─sees DR pellet undersupply increasing for the foreseeable future. Seaborne Pellet Supply and Supply/Demand balance 180 4.0% Over Supply 3.2% Supply 2.2% 2.0% 160 140 0.0% (mt) Under Supply -1.5% -0.5% -1.9

  11. Slide 11: Demand for DR Pellets

    Demand for DR Pellets DR pellet demand is projected to increase significantly in SE Asia and the Gulf Region. SE Asia 70 +94%  Perwaja Steel  Mega Steel 60  Krakatau Steel 50 Gulf 40 +50%  Hadeed SE Asia  Qasco Mt +130% Gulf  Shadeed 30  Al-Tuwairqi 20  Others 10 0 2005 2008 2012 2017 Driver

  12. Slide 12: Prices…the Pellet opportunity is attractive

    Prices…the Pellet opportunity is attractive… With increasing demand, future price forecasts continue to look strong, with a good premium for BF pellets over DSO… Iron Ore and pellet Prices US$/t FOB Europe 200 180 160 Settlement 140 US$/tonne 120 100 80 60 BF Pellets Lumps 40 Fines 20 0 2006 2014 20

  13. Slide 13: …but the DR Pellet opportunity is even more attractive

    …but the DR Pellet opportunity is even more attractive with a further 10% premium for DR pellets over BF pellets. Iron Ore and pellet Prices US$/t FOB Europe 200 180 160 For DR pellets expect a Settlement premium of: 140 US$/tonne 120 US$17/t over BF 100 US$20/t over Lump (DSO) US$40/t over Fines (D

  14. Slide 14: Price – this year's result

    Price – this year’s result Prices 2007 ==> 2008 $180.00 $160.00 +86.67% $140.00 $120.00 2007 +71% US$/tonne FOB * $100.00 2008 $80.00 $60.00 $40.00 $20.00 $0.00 Carajas lump DR pellets Iron feedstock * Benchmark prices in US¢/dmtu, translated to US$/tonne FOB @ 67% Fe for ease of understanding. 14

  15. Slide 15: In Summary

    In Summary:  Iron Ore consumption is increasing worldwide, particularly in China.  With abundant gas and expanding infrastructure, demand for DR grade pellets is increasing exponentially in the Middle East and South East Asia  Supply is not matching demand in the DR market  Prices in the DR mark

  16. Slide 16: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 16

  17. Slide 17: Grange Overview

    Grange Overview Board of Directors Shares Anthony Bohnenn Non Executive ASX Code: GRR Chairman Current shares on Issue: 115,201,099 Russell Clark Managing Director Unlisted Options on Issue to Rio Tinto: 17,500,000 Alex Nutter Technical Director Share price (19 August 2008: ~A$2.00 Richard Krasnoff

  18. Slide 18: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 18

  19. Slide 19: Project Highlights

    Project Highlights Advanced Project  Initial Feasibility Study Completed  Infrastructure Solutions in Place  Ability to produce High Quality (DR Grade) Pellets with very low Phosphorus content  Growing DR Pellet Market in SE Asia & Middle East  Pellet Plant Close to Key Markets  Joint Venture

  20. Slide 20: Project Overview

    Project Overview Dual Location PELLET PLANT PRODUCING 4. DIRECT REDUCTION AND Southdown  Open pit mine operation BLAST FURNACE PELLETS  Magnetite concentrate production 6.6mtpa @ 69% Fe  Slurry pipeline to existing port  Shipping in Capesize vessels Kemaman  Pellet production ~7mtpa  Deep wate

  21. Slide 21: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 21

  22. Slide 22: Tenement & Deposit Location

    Tenement & Deposit Location 70% Grange / 30% Sojitz JV 100% Grange Resources Ltd 22

  23. Slide 23: Southdown Resource

    Southdown Resource Mining Leases (Western Area) Over 230 drill holes to date Indicated and inferred resources: 479 MT at 37.3 % magnetite Exploration Licence (Eastern Area) Only 23 drill holes to date Target Potential Resources: Approximately 500 MT (est) Total Southdown open cut mineable resource p

  24. Slide 24: Metallurgical & Pelletising Testwork

    Metallurgical & Pelletising Testwork Kobelco Kobelco Concentrate Pellets Comprehensive programme of metallurgical % % test work completed, culminating in the successful production of high quality DR Fe 69.76 67.23 and BF grade pellets from Kobelco (Japan) and SiO2 1.00 1.24 Lurgi (Germany) Al2 O3 1.

  25. Slide 25: 25

    25

  26. Slide 26: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 26

  27. Slide 27: Project Infrastructure – Southdown & Albany

    Project Infrastructure – Southdown & Albany All key infrastructure in place or well advanced  Water Pit dewatering, site water harvesting, retreating Albany waste water, groundwater  Power Premier Power (Wesfarmers) (coal and natural gas potentially augmented by wind power)  Power Transmission We

  28. Slide 28: Project Infrastructure – Southdown & Albany

    Project Infrastructure – Southdown & Albany Slurry Pipeline  Optimal transport method  Finalising easements with landowners Power  Western Power Networks 220kv line from Muja (150MW capacity). No EPA Assessment  Interconnected to SWIS1  Transmission line easement progressing 1 South West Interc

  29. Slide 29: Project Infrastructure – Port of Albany

    Project Infrastructure – Port of Albany Concentrate Storage Shed & Channel to be Filter Plant dredged and widened Proposed Berth 7 (170,000 DWT vessels) Existing Berth 6 (woodchips export) • Work advancing on port design and pre-development engineering • Heads of Agreement signed with Albany Port Au

  30. Slide 30: Project Infrastructure - Kemaman

    Project Infrastructure - Kemaman All key infrastructure in place  Deep Water Port Existing Wharf at Kemaman (West Wharf) Suitable for Capesize vessels  Transport Conveyor corridor between Port and pellet plant  Power, Gas & Water Power – TNB (substation adjacent to site) Gas – Petronas, Water – m

  31. Slide 31: Project Infrastructure – Kemaman Site

    Project Infrastructure – Kemaman Site 31

  32. Slide 32: Project Infrastructure – Kemaman Port

    Project Infrastructure – Kemaman Port 32

  33. Slide 33: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 33

  34. Slide 34: Kemaman Pellet Plant – Proximity to Customers

    Kemaman Pellet Plant – Strategic Position Proximity to Customers DR PELLET CONSUMERS COUNTRY 1 Perwaja Steel Malaysia 2 Amsteel Malaysia 3 Krakatau Steel Indonesia 4 Megasteel Malaysia 5 Qasco Qatar 6 Hadeed Saudi Arabia 7 Various UAE 8 Various India BF PELLET CONSUMERS COUNTRY A China Steel Corp. T

  35. Slide 35: Kemaman Pellet Plant – Freight Advantage

    Kemaman Pellet Plant – Strategic Position Kemaman Freight Advantage Kemaman has distinct freight advantages over South American pellet producers • Close to key markets hence reduced shipping costs • Panamax size vessels can economically deliver smaller quantities to ports not able to handle capesize

  36. Slide 36: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 36

  37. Slide 37: Operating and Capital Costs

    Operating and Capital Costs Project costs are well understood and are the product of a detailed feasibility study (Note: Costs below are as at June 2007) Operating & Capital Costs US$ Operating Costs (US$/t pellets)  Southdown Mining & Processing1 35.4  Shipping to Malaysia (incl. handling) 10.6 

  38. Slide 38: Grange – Southdown/Kemaman overview

    Grange – Southdown/Kemaman overview 1 Grange Resources Limited 2 The Southdown and Kemaman Project 3 The Southdown Magnetite Deposit 4 Project Infrastructure 5 Markets 6 Economics 7 Recent Developments and Current Status 38

  39. Slide 39: Project Status

    Project Status The Southdown & Kemaman projects are well advanced with feasibility complete, most infrastructure in place and approvals in progress. Item Status Expected Timing Initial Feasibility Study  Refinement of process flowsheet work underway with Metso Minerals (Q3 2008) Kemaman Environment

  40. Slide 40: Summary of Grange's DR Pellet opportunity

    Summary of Grange’s DR Pellet opportunity An advanced Iron Ore Project for the Direct Reduction Pellet Market  Grange has the ore, the land and access to infrastructure.  Grange’s Pellets will be a premium Direct Reduction grade.  Our pellets will be sold into a niche market:  Geographically adv

  41. Slide 41: Key Contacts

    Key Contacts Russell Clark Managing Director & CEO, Grange Resources Limited Tel: +61 8 9321 1118 rclark@grangeresources.com.au 41