  1. Slide 1: Expanding, Low-Cost, Zimbabwean Gold Producer

    Expanding, Low-Cost, Zimbabwean Gold Producer December 2015 www.caledoniamining.com

  2. Slide 2: Disclaimer

    Disclaimer This presentation does not constitute, or form part of, any offer to sell or issue or any solicitation of any offer to purchase or subscribe for, any shares in Caledonia Mining Corporation (“Caledonia”), nor shall it (or any part of it) or the fact of its distribution, form the basis of,

  3. Slide 3: Caledonia Mining Overview

    Caledonia Mining Overview • 49% owned - fully indigenised Blanket Gold Mine, • 2014 production 41,771oz Zimbabwe • Low-cost: 2014 cash-cost $652/oz; AISC $969/oz • $70m, internally-funded investment 2015-2021 to increase production to 80k oz • Robust cash position: C$22.4m at September 30, 2015 Cale

  4. Slide 4: Valuation Parameters: High Yield; Low PE Ratio

    Valuation Parameters High Yield; Low PE Ratio Sources: Company Information; S&P Capital IQ • Low rating is due largely to negative perceptions about Zimbabwe • Blanket is fully indigenised and has significant, fully-funded growth plans • Investor concerns about Zimbabwe are over-done! 4

  5. Slide 5: Blanket Mine Competitive Operational Performance

    Blanket Mine Competitive Operational Performance • Caledonia compares well to other African gold producers in terms of costs • As Caledonia implements its growth strategy, Caledonia’s operational and financial performance should improve significantly – 2016 target AISC: below US$900/oz – 2018 target

  6. Slide 6: Zimbabwe Investor Concerns

    Zimbabwe Investor Concerns • Political continuity: ZANU-PF in power since 1980 Political Stability • New government is pragmatic and pro-business • No civil disorder; established, functional government administration • 51% of all businesses must be owned by Zimbabweans Indigenisation • Caledonia imp

  7. Slide 7: Capital Structure, Financials

    Capital Structure, Financials Capital Structure Shares in issue (m) 52.1 Options (m) 2.7 Cash (30 Sept 2015) C$22.4m Overdraft (30 Sept 2015) C$2.8m Net Assets (30 Sept 2015) C$67.4m Listing and Trading Share price C$0.78 Market capitalisation (C$’m) C$40.6m Summary Profit and Loss Year H1 52 week l

  8. Slide 8: Resources

    Resources 1. Tonnes are in situ Mineral Resources at August 2014 (at $1,250 gold) 2. All figures are in metric tonnes Tonnes Grade (g/t) Gold 3. Mineral Resources include Mineral Reserves (000’s) (k.oz) 4. Mineral Resources are stated at cut-off grade of 1.96g/t Measured & Indicated 4,051 3.82 498 5

  9. Slide 9: Gold Production: Revised Investment Plan Addresses Falling Production

    Gold Production Revised Investment Plan Addresses Falling Production • Quarterly production approx. 10,000 ounces per quarter compared to over 12,000 ounces per quarter in mid-2012 – Lower production due to lower grades which have fallen from a peak of 4.5g/t to 3.4g/t in Q4 2014. • Constraints on u

  10. Slide 10: The Revised Investment Plan: Improved Logistics; Accelerate Access to Deeper Resources

    The Revised Investment Plan Improved Logistics; Accelerate Access to Deeper Resources • A new Tramming Loop on 22 Level (750m below surface) increases tramming capacity (ore and waste) from 400tpd to 1,000tpd Increase Underground Material Handling • Modest cost ($0.8m approx) completed ahead of sche

  11. Slide 11: Revised Investment Plan: Improved Logistics; Accelerate Access to Deeper Resources

    Revised Investment Plan Improved Logistics; Accelerate Access to Deeper Resources Central Shaft No. 4 Shaft 22 Level No. 6 Winze (750m) Plan illustrative and not to scale 11

  12. Slide 12: Revised Investment Plan: Projected Production

    Revised Investment Plan Projected Production • Projected production in terms of the revised Life of Mine Plan is set out below • Revised Life of Mine Plan has been independently reviewed and confirmed by Minxcon, Johannesburg. • Projections exclude any production from the satellite exploration prope

  13. Slide 13: Revised Investment Plan: Capital Expenditure and Funding

    Revised Investment Plan Capital Expenditure and Funding • US$65m of capital investment 2015 to 2021 • Local debt funding increased from $2.5m to $5m • Blanket dividends suspended: cash redeployed into investment • At $1,200/oz all capex funded by internal cash generation • At the current lower gold

  14. Slide 14: Revised Investment Plan: Low-Risk Growth

    Revised Investment Plan Low-Risk Growth • Implementation parameters (e.g. daily sinking rate) based on achieved rates at other Blanket projects Not a “Stretch” plan • Allowance built in for slippage • Highly experienced management team with experience of similar projects • 97% of the capex is genera

  15. Slide 15: Revised Investment Plan: Increasing Production and Falling Costs Boost Profit

    Revised Investment Plan Increasing Production and Falling Costs Boost Profit • Strong growth in profit and cash flows ─ increasing production, falling average costs of production, reduced G&A • Robust value proposition: opportunity for rapid share price appreciation: – Increasing profit – Increasing

  16. Slide 16: Dividend Policy: Committed to Shareholder Returns

    Dividend Policy Committed to Shareholder Returns • November 2013 Caledonia announced a new dividend policy: – 2014 dividend of 6 Canadian cents – payable quarterly @1.5 cents/quarter • Total 2015 dividend cost: C$3.1m – 8x covered by cash resources • Caledonia’s Board remains committed to the mainta

  17. Slide 17: Milestones to unlocking value proposition

    Milestones to unlocking value proposition Completion of tramming loop: mid-2015  Production commences at No 6 Winze: Q1 2016 Completion of vertical Central shaft early 2018 Commence production from Central Shaft: mid-2018 Concentrating on focused optimal extraction and lower costs 17

  18. Slide 18: Contacts

    Contacts Caledonia Mining PR (UK): BlytheWeigh Website: www.caledoniamining.com Tim Blythe, Camilla Horsfell Share Codes: TSX - CAL; OTCQX – CALVF; AIM - CMCL AIM Broker/Nomad: WH Ireland Research: Edison Investment Research Mark Learmonth www.edisoninvestmentresearch.co.uk/research Tel: +27 11 447

  19. Slide 19: Other Information: Location

    Other Information: Location • Key greenstone mining district • All infrastructure in place • Skills and labour freely available • Close enough to Johannesburg for easy supply of SA- sourced supplies 19

  20. Slide 20: Blanket Gold Mine, Zimbabwe: The First Indigenised Zimbabwean Gold Miner

    Blanket Gold Mine, Zimbabwe The First Indigenised Zimbabwean Gold Miner • Indigenisation completed and implemented in Q3 2012 − 10% of Blanket donated to local community − 41% of Blanket sold to 3 parties for US$30.09 million $30m facilitation funding Caledonia − Zimbabweans given full credit for re

  21. Slide 21: Other Information: Directors and Management

    Other Information Directors and Management Management Directors Chief Executive Steve Curtis Chairman Leigh Wilson (USA) Chief Finance Officer Mark Learmonth CEO Steve Curtis (S Africa) Chief Operating Officer Dana Roets CFO Mark Learmonth (S Africa VP Exploration Dr Trevor Pearton Independent Direc