Capstone Copper Corp. · TSX:CS

Capstone Copper — Investor Presentation (March 2026)

38 slides from Capstone Copper's investor presentation, March 2026

  1. Slide 1: Corporate Update

    Corporate Update March 2026 Santo Domingo, Chile CAPSTONE COPPER CORP. | TSX:CS | ASX:CSC

  2. Slide 2: Cautionary Notes

    Cautionary Notes CAUTIONARY NOTE TO UNITED STATES INVESTORS REGARDING PRESENTATION OF MINERAL RESERVE AND MINERAL RESOURCE ESTIMATES As a British Columbia corporation and a “reporting issuer” under Canadian securities laws, we are required to provide disclosure regarding our mineral properties in ac

  3. Slide 3: Cautionary Notes

    Cautionary Notes CAUTIONARY NOTE REGARDING FORWARD LOOKING INFORMATION This document may contain “forward-looking information” within the meaning of Canadian securities legislation and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 19

  4. Slide 4: Copper in Top-Tier Jurisdictions in the Americas

    29 Cu Copper COPPER IN TOP-TIER JURISDICTIONS IN THE AMERICAS Peer-Leading Declining Best-in-Class Strong Financial Copper Growth Cash Costs Mine Build and Position Operating Team ~70% to ~375ktpa1 ~30% decrease1 +150 years of experience >$1B liquidity*,2 *Adjusted EBITDA and Available Liquidity are

  5. Slide 5: District-Scale Growth in the Americas

    District-Scale Growth in the Americas MANTOS BLANCOS (100%) Production by Region5 Producing Asset Development Stage Asset 2026E Production Open Pit 48-56 13+ year mine life kt Cu U.S. 20,000tpd mill capacity 23% +60ktpa cathode capacity3 Cu Ag Mexico PINTO VALLEY (100%) HQ, Vancouver, Canada 10% Chi

  6. Slide 6: Clear Path to Transformational Growth

    Clear Path to Transformational Growth Further organic Cu upside opportunities: • MB Phase II • SD Oxides • MV Phase II • Sierra Norte 500 $3.75 Annual Copper Production (kt) 400 ~375kt $3.00 C1 Cash Cost2 (US$/lb) ~265kt SANTO DOMINGO1 300 $2.25 225kt MV OPTIMIZED1 200 184kt $1.50 164kt MANTOVERDE1

  7. Slide 7: Executing District Growth Strategy

    Executing District Growth Strategy Transformational 2025 Sets a Strong Foundation for 2026 and Beyond 2025 Key Achievements 2026 Strategic Priorities Project Completion MV-O Execution Ramped-up projects at MV Complete construction and and MB, achieving +22% ramp-up of MV-O, delivering production gro

  8. Slide 8: Executing Key Catalysts in 2026

    Executing Key Catalysts in 2026 In alignment with our district-growth strategy Q1 Q2 Q3 Q4 MV-O CONSTRUCTION AND RAMP-UP MV PHASE II & SANTO DOMINGO/SIERRA NORTE EXPLORATION PROGRAMS MANTOS BLANCOS PHASE II STUDY SANTO DOMINGO FID Executing peer-leading copper production growth, with a focus on oper

  9. Slide 9: Balance Sheet Strength & Financial Flexibility

    Balance Sheet Strength & Financial Flexibility With Disciplined Approach to Future Growth Net Debt1 (US$M) Net Debt / TTM EBITDA* Adjusted EBITDA* Sensitivity (US$M) 3 Consol. Attr. 3.6x 2026E EBITDA 3, 4 ~$3,000 Annual EBITDA with MV-O Run-rate Production 3, 4 Cash & ST Investments $304 $249 Annual

  10. Slide 10: Balance Sheet Strength & Financial Flexibility

    Balance Sheet Strength & Financial Flexibility With Disciplined Approach to Future Growth Capstone Balance Sheet Summary (as at December 31, 2025) As at Available US$M (1) Total Facility Size Interest Tenor As at 31-Dec-25 31-Dec-25 Liquidity(4) Attributable At 31-Dec-25 Revolving Credit Facility $1

  11. Slide 11: Mantoverde

    2024/2025 Plant Throughput2 (ktpd) Mantoverde Planned maintenance 33 power 34 and Chile 35 37 Design throughput: 32 ktpd1 32 32 outage 30 30 Asset Overview 26 26 27 25 Ball and SAG mill motor issues and maintenance Location Atacama Region, Chile; ~900m above sea level 15-day 21 20 shutdown 18 for fa

  12. Slide 12: Mantos Blancos

    Mantos Blancos 2024 & 2025 Throughput1 Performance (ktpd) Asset Overview Confidence in Achieving Throughput Design Rates Location Antofagasta Region, Chile; ~900m above sea level Ownership Capstone (100%) Design throughput: 20 ktpd2 21.4 Mine Type Open Pit (operating since 1960) 21.3 Debottlenecking

  13. Slide 13: Pinto Valley

    Pinto Valley Pinto Valley (Arizona, USA) Asset Overview Pinto Valley District in Globe-Miami, Arizona Arizona (Globe-Miami), USA; Location ~1,000m above sea level Ownership Capstone (100%) Mine Type Open Pit (operating since 1975) Commodity Cu (primary), Mo/Au (secondary) Product(s) Sulphide concent

  14. Slide 14: Cozamin

    Cozamin Asset Overview Location Zacatecas, Mexico; ~2,400m above sea level Ownership Capstone (100%) Mine Type Underground (operating since 2007) Commodity Cu (primary); Ag (secondary) Product(s) Sulphide concentrate Capacity 4,400 tpd sulphide concentrator Growth Catalysts • Mine plan enables highe

  15. Slide 15: Expansion & Optionality Across the Portfolio

    Expansion & Optionality Across the Portfolio MANTOVERDE – SANTO DOMINGO DISTRICT MV-SD 35km Apart PINTO VALLEY COZAMIN MANTOS BLANCOS MANTOVERDE SANTO DOMINGO Mine Life Extension and Fully Permitted Project; Mine Life Extension and Expansion Opportunities Across our Producing Assets Expansion Opport

  16. Slide 16: Expansion & Optionality Across the Portfolio

    Expansion & Optionality Across the Portfolio Project Status MV Optimized Construction underway Near-Term +20kt copper/year incremental production1 Low capital intensity, brownfield expansion Santo Domingo Fully permitted, sanctioning +106kt copper/year incremental production2 decision expected H2 20

  17. Slide 17: Mantoverde-Optimized Key Metrics at a Glance

    Mantoverde-Optimized Key Metrics at a Glance MV-O (2024) vs. MVDP (2021) Feasibility Study Mill Feed (Mt) & Mine Life (Years) Mill Throughput (ktpd) Head Grade (%) +6 years 19 25 32 45 394Mt Incremental Mine Life 236Mt 0.49% 0.60% +$100M/yr MVDP MV-O MVDP MV-O MVDP MV-O Incremental Avg. Annual EBITD

  18. Slide 18: Mantoverde Optimized: A Capital-Efficient Brownfield Expansion

    Mantoverde Optimized A Capital-Efficient Brownfield Expansion 2024 2025 2026 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Feasibility Study $176M Approval of Long-Lead Items Initial Capex for Brownfield DIA Permit Expansion Opportunity Detailed Engineering Sanctioning Construction & Tie-Ins (~15 days Q3/26)

  19. Slide 19: Santo Domingo Key Metrics at a Glance

    Key Metrics at a Glance - July 2024 Feasibility Study Santo Domingo 29 Cu Copper 19 Year 106kt $0.28/lb Mine Life Avg. Annual C1 Cash Costs2 Asset Overview Cu Production2 (by-product basis) Location Atacama Region, Chile; low elevation at ~1,000m above sea level 1 Ownership Capstone (75%), Orion Res

  20. Slide 20: Santo Domingo Path Forward

    Santo Domingo Path Forward Advancing Remaining Workstreams in Parallel In Progress: Completed: In Progress: Engineering & 2 Study Balance Sheet Optimization Published updated Targeting <1.0x net debt to Progress detailed engineering; Feasibility Study for EBITDA3 leverage and pursue incremental copp

  21. Slide 21: Santo Domingo Illustrative Funding Structure

    Santo Domingo Illustrative Funding Structure Prudent Approach to Capital Allocation in Pursuit of Transformational Growth $2.3Bn1 $1.2Bn2 Capstone Q4 2025 Balance Sheet Summary4 Remaining Funding Requirement  Consolidated Net Debt5 of $780M Capstone portion of remaining funding  0.8x Net Debt / LT

  22. Slide 22: Achieving District Scale Optimization in the MV-SD District

    Achieving District Scale Optimization in the MV-SD District Unlocking a New World-Class Copper District with Additional Value Through Upside Opportunities Targeting +250,000 tonnes per year of low-cost copper production with a significant by-product of premium grade iron ore, with the potential to b

  23. Slide 23: MB Phase II Study

    MB Phase II Study Opportunity Highlights Stage / Impact • Controlled Potential Sulphidation (CPS) • Flotation activator for copper oxides in sulphide • At 20ktpd throughput, opportunity to Continuous circuit expand sulphide Cu production by Improvements • Energy Efficient Pulp Lifter (EEPL) Conversi

  24. Slide 24: Enhancing the Pipeline Through Exploration

    Enhancing the Pipeline Through Exploration MANTOVERDE – SANTO DOMINGO DISTRICT MV-SD 35km Apart SANTO DOMINGO + PINTO VALLEY COZAMIN MANTOS BLANCOS MANTOVERDE SIERRA NORTE Mala Noche Vein SR Gap MNFWZ – Vein 20 MNV West MNFWZ Deep District Growth Study Mine Life Extension Near-Mine Exploration Near-

  25. Slide 25: MV-SD: Exploration Program

    MV-SD: Exploration Program Mantoverde Initial Two-Year $25M Exploration Mantoverde & Santo Domingo District1 Program Sierra Norte • Targeting higher copper grades 6 5 N • Exploring new areas adjacent or inside the current Mantoverde pits 4 • Testing high priority targets in the northern area of Nort

  26. Slide 26: MV Initial Two-Year Exploration Program

    MV Initial Two-Year Exploration Program Results from Phase 1 Overview of Phase 11: Highlights from Initial Results: 30,000-metres of drilling focused on areas • Higher than expected grades in Brecha Flores sector, where drill intercepts returned copper grades above those predicted adjacent to MV-O P

  27. Slide 27: Santo Domingo and Sierra Norte Exploration Program

    Santo Domingo and Sierra Norte Exploration Program Santo Domingo Exploration Potential IOCG type of mineralization with copper, gold, iron and cobalt ~340Mt of sulphide resource not included into reserves Key programs include:  54,700 metre drill program at Opportunity to define an oxide resource i

  28. Slide 28: Three “Geo’s” Constraining Copper Supply Growth…

    Three “Geo’s” Constraining Copper Supply Growth… LME copper prices gained +40% over 2025, the highest annual increase since 2009 • Declining Cu grades • More complex mining • Security of supply • Lack of new copper methods (deeper • Rising geopolitical discoveries underground mines, tensions • Lack

  29. Slide 29: …While New Sources of Copper Demand Emerge

    …While New Sources of Copper Demand Emerge Robust “traditional” demand amplified by emerging global trends • Population growth • Renewable power • AI & data centres • Urbanization • Electric vehicles • Onshoring of supply • Industrialization • Industry electrification chains • Increasing living • Gr

  30. Slide 30: Capstone Copper – Capital Structure

    Capstone Copper – Capital Structure Share Metrics Analyst Coverage Total Shares Outstanding1 764 million Barrenjoey J.P. Morgan Total Shares Outstanding (Fully Diluted)1 770 million Bradesco BBI Macquarie Shares Held as ASX CDIs2 174 million BMO Capital Markets Moelis & Company Market Cap3 US$6.5Bn

  31. Slide 31: Copper in Top-Tier Jurisdictions in the Americas

    29 Cu Copper COPPER IN TOP-TIER JURISDICTIONS IN THE AMERICAS Peer-Leading Declining Best-in-Class Strong Financial Copper Growth Cash Costs Mine Build and Position Operating Team ~70% to ~375ktpa1 ~30% decrease1 +150 years of experience >$1B liquidity*,2 *Adjusted EBITDA and Available Liquidity are

  32. Slide 32: 2025 Actuals: Record Results from a Diversified Portfolio

    2025 Actuals: Record Results from a Diversified Portfolio Q1 2025 Q2 2025 Q3 2025 Q4 2025 Quarterly Copper Production (kt) and Cu C1 Cash Cu C1 Cash Cu C1 Cash Cu C1 Cash C1 Cash Costs (US$/lb) 1 Production Costs1 Production Costs1 Production Costs1 Production Costs1 (tonnes) (US$/lb Cu) (tonnes) (U

  33. Slide 33: 2022-2025: Executing Transformational Growth

    2022-2025: Executing Transformational Growth 2022 2023 2024 2025 Annual Copper Production (kt) and Cu C1 Cash Cu C1 Cash Cu C1 Cash Cu C1 Cash C1 Cash Costs (US$/lb) 1 Production Costs1 Production Costs1 Production Costs1 Production Costs1 250 $3.00 (tonnes) (US$/lb Cu) (tonnes) (US$/lb Cu) (tonnes)

  34. Slide 34: 2026 Production, Cost and Capital Guidance

    2026 Production, Cost and Capital Guidance Delivering reliable results from a portfolio of long-life assets in top-tier jurisdictions FY 2026 FY 2026 Cu Production C1 Cash Costs1 Sustaining Capital Expansionary Capital Capital Stripping Total (kt) (US$/lb Cu) (US$M) (US$M) (US$M) (US$M) Sulphide Bus

  35. Slide 35: Consolidated Estimated Mineral Resources

    Consolidated Estimated Mineral Resources MINERAL RESOURCES – Inclusive of Mineral Reserves CONTAINED METAL NOTES: Mineral Resources take into account mining activities to the effective date, where applicable and are reported insitu, using the 2014 CIM Definition Standards. Mineral Resources that are

  36. Slide 36: Consolidated Estimated Mineral Reserves

    Consolidated Estimated Mineral Reserves NOTES: Mineral Reserves take into account mining activities as stated, where applicable. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content. Grade TCu% refers to total cop

  37. Slide 37: Sierra Norte

    Sierra Norte Historical Mineral Resources Notes: Category Tonnes (Mt) CuT % CuS % Copper (kt) The Historical Mineral Resource was derived from the report “Actualización del Modelo Geológico y de la Estimación de Recursos Minerales del Proyecto Diego de Almagro” completed by Amec Foster Carmen-Paulin

  38. Slide 38: General Enquiries

    GENERAL ENQUIRIES Capstone Copper Corp. 2100 – 510 West Georgia Street Vancouver, BC - V6B 0M9 Capstonecopper.com info@capstonecopper.com +1-604-684-8894 Toll-free NA 1-866-684-8894 MEDIA & INVESTOR ENQUIRIES Daniel Sampieri, Vice President, Investor Relations +1-437-788-1767, Toronto, ON Michael Sl

Capstone Copper — Investor Presentation (March 2026) on 6ix