Darcy Partners Forum Houston March 8th 2017 Eric Laing, Geoff Steele
Slide 2: Quote on change and innovation
Without change there is no innovation, creativity, or incentive for improvement. Those who initiate change will have a better opportunity to manage the change that is inevitable. William Pollard
Slide 3: Horizontal Well Flow
Horizontal Well Flow THE PROBLEM: After initial flush production from a newly fractured well bore, all wells exhibit the same pattern of significant declines in the first 6-24 months. THE CAUSE: Frac pressures are multiples of formation pressure- once Frac pressure is dissipated, it is back to natur
Slide 4: Regional Production Decline Rates
Regional Production Decline Rates Permian Eagle Ford Bakken
Slide 5: Production Equipment-Best Practices
Production Equipment-Best Practices Production equipment landed in close proximity to perforation intervals ENSURES: Regulated drawdown Lift equipment longevity and efficiency Predictable decline rates Prevention of near wellbore liquid loading
Slide 6: The Challenge of Evolving Wellbore Flow
The Challenge of Evolving Wellbore Flow Vertical flow is well understood and we can control the regimes as the well ages and flowing pressures decrease. HOWEVER, Why do we think that placing an artificial lift system at the heel, or close to the heel, in a horizontal well bore will provide the same,
Slide 7: Solution: Divide The Wellbore
Solution: Divide The Wellbore Divide the well bore into Vertical and Horizontal flow scenarios that can be controlled. Evolutionary - Patent pending High Angle Rod Pump (Well Specific) Revolutionary - Patented Horizontal Pumping System (Broad Applications) Multiple pumps placed along the length of t
Slide 8: The RAISE High Angle Rod Pump – An Evolutionary Solution
The RAISE High Angle Rod Pump – An Evolutionary Solution OPTIONAL TOP VALVE UPPER BARREL INTAKE PLUNGER TRAVELLING VALVE PLUNGERS & LOWER BARREL TRAVELLING INTAKE VALVES
Slide 9: The RAISE High Angle Rod Pump – An Evolutionary Solution
The RAISE High Angle Rod Pump – An Evolutionary Solution Eliminates gas lock Eliminates requirement for separation Low SPM minimizes tubing and rod wear
Slide 10: Latest High Angle Rod Pump Installation
Latest High Angle Rod Pump Installation “We are up to ~12 m3/d fluid, ~65% BSW, ~10 e3m3/d gas. With the 1.5” pump @3.5 spm we are around 70% pump efficiency which is amazing for a high GOR HZ well with no gas separator. I realize that this may be flush as it was down a long time but to put it in pe
Slide 11: No existing vertical pump technologies address horizontal flow
There are no existing vertical pump technologies that completely address the flow issues along the entire horizontal section - material volumes of oil & gas reserves are being left behind.
Slide 12: The RAISE Horizontal Pumping System – A Revolutionary Solution
The RAISE Horizontal Pumping System – A Revolutionary Solution In test wells that had produced for over 6 years, the Raise Horizontal Pumping System deployments have shown the following: System is robust & can be run and retrieved without issue Recovery of high water cut fluids (Frac water present)
Slide 13: Multiple Deployments
Multiple Deployments Horizontal Pumping System deployed and retrieved in close tolerance wellbores (4 ½ inch mono bore) Raise has proven through field testing : Pumps rated up to 5000psi working pressure Reliable Activation Optimum Pump placement Multiphase flow knowledge
Slide 14: Future Architecture
Future Architecture Wells drilled longer and trajectory targeting high porosity areas (pumps evacuate troughs) Frac placement at high perm areas Larger cased hole size to accommodate production tools Life of the well consideration during well planning Lift solutions installed at correct stage of dra