Slide 1: 2026 Annual General Meeting Chairman's Address and Presentation
For personal use only 27 November 2026 2026 ANNUAL GENERAL MEETING CHAIRMAN’S ADDRESS AND PRESENTATION Fenix Resources Limited (ASX: FEX) (Fenix or the Company) is pleased to provide a copy of the Chairman’s address and presentation which will be delivered to shareholders at the Fenix Annual General

Slide 2: Chairman's Address to the 2026 Annual General Meeting
2026 AGM Chairman’s Address | 27 November 2026 CHAIRMAN'S ADDRESS TO THE 2026 ANNUAL GENERAL MEETING For personal use only Dear Fellow Shareholders, Good morning and welcome to the Fenix 2026 Annual General Meeting. It is a pleasure to be here with you today. 2026 has been a transformative and defin

Slide 3: Progress on Growth Projects
2026 AGM Chairman’s Address | 27 November 2026 Progress on Growth Projects Several recent operational milestones support the Company's strategic vision: For personal use only • All key approvals were received for the new Beebyn-W10 mine, with mining now underway and the Beebyn Hub now established as

Slide 4: A Personal Reflection
2026 AGM Chairman’s Address | 27 November 2026 A Personal Reflection In my 2025 AGM address, I promised that the best is yet to come. I hope in reviewing our FY26 For personal use only Annual Report and today’s presentation, you can recognise the progress Fenix is making towards achieving our ambiti

Slide 5: 2026 Annual General Meeting Executive Chairman's address
rsonal use only 2026 Annual General Meeting Executive Chairman's address ASX: FEX John Welborn | 27 November 2026

Slide 6: Important information: Forward-looking statements and disclaimer
Important information Forward-looking statements and disclaimer rsonal use only Disclaimer The material in this presentation has been prepared by Fenix Resources Ltd (“Fenix”, “Fenix Resources” or “the Company”) and is general background information on Fenix. This information is given in summary for

Slide 7: FY26 results
FY26 results Year ended 30 June 2026 rsonal use only 83% 87% SHIPMENTS REVENUE To 4.4Mt To A$589.7m 33% 49% OPERATING CASH FLOW EBITDA To A$95.9m To A$80.7m Source: FY26 full-year results, released to ASX 26 August 2026. ASX: FEX | 3

Slide 8: Fenix delivers
Fenix delivers What we have done, year by year rsonal use only FY20 Iron Ridge Feasibility Study: production of 1.25Mtpa, 6 year mine life, expected C1 cash costs of A$77/t FY21 Raised A$15m in equity, built and commissioned Iron Ridge at 1.25Mtpa, paid dividend of 5.25c/sh FY22 1.3Mt shipped in 23

Slide 9: More tonnes. Lower costs. Delivered.
More tonnes. Lower costs. Delivered. Production more than tripled. Costs down 17%. rsonal use only 6 90 88 5 86 C1 cash cost (A$/wmt FOB) 84 Iron ore shipments (wmt) 4 82 3 80 78 2 76 74 1 72 0 70 FY22 FY23 FY24 FY25 FY26 FY27 Guidance Iron ore shipments (wmt) C1 cash cost (A$/wmt FOB) Refer to the

Slide 10: Costs up everywhere in iron ore. Except here.
Costs up everywhere in iron ore. Except here. Percentage change in reported unit costs (A$) 100.0% rsonal use only 80.0% 60.0% BHP Rio Tinto Change in unit cost (%) 40.0% Fortescue Vale Kumba 20.0% Anglo Minas-Rio Fenix 0.0% MinRes 1H21 2H21 1H22 2H22 1H23 2H23 1H24 2H24 1H25 2H25 1H26 -20.0% -40.0%

Slide 11: Dividends since commencement of production
Dividends since commencement of production Cumulative fully franked dividends paid to shareholders rsonal use only A$100,000,000 A$80,000,000 DIVIDENDS PAID A$60,000,000 A$81.5m Fully franked, dividends paid to shareholders since production commenced in December 2020 A$40,000,000 Paid as the busines

Slide 12: Our Values
Our Values rsonal use only Simplicity We save time by keeping it simple Team Thinking We work best when we work together and take responsibility for our actions Honesty We are direct and accurate in our work Proactive Forward Thinking We challenge ourselves to embrace change and always look to how w

Slide 13: FY27 focus for Fenix
FY27 focus for Fenix rsonal use only Safety Production Costs 3.9 4.7 to 5.3Mt A$70 to 80/wmt TRIFR at 30 September 2026 FY27 total iron ore sales guidance FY27 C1 cash cost guidance 20% lower than 4.9 at 30 5Mtpa Beebyn Hub plant Held at FY26 levels despite June 2026 commissioned, full ramp-up in hi

Slide 14: Appendix 1. Beebyn Hub Ore Reserve
APPENDIX 1. BEEBYN HUB ORE RESERVE rsonal use only Maiden Beebyn Hub Ore Reserve (Beebyn-W11 and Beebyn-W10 Stage 1) – 57% Fe cut-off applied Fe SiO2 Al2O3 LOI P S JORC Classification Tonnes (Mt) % % % % % % Proved 23.4 59.90 4.47 2.78 4.39 0.08 0.02 Probable 3.5 60.64 4.58 2.90 3.20 0.08 0.02 Total

Slide 15: Appendix 2. Reported C1 Cash Costs - Data
APPENDIX 2. REPORTED C1 CASH COSTS - DATA rsonal use only Period BHP Rio Tinto Fortescue Vale Kumba Anglo Minas-Rio Fenix MinRes 1H21 7.5% 5.8% -1.9% -16.3% 18.2% -0.7% 0.0% 0.0% 2H21 19.6% 25.5% 4.4% -5.1% 18.0% 23.7% 2.1% 3.8% 1H22 32.1% 38.5% 15.1% 5.9% 36.6% 69.7% -1.9% 12.2% 2H22 47.0% 46.0% 29

Slide 16: Appendix 3. Reported C1 Cash Costs - References
APPENDIX 3. REPORTED C1 CASH COSTS - REFERENCES Release Title and Date Company Company Data Source 1H21 2H21 1H22 2H22 1H23 2H23 1H24 2H24 1H25 2H25 1H26 Half Yearly Half Yearly Report Half Yearly Appendix 4E and Half Yearly BHP Appendix Half Year 2025 BHP Appendix 4E https://www.bhp.com/investor- r

Slide 17: Contact
rsonal use only CONTACT | ASX: FEX John Welborn Executive Chairman info@fenixresources.com.au

Slide 18: Forward Looking Statements
Forward Looking Statements The Chairman’s Address may include forward-looking statements. Forward-looking statements are only predictions and are subject to risks, uncertainties and assumptions which are outside the control of the Company. Actual values, results or events may be materially different

Slide 19: About Fenix Resources Ltd
For personal use only Fenix Resources Ltd (ASX: FEX) is a fully integrated mining, logistics and port services business with a current annual production rate of more than 5 million tonnes of iron ore and an identified pathway to long-term production of 10Mtpa. Fenix currently operates three iron ore
Source: ASX announcement, Nov 27, 2026
More decks from Fenix Resources Limited
Investor Presentation (August 2026)20 slides · Aug 4, 2026
Noosa Mining Investor Conference 202623 slides · Jul 22, 2026
RIU Sydney Resources Round-Up Conference 202624 slides · May 2026
Investor Presentation (April 2026)21 slides · April 2026
Q2 2026 Earnings Presentation23 slides · Feb 26, 2026
Noosa Mining Conference 202513 slides · July 2025