  1. Slide 1: BUA Cement Plc: Sustaining Value and Competitiveness

    BUA CEMENT PLC Sustaining Value and Competitiveness Full Year 2020 Presentation to Investors and Analysts 1

  2. Slide 2: Disclaimer

    Disclaimer Unless otherwise indicated, the financial information provided herein has been prepared under International Financial Reporting Standards (IFRS). This presentation contains forward-looking statements and information. Forward-looking statements and information are statements that are not h

  3. Slide 3: BUA Cement and Sokoto Cement are products of BUA Cement PLC

    *BUA Cement and Sokoto Cement are products of BUA Cement PLC. 3

  4. Slide 4: Contents

    CONTENTS Our Corporate Philosophy 05 Operational Highlights 06 Financial Highlights 10 Strategic Priorities 16 Sustainability 21 Appendix 24 4

  5. Slide 5: Our Philosophy, Vision, Mission and Value Proposition

    Our Philosophy Our Vision Our Mission Our Value Proposition To be a highly competitive To produce and market high We are a professional supplier of premum market leader in Nigeria quality cement for national brand cement and provide reliable delivery development to our customers with application tra

  6. Slide 6: Company Overview

    Company Overview Largest Cement producer 1 in the North-West, South-South and South East 2 Modern lines 2 Operational across two States N2.6 trillion 3 Market capitalisation as at Dec. 2020 >60 per cent 4 Capacity utilisation attained N209.4 billion (FY2020) 5 Revenue 5.1 mmt (FY2020) 6 Cement volum

  7. Slide 7: Flawless Execution, Disciplined Approach

    Flawless Execution, Disciplined Approach Incorporation of CCNN; Commissions its 0.5mmt Listed on the Nigeria Stock FGN divests its majority Scancem divests its majority commences operation in 1967 (Line-2), with the Exchange (NSE), resulting holding to Scancem holding to Damnaz Cement with an instal

  8. Slide 8: Strategic Positioning, Increasing Market Presence

    Strategic Positioning, Increasing Market Presence Sokoto Plant Sokoto State Line 1 500,000MTPA Line 2 1.5MMTPA Line 3 3MMTPA (2021) BUA Cement Plc Obu Plant Head Office Edo State Victoria Island, Lagos, Nigeria Line 1 3MMTPA Line 2 3MMTPA 8

  9. Slide 9: Obu Plants

    OBU PLANTS OBU PLANT (LINES 1 & 2) LOCATION PRODUCTION CAPACITY COMPLETION DATE Okpella, Edo State Line 1 – 3million mtpa 2015 – Obu Cement Line 1 South-South Nigeria Line 2 – 3million mtpa 2019 – Obu Cement Line 2 9

  10. Slide 10: Highlights from 2020 – We Continue to Deliver Value

    Highlights from 2020 – We Continue to Deliver Value PERFORMANCE 1 Resilient performance driven by superior product quality, with a well instituted Business Continuity Plan (BCP). EBITDA 2 PROFITABILITY 3 EPS 4 EBITDA increases by 18.0% to N96.8 billion, Profit before Tax (PBT) and Profit after Tax E

  11. Slide 11: Uncertain and Challenging Macro Economic Environment

    Uncertain and Challenging Macro Economic Environment Oil Price GDP Foreign Movement Growth Exchange Oil price down GDP growth Naira depreciated by 21.5% (y/y) to contracted by 12.6% from N364.5/$, $51.8/bbl. (Dec. 1.9% in 2020, as at Dec. 2019 to 2020) amid the having expanded N410.2/$, as at Dec. g

  12. Slide 12: Resilient Performance Built on Readiness

    Resilient Performance Built on Readiness 1 Revenue per ton (N’000) 2 EBITDA (N‘bn) 3 EBITDA Margin 41.1 96.8 39 82 46.7% 46.2% 2019 2020 2019 2020 2019 2020 • Revenue per ton rose by 5.3% to N41,066/ton, as at FY2020 from N38,995/ton, as at FY2019; due to lifting bonus adjustment and increased volum

  13. Slide 13: Rising Sales Volume Drives EBITDA

    Rising Sales Volume Drives EBITDA (Δ;y/y) EBITDA (2020) 96.8 Depreciation 1.4 SD&A (net) 0.4 Cost of sales (20.9) Revenue 33.9 EBITDA (2019) 82.0 (50) (20) 10 40 70 100 N’billions • Revenue during the year was up 19.3% to N209.4 billion, as at FY2020 from N175.5 billion, as at FY2019, driven by incr

  14. Slide 14: Balancing Cost Containment with Investment in Route-to-Market Strategy

    Balancing Cost Containment with Investment in Route-to-Market Strategy Cost of sales Energy cost Dist. & sell. cost per ton (N‘000) per ton (N‘000) per ton (N‘000) 22.3 20.6 0.96 0.95 8.1 8.4 2019 2020 2019 2020 2019 2020 • Cost of sales/ton recorded an 8.1% increase to N22,345/ton, as at FY2020 fro

  15. Slide 15: Sokoto Plants

    SOKOTO PLANTS SOKOTO PLANT (LINE 3) LOCATION PRODUCTION CAPACITY COMPLETION DATE Kalambaina, Sokoto New Line 3 – 3million mtpa 2021 (North-West, Nigeria) 15

  16. Slide 16: In Pursuit of Value Creating Priorities

    In Pursuit of Value Creating Priorities Priority Activity Status Areas • Drive revenue and cost synergies across revenue and margin lines Synergy • Continue hamonisation of sales and marketing strategy across the two plants • Increase customer on-boarding in new locations New Markets • Pursue steady

  17. Slide 17: Projects, Cost and Funding

    Projects, Cost and Funding Projects Project Cost Funding Sources  Guyuk, Adamawa State Estimated cost for all three  Series II Bond Issue  Obu, Edo State (3) plants is $1.1 billion  Internally generated  Kalambaina, Sokoto State sources …adopting an approach that further enhances value 17

  18. Slide 18: Investing for Competitiveness and Development

    Investing for Competitiveness and Development The intended expansion at Our entry into Adamawa State, Obu, Edo State will be a OBU Line 3 Adamawa North-East Nigeria will see the brownfield 3mmtpa plant, Line 1 construction of a greenfield commencing in 2021. Thus, plant with an annual capacity bring

  19. Slide 19: Well Positioned to Lead Export Drive

    Well Positioned to Lead Export Drive The commencement of AfCFTA provides Comments enormous upside for export activities • West Africa to witness rising Large clinker urbanization rates. This we imports from observe through: outside Africa  The % of population living in urban areas, which rose from

  20. Slide 20: BUA Cement (Sokoto)

    BUA Cement (Sokoto) Line 3 under construction 20

  21. Slide 21: Leading Through Sustainability

    Leading Through Sustainability CO2 Emission Dust Emission (KgCO2/TCEM) (Mg/M3) 504 2021 502 15 2021 13 Water Usage & Energy Efficiency Conservation (Kcal/kg) (M3/DAY) 154 2021 157 754 2021 752 Inserted picture: New, sustainable and resilient community development at Sabon Garin Gidam Bailu, Sokoto S

  22. Slide 22: Making Positive Changes

    Making Positive Changes Top: BUA Specialist Care Centre, Kano, a 200-bed special care facility for COVID. Bottom left to right: COVID-19 Food Outreach across Nigeria; Donation of over 65 Ambulances and 25 Sport Utility Vehicles (SUV) to State …through impactful CSR, everywhere we go Governments acro

  23. Slide 23: BUA Cement Plant Sokoto

    BUA CEMENT PLANT SOKOTO KEY FACTS 82MW Captive Power plant High Capacity Coal mill, multi-fuel Cement plant Location Kalambaina, Sokoto (North-West Nigeria) Production Capacity Line 1– 500,000mtpa Line 2– 1.5mmtpa New Line 3– 3mmtpa Completion Date 1985 2018 2021 Line-1 Line-2 Line-3 23

  24. Slide 24: Appendix

    APPENDIX 24

  25. Slide 25: Board of Directors

    Board of Directors ABDULSAMAD RABIU YUSUF BINJI JACQUES PIEKARSKI CHIMAOBI MADUKWE Chairman Managing Director/CEO Executive Director/CFO Non-Executive Director Abdul Samad Rabiu, CON., is Yusuf Haliru Binji is the Jacques Piekarski is a Chimaobi Madukwe is a Non- the Chairman of BUA Cement Managing

  26. Slide 26: Board of Directors

    Board of Directors KABIRU RABIU FINN ARNOLDSEN KHAIRAT A. GWADABE SHEHU ABUBAKAR Non-Executive Director Non-Executive Director Independent Non-Executive Independent Non-Executive Director Director Kabiru Rabiu is a Non-Executive Finn Arnoldsen, Norwegian, is a Senator Khairat Abdulrazaq- Shehu Abuba

  27. Slide 27: Thank You

    Thank You www.buacement.com 5th Floor, BUA Towers PC 32, Churchgate Street Victoria Island, Lagos, Nigeria Email: investor.relations@buacement.com 27