Lynas Rare Earths Limited · ASX:LYC

Lynas Rare Earths — Lynas — The 6th International Rare Earth Conference, Hong Kong 2010

28 slides from Lynas Rare Earths's conference presentation, Nov 10, 2010

  1. Slide 1: Hong Kong Rare Earths Conference Presentation cover note

    Corporate Office Telephone: +61 2 8259 7100 Level 7 Facsimile: +61 2 8259 7199 56 Pitt Street Website: www.lynascorp.com Sydney NSW 2000 ACN: 009 066 648 AUSTRALIA For personal use only 10 November 2010 Hong Kong Rare Earths Conference Presentation 10 November 2010 Enclosed is an amended copy of the

  2. Slide 2: The Lynas Story

    The Lynas Story For personal use only THE 6TH INTERNATIONAL RARE EARTH CONFERENCE Hong Kong 9-11 November 2010

  3. Slide 3: Disclaimer

    Disclaimer For personal use only • The release, publication or distribution of this presentation in certain jurisdictions may be restricted by law and therefore persons in such jurisdictions into which this presentation is released, published or distributed should inform themselves about and observe

  4. Slide 4: Prices are returning to historic levels

    Prices are returning g to historic levels For personal use only HISTORIC SUPPLY, DEMAND AND PRICING Tonnes REO US$/Kg US$61.96/kg 8 Nov 2010 US Inflation adjusted Actual Price 3

  5. Slide 5: Limited price drop in 2009 to Chinese cash cost of production

    Limited price drop in 2009 to Chinese cash cost For personal use only of production PRICE DRIVERS 2009 Tonnes REO US$/Kg • Demand sharply dropped due to the GFC • Limited price drop to Chinese cash cost of p production 4

  6. Slide 6: The shortage of Rare Earths has the world currently thirsting for these vital elements

    The shortage of Rare Earths has the world For personal use only currently thirsting for these vital elements PRICE DRIVERS 2010 Tonnes REO US$/Kg • Consolidation of production and marketing channels • Chinese policies restricted supply • Demand recovering strongly • Prices starting to grow inside Ch

  7. Slide 7: Future outlook – structural change in industry has commenced

    Future outlook – structural change in industry has For personal use only commenced FUTURE PRICE DRIVERS Supply vs Demand Other impacts on cash costs: • Wage increases • Energy and Chemical cost increase • China CPI • Environmental operating costs including energy and chemicals $4 to $6 per kg • Cons

  8. Slide 8: Lynas will offer the first new source of supply of Rare Earths outside of China - Q3 2011

    Lynas will offer the first new source of supply of Rare Earths outside of China - Q3 2011 For personal use only LYNAS VITALS AT A GLANCE VISION: To be a global leader in Rare Earths for a sustainable future Mount Weld EXCHANGE: ASX Top 200 Company; code LYC SHARES: 1,657m on issue OPTIONS: 78m strik

  9. Slide 9: Lynas is on track for production in Q3 2011

    Lynas y is on track for p production in Q3 2011 For personal use only KEY MILESTONES TO ENSURE A RELIABLE SOURCE OF RARE EARTHS • Lynas raised A$450 million in the equity markets to fund the completion of its project • All approvals in Australia and Malaysia in place to complete construction of proc

  10. Slide 10: 15% more resources in Mount Weld; New Total Resource of 1.4 million tonnes of REO

    As at September 2010, 15% more resources in The current mining operation is within the Mount Weld; New Total Resource of 1.4 million Central Zone Pit For personal use only tonnes of REO CENTRAL LANTHANIDE DEPOSIT AND DUNCAN DEPOSIT RESOURCES Central Lanthanide Deposit & CLD & Duncan Mineral Resource

  11. Slide 11: Mount Weld Rare Earths initial mining campaign complete, loss time injury free

    Mount Weld Rare Earths initial mining campaign complete loss-time-injury-free complete, loss time injury free For personal use only MOUNT WELD STOCKPILES WITH RARE EARTH OXIDE PERCENTAGES DUNCAN DEPOSIT (DD) Offi Offices 773,000t on stockpiles 8% 13% DD CLD 17% DEPOSIT 26% 15% 13% 21% 20% Conc. DD P

  12. Slide 12: Schematic - Concentration Plant process at Mount Weld

    Schematic - Concentration Plant process at Mount Weld which has been fully pilot plant tested Weld, For personal use only 11

  13. Slide 13: Commissioning of the Concentration Plant is on schedule for February 2011

    Commissioning of the Concentration Plant is on schedule for February 2011 For personal use only CONSTRUCTION AT THE CONCENTRATION PLANT Flotation section under construction 12

  14. Slide 14: Commissioning of the Concentration Plant is on schedule for February 2011

    Commissioning of the Concentration Plant is on schedule for February 2011 For personal use only CONSTRUCTION AT THE CONCENTRATION PLANT Flotation building Concentration thickener and packing area 13

  15. Slide 15: Commissioning of the Concentration Plant is on schedule for February 2011

    Commissioning of the Concentration Plant is on schedule for February 2011 For personal use only CONSTRUCTION AT THE CONCENTRATION PLANT Ball mill being installed 14

  16. Slide 16: Containers of Rare Earths concentrate will be trucked to Fremantle for shipping to Malaysia

    Containers of Rare Earths concentrate will be trucked to Fremantle for shipping to Malaysia For personal use only • Mount Weld to Fremantle = 1000km • Transportation approx. 9% of total costs 15

  17. Slide 17: Lynas will expand the Malaysian processing hub

    Lynas will expand the Malaysian processing hub, with the ability to take multiple sources of For personal use only material PROCESSING HUB WITH EXCEPTIONAL INFRASTRUCTURE Gebeng Industrial Estate, INDUSTRIAL INFRASTRUCTURE East Coast Malaysia KNOWLEDGE INFRASTRUCTURE GOVERNMENT INFRASTRUCTURE ¾ Incl

  18. Slide 18: Schematic - Lynas Advanced Materials Plant core process

    Schematic - Lynas Advanced Materials Plant core process which uses mature industry technology process, For personal use only 17

  19. Slide 19: Lynas Advanced Materials Plant

    Lynas Advanced Materials Plant For personal use only Phase 1 : 11,000t REO Phase 2 : 22,000t REO -18-

  20. Slide 20: First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011

    First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011 For personal use only FEATURES OF CONSTRUCTION AT THE LAMP Prefabricated Bluescope steel buildings Working on the foundations at the LAMP 19

  21. Slide 21: First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011

    First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011 For personal use only FEATURES OF CONSTRUCTION AT THE LAMP Lynas-constructed stormwater detention pond Concrete Batch Plants 20

  22. Slide 22: First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011

    First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011 For personal use only CONSTRUCTION AT THE LAMP Foundation works and steel reinforcement in place ready for further concrete pours 21

  23. Slide 23: First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011

    First feed to kiln at the Lynas Advanced Materials Plant is scheduled for Q3 2011 For personal use only CONSTRUCTION AT THE LAMP Rotary kilns foundations Rotary kilns bodies 22

  24. Slide 24: Time and expertise are vital for the effective execution of a Rare Earths project

    Time and expertise are vital for the effective execution of a Rare Earths project For personal use only MAN HOURS TO COMPLETE OUR LYNAS ADVANCED MATERIALS PLANT 4,000,000 1 000 000 1,000,000 900,000 800,000 700,000 600,000 500,000 300,000 280,000 400,000 300,000 200,000 40,000 100,000 0 Engineering

  25. Slide 25: We are industrialising our operations to meet our customers' expectations

    We are industrialising our operations to meet our customers’ expectations customers For personal use only FOUR PILLARS UNDERPINNING LYNAS’ OPERATIONS Marketing and Sales • Serving long-term customer requirements and commitments, and thus providing input for plant extensions and new facilities. Indus

  26. Slide 26: Eight customer agreements have been signed

    Eight customer agreements have been signed For personal use only Rhodia Customer Agreement - Supply Contract • >US$200M¹ 8th Customer Agreement – Supply Contract • Long L term t 10 year contract, t t Phase Ph I • Long term contract • Cerium, Europium, Terbium & Lanthanum • Product from Phase I & II

  27. Slide 27: Lynas – online in 2011, delivering Rare Earths globally

    Lynas – online in 2011, delivering Rare Earths globally For personal use only Our vision is to be a global leader in Rare Earths for a sustainable future. We are close to realising this vision. Lynas will be online in 2011, delivering Rare Earths globally. This is the first new production outside of

  28. Slide 28: Note – Competent Person statement

    NOTE For personal use only The information in this report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by Brendan S Shand, who is a member off The Australasian Institute off Mining and Metallurgy. Brendan Shand is an employee of Lynas Corpor

Lynas — The 6th International Rare Earth Conference, Hong Kong 2010 on 6ix