  1. Slide 1: Agency Consultation Meeting

    Agency Consultation Meeting Oakdale West Industrial Estate September 2021 1

  2. Slide 2: Overview

    Overview Welcome and Introductions Upcoming Developments Project Update – OWIE Project Update – Buildings 1A, 1B, 1C & 2B CEMP Consultation – Buildings 3B & 4E Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Dan Thompson Carl Vincent Kym Dracopoulos Kate McKinnon Alasdair Cameron Kiera Plumridge Lachlan O’Reilly Luke Ridley

  4. Slide 4: Oakdale West Estate - MOD 7 Estate Masterplan

    [REFER TO DRAWING OAK MPC3 FOR CONTINUATION PRELIMINARY. Oakdale West Estate - MOD 7 Estate Masterplan ( global environmental and advisory solutions S | Re —

  5. Slide 5: Upcoming Developments

    Upcoming Developments • Current Development Application and Modification Status – SSD 7348 Modification 7 – Changes to Precinct 3 and Precinct 4; – SSD 7348 Modification 8 – Modifications to Warehouses 1A, 1B & 1C; – SSD 22191322 – Building 4E Development – Due to commence Oct / Nov 21; Building 4E

  6. Slide 6: Progress To Date & Upcoming Works - OWIE

    Progress To Date & Upcoming Works - OWIE • Progress to Date: – Road 08 service installation and road construction works; – Precinct 3 & 4 Bulk Earthworks; – Ongoing defect rectification; – Precinct 5 Bulk Earthworks; – Dedication of Estate Road 1, 6 and 7. • Upcoming Works: – Road 08 road constructi

  7. Slide 7: Progress To Date & Upcoming Works – Building 1A

    Progress To Date & Upcoming Works – Building 1A • Progress to Date: – Office Precast Installation; – Roofing Installation; – Wall Cladding Installation; – Structural Steel Installation; – In-ground Services Installation; • Upcoming Works: – Office Precast Installation; – Roofing Installation; – Wall

  8. Slide 8: Progress To Date & Upcoming Works – Building 1B & 1C

    Progress To Date & Upcoming Works – Building 1B & 1C • Progress to Date: – Installation of Erosion & Sediment Controls; – Site Establishment; • Upcoming Works: – Site Establishment; – Stormwater Installation; – In-ground services Installation; – Detailed Earthworks; – Footing Installatoin; 8

  9. Slide 9: Progress To Date & Upcoming Works – Building 2B

    Progress To Date & Upcoming Works – Building 2B • Progress to Date: – Internal Fitout Works Progressing; – Carpark installation ongoing; – External Hardstand installation ongoing; – Landscaping installation underway; • Upcoming Works: – Internal Fitout Works ongoing; – Carpark installation ongoing;

  10. Slide 10: Progress To Date & Upcoming Works – Building 3A

    Progress To Date & Upcoming Works – Building 3A 10

  11. Slide 11: Progress To Date & Upcoming Works – Building 3A

    Progress To Date & Upcoming Works – Building 3A • Site Commencement 23rd August 2021; • Installation of Site Sediment Control Measures • Bulk Earthworks pad trimming and levelling • In-ground stormwater service installation; • Warehouse Structural Steel Column Footing installation 11

  12. Slide 12: Consultation Requirements – Building 3B - CEMP

    Consultation Requirements – Building 3B - CEMP • In anticipation of the draft Consent • PCC Development Conditions for PCC DA21/0440, per the Application DA21/0440 under overarching SSD requirements, Goodman the overarching State wish to consult the CEMP with the relevant Significant Development Sta

  13. Slide 13: Consultation Requirements – Building 4E - CEMP

    Consultation Requirements – Building 4E - CEMP • In anticipation of the draft Consent • State Significant Development Conditions for SSD 22191322, • Project to be Completed by Goodman wish to consult the CEMP Qanstruct; with the relevant Stakeholders for the • Construction is forecast to project pri

  14. Slide 14: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 2020 QTR 3 (JULY-SEPT) 9 2020 QTR 4 (OCT-DEC) 7 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – JUN) 11 2121 QTR 7 (JULY – SEP PART) 10 TOTAL TO DATE 72 Copyright © ErSed 2011

  15. Slide 15: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD 09/06/21 REVIEW AND CLOSE OUT OF APRIL AUDIT • LOT 1A • AQMP • SWMP • FIP • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS • MONITORING AND REPORTING Copyright © ErSed 2011

  16. Slide 16: Environmental Performance: SSD7348

    ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES OR INCIDENTS NIL Copyright © ErSed 2011

  17. Slide 17: Environmental Performance: SSD7348

    ENVIRONMENTAL PERFORMANCE: SSD7348 COMPLAINTS, NIL Copyright © ErSed 2011

  18. Slide 18: EC Inspections and Audits - SSD10397

    EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY 20 3 AUGUST 20 0 SEPTEMBER 20 1 OCTOBER 20 1 NOVEMBER 20 1 DECEMBER 20 1 JANUARY 21 0 FEBRUARY 21 1 MARCH 21 5 APRIL 21 1 MAY 21 1 JUNE 21 2 (1 Inspection + 1 Audit) JULY 21 0 AUG 21 2 SEPT 21 (PART) 0 TOTAL 19 Copyright © ErSed

  19. Slide 19: Environmental Performance - SSD10397

    ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS 29 JUNE 21 An incident occurred on site on 29 JUNE 21. This did not result in environmental harm. NON COMPLIANCES NIL Copyright © ErSed 2011

  20. Slide 20: Safety

    Safety • Building 1A - Elevated Work Platform Near Miss; • Building 1A – Crane Near Miss; • No major injuries have occurred on site during this reporting period; 20

  21. Slide 21: Consultation and Community Interactions

    Consultation and Community Interactions No complaints, enquiries or communications 21

  22. Slide 22: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  23. Slide 23: Stakeholder Feedback & Questions

    Stakeholder Feedback & Questions 23