  1. Slide 1: Newcastle Community Dialogue Group – Meeting 15

    Newcastle Community Dialogue Group 03 September 2020 – Meeting 15

  2. Slide 2: Open and welcome, apologies, declarations, previous minutes and business arising

    Open and welcome, apologies, Newcastle Gas Storage Facility 1 declarations, previous minutes and business arising 3 Latest news Newcastle Power Station Project 2 4 General business Latest news and next steps Next meeting and close

  3. Slide 3: Apologies, declarations, previous minutes and business arising

    Apologies, declarations, previous minutes and business arising

  4. Slide 4: Newcastle Power Station Project: Latest news and Next steps

    Newcastle Power Station Project Latest news and Next steps

  5. Slide 5: Timeline

    Timeline Jan April Nov Dec April Aug Dec Jan 2019 2019 2019 2019 2020 2020 2020 2021 Lodge PEA Lodge EPBC Submit EIS Exhibition of Submit Submit Minister EPBC Approval application Referral with EIS ends Response to Amendment recommends granted – CA with DPIE (CSSI) DAWE Submissions Report Project Ap

  6. Slide 6: Amendment Report lodged with DPIE

    • Our ‘Amendment Report’ was lodged with the Department of Planning Industry and Environment (DPIE) on 14th August 2020 and was accepted on 27th of August 2020. It makes small amendments to the original EIS submission, including provision of two lay-down areas. • The report is supported by seven exp

  7. Slide 7: Further notification included the following stakeholders

    Further notification included the following stakeholders: • Port Stephens Council • Transgrid • Newcastle Gas Storage Facility • Landholders in the vicinity within a 2 km radius. 3 September 2020 7

  8. Slide 8: Next steps: DPIE assessment of the NPSP proposal

    • Formal DPIE assessment of the NPSP proposal. • DPIE has sent the amendment report to agencies for further comment, which could prompt more queries. • Once the potential additional queries are solved, DPIE will proceed with recommendations and final determination, expected to take place by the end

  9. Slide 9: Newcastle Gas Storage Facility: Latest news

    Newcastle Gas Storage Facility Latest news

  10. Slide 10: General

    General • The plant has completed liquification in March. • Gas send out (vaporisation) to supply NSW started in June. • COVID-19 slowed down all maintenance and capital project activities. • We have been mainly in SENDOUT mode since June. • Several plant critical process safety tests and routine in

  11. Slide 11: Environmental Update

    Update required Environmental Update • Air Emissions testing was undertaken on H-101 Unit in April with no exceedance reported. • 6-monthly groundwater and surface water monitoring was undertaken in March with no exceedance reported • Air Emissions testing being undertaken on F-501A, B & C Heaters i

  12. Slide 12: Local Community Investment Program is open

    • The AGL Newcastle Gas Storage Facility’s Local Community Investment Program is open. • Applications will be received until the 30th of September 2020. • Promotion: • Online ads on Facebook within the Port Stephens, Maitland and Newcastle areas. • Printed ads on Port Stephens Examiner and Maitland

  13. Slide 13: Bushfire wildlife relief partnership

    It is calculated that more than a billion animals died in Australia during the bushfire season between 2019 and 2020, with at least 800 million of these losses in NSW and VIC. Still, these numbers are very conservative. We established a partnership with the Biodiversity and Conservation Division of

  14. Slide 14: Community organisations: Carrie's Place, Yacaaba Centre, Tomaree Neighbourhood Centre

    Carrie’s Place Yacaaba Centre Port Stephens Family and Neighbourhood Tomaree Neighbourhood Centre Services 3 September 2020 14

  15. Slide 15: General Business: Next meeting and close

    General Business Next meeting and close

  16. Slide 16: Lisa Andrews, Ernesto Calderon

    Lisa Andrews Ernesto Calderon Independent Chairperson Newcastle Gas Storage Facility and 0401 609 693 Newcastle Power Station Project Community Relations Manager lisaandrews.ic@gmail.com 0498 001 536 ecalderon@agl.com.au