Titagarh Rail Systems Ltd · NSE:TITAGARH

Titagarh Rail Systems — Q2 FY27 Earnings Presentation

39 slides from Titagarh Rail Systems's earnings presentation, Nov 13, 2026

  1. Slide 1: Regulation 30 Announcement Cover Letter

    Slide 1: Regulation 30 Announcement Cover Letter

    13th November, 2026 BSE Limited (BSE) National Stock Exchange of India Limited (NSE) The Department of Corporate Services The Listing Compliance Department Phiroze Jeejeebhoy Towers Exchange Plaza Bandra-Kurla Complex Dalal Street, Mumbai – 400 001 Bandra (E), Mumbai – 400 051 Scrip Code: 532966 Sym

  2. Slide 2: Investor Presentation Q2 FY27

    Slide 2: Investor Presentation Q2 FY27

    INVESTOR INVESTOR PRESENTATION PRESENTATION Q3 & 9M FY26 Q2 FY27 VISION & ROADMAP

  3. Slide 3: Safe Harbor

    Slide 3: Safe Harbor

    Safe Harbor This presentation and the accompanying slides (the “Presentation”), which have been prepared by Titagarh Rail Systems Limited (TRSL, the “Company’), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe f

  4. Slide 4: Pioneering Innovation & Precision Engineering for Unparalleled Rail Systems

    Slide 4: Pioneering Innovation & Precision Engineering for Unparalleled Rail Systems

    Pioneering Innovation & Precision Engineering for Unparalleled Rail Systems 01 Q2 FY27 Highlights & About the Company 02 Order Book Position (₹ and Units) 03 Business Update, Strategy & Roadmap 04 Q2 FY27 Financial Performance 05 Subsidiaries & Joint Ventures – Key Updates 06 Shareholding Pattern &

  5. Slide 5: Q2 FY27 at a Glance – Highlights of the Quarter

    Slide 5: Q2 FY27 at a Glance – Highlights of the Quarter

    Q2 FY27 at a Glance – Highlights of the Quarter A breakthrough quarter: record Passenger Rail performance, landmark partnerships and a strong, diversified order book 51 ₹300 Cr 4,955 ~₹28,695 Cr Metro cars invoiced in Q2 PRS revenue – highest ever Wagons ordered in Q2 (from Total order book incl. JV

  6. Slide 6: About the Company

    Slide 6: About the Company

    About the Company

  7. Slide 7: Business Unit Structure (Orderbook at Sep 2026)

    Slide 7: Business Unit Structure (Orderbook at Sep 2026)

    Business Unit Structure (Orderbook at 30 Sep 2026)* Titagarh Rail Systems Limited Other Businesses & Railway Systems Joint Venture ~14,920 crs ~13,775 crs Freight Rail Systems BU Passenger Rail Systems BU On next slide ~4,119 crs ~10,801 crs Mainline Propulsion and Wagon Metro Coach Services (Vande

  8. Slide 8: Business Unit Structure – Other Businesses & Joint Venture

    Slide 8: Business Unit Structure – Other Businesses & Joint Venture

    Business Unit Structure (Orderbook at 30 Sep 2026) Other Businesses & Joint Venture ~13,775 crs Non- Core Growth Opportunities Strategic Joint Venture ~449 crs ~13,326 crs Ramkrishna Titagarh Rail Wheels Vande Bharat Service JV with BHEL Shipbuilding and Maritime Limited (Forged Wheel (50%) Manufact

  9. Slide 9: Manufacturing Facilities, Engineering & Design Centres

    Slide 9: Manufacturing Facilities, Engineering & Design Centres

    Manufacturing Facilities, Engineering & Design Centres 1 Kolkata (India) Passenger Rail Systems Unit 9 Delhi (India) Regional Office North 2 Kolkata (India) Wagon Plant Mumbai (India) Foundry Unit 1 Regional Office West Foundry Unit 2 Chennai (India) 9 Regional Office South 3 Bharatpur (India) Wagon

  10. Slide 10: Order Book Position

    Slide 10: Order Book Position

    Order Book Position

  11. Slide 11: Strong Order Book Position

    Slide 11: Strong Order Book Position

    Strong Order Book Position ~15,369 ₹ Cr ~28,695 ₹ Cr TRSL Order Book (STANDALONE Incl. WOS) Total Order Book incl prorate share of JVs Sr. No. Business Unit Contribution to Orderbook (Amount) Contribution to Orderbook (%) 1 Freight Rail Systems ~4,119 Crores 27.61% 2 Passenger Rail Systems ~10,801 C

  12. Slide 12: Major Business Update

    Slide 12: Major Business Update

    Major Business Update

  13. Slide 13: Passenger Rail Systems – A Breakthrough Quarter

    Slide 13: Passenger Rail Systems – A Breakthrough Quarter

    Passenger Rail Systems – A Breakthrough Quarter PRS revenue (₹ Cr) – more than doubled year-on-year 300.18 51 229.75 122.21 METRO CARS INVOICED IN Q2 FY27 +325% YoY | +70% QoQ Q2 FY26 Q1 FY27 Q2 FY27 ₹300 Cr HIGHEST-EVER QUARTERLY PRS REVENUE 39% PRS share of revenue vs 16% YoY / 31% QoQ 16.75% PRS

  14. Slide 14: Strategic Milestones of the Quarter

    Slide 14: Strategic Milestones of the Quarter

    Strategic Milestones of the Quarter 1 JV with BHEL signed 2 MoU with Siemens • JV Agreement signed on 15 Sep 2026 to incorporate an SPV in • Strategic MoU signed with Siemens, a global leader in rail New Delhi (initial paid-up capital ₹50 lakh) technology • 50:50 ownership with equal governance righ

  15. Slide 15: Specialised Wagons

    Slide 15: Specialised Wagons

    SPECIALISED WAGONS

  16. Slide 16

    Slide 16

  17. Slide 17: Strategy & Roadmap

    Slide 17: Strategy & Roadmap

    Strategy & Roadmap

  18. Slide 18: Vision & Roadmap – FY25 to FY30

    Slide 18: Vision & Roadmap – FY25 to FY30

    Vision & Roadmap – FY25 to FY30 OUR VISION From India’s leading wagon maker to a full-spectrum rail mobility company – metro, Vande Bharat, propulsion, forged wheels, high-speed rail and maritime #MobilityForBillions Business FY25 FY26 FY27E FY28E FY30E Metro coaches (production) 12 63 ~200 275 500

  19. Slide 19: Strategic Plan – Progress Scorecard (Q2 FY27)

    Slide 19: Strategic Plan – Progress Scorecard (Q2 FY27)

    Strategic Plan – Progress Scorecard (Q2 FY27) Strategic pillar Strategic plan target Q2 FY27 progress Status Metro production 200–220 coaches in FY27; 51 metro cars invoiced; record ₹300 Cr PRS revenue; PRS 39% of Passenger Rail leadership On track ~275–300 in FY28 revenue Vande Bharat sleeper 192 V

  20. Slide 20: FRS outlook: capacity in place, demand intact

    Slide 20: FRS outlook: capacity in place, demand intact

    FRS outlook: capacity in place, demand intact CAPACITY 12,000 O/S ORDER BOOK CURRENT DISPATCHES TARGET by Q4 9,144 ~400 / month 1000 / month wagons per annum installed capacity achieved multiple times, 1,000 per month Planned ramp up to 10000/ month with the 1155 in Q1, 1280 in Q2 receipt of the new

  21. Slide 21: High Speed Rail – Next Big Opportunity

    Slide 21: High Speed Rail – Next Big Opportunity

    High Speed Rail – Next Big Opportunity India's High-Speed Rail 8 Corridors Announced U N D E R C O N S T R U C T IO N Mumbai – Ahmedabad (508 km) | First section operational Aug 2027 A once-in-a-generation infrastructure opportunity 7 N E W C O RR I D O RS — BU DG E T 2 0 2 6 – 2 7 Planned network M

  22. Slide 22: Q2 FY27 Financial Performance

    Slide 22: Q2 FY27 Financial Performance

    Q2 FY27 Financial Performance

  23. Slide 23: Key Financial Highlights

    Slide 23: Key Financial Highlights

    Key Financial Highlights Rs 300 Cr PRS revenue 51 metro cars invoiced 39% PRS share of revenue 1,155 wagons dispatched Highest ever quarter, +325% YoY / +70% QoQ vs 31% QoQ / 16% YoY vs 1,872 YoY / 1,284 QoQ +146% YoY / +31% QOQ ₹ in Crores Segment Breakup Q2 FY 27 % Q1 FY 27 % Q2 FY 26 % FY 26 % Fr

  24. Slide 24: Key Financial Numbers – Last 5 quarters (standalone)

    Slide 24: Key Financial Numbers – Last 5 quarters (standalone)

    Key Financial Numbers – Last 5 quarters (standalone) Revenue from operations EBITDA and EBITDA margin (before exceptional items)* 1000 140 13.81% 900 823 859 12.09% 12.79% 14% 788 773 12.04% 104 800 735 120 11.25% 107 99 12% 700 100 89 94 600 10% 500 80 8% 400 60 6% 300 200 40 4% 100 0 20 2% Q2FY26

  25. Slide 25: Balance Sheet – Standalone

    Slide 25: Balance Sheet – Standalone

    Balance Sheet– Standalone September 30, September 30, PARTICULARS March 31, 2026 PARTICULARS March 31, 2026 2026 2026 Unaudited Audited Unaudited Audited ASSETS EQUITY AND LIABILITIES 1 Non-current Assets EQUITY a) Property, Plant and Equipment 1,055.67 1,072.47 a) Equity Share Capital 26.93 26.93 b

  26. Slide 26: Cash Flow – Standalone

    Slide 26: Cash Flow – Standalone

    Cash Flow– Standalone A. Operating activities H1 FY27 H1 FY26 FY26 Profit before tax 152.69 70.64 222.82 Depreciation and amortisation 30.32 24.34 50.22 Finance cost 30.73 36.1 70.37 Interest income (8.27) (24.22) (34) Exceptional items (non-cash) – 53.96 57.58 Other non-cash items (net) (5.57) 5.03

  27. Slide 27: Key Financial Numbers – Last 5 quarters (Consolidated)

    Slide 27: Key Financial Numbers – Last 5 quarters (Consolidated)

    Key Financial Numbers – Last 5 quarters (Consolidated) Revenue from operations EBITDA and EBITDA margin (before exceptional items) 1000 875 140 900 799 833 13.41% 765 793 12.33% 14% 800 120 11.11% 11.06% 106 12% 700 9.89% 97 95 100 92 600 10% 79 500 80 8% 400 60 6% 300 40 4% 200 20 2% 100 0 0 0% Q2F

  28. Slide 28: Balance Sheet – Consolidated

    Slide 28: Balance Sheet – Consolidated

    Balance Sheet– Consolidated PARTICULARS (Rs. in Crores) September 30, 2026 March 31, 2026 PARTICULARS (Rs. in Crores) September 30, 2026 March 31, 2026 Unaudited Audited Unaudited Audited ASSETS EQUITY AND LIABILITIES 1 Non-current Assets EQUITY a) Property, Plant and Equipment 1,088.73 1,105.69 a)

  29. Slide 29: Cash Flow – Consolidated

    Slide 29: Cash Flow – Consolidated

    Cash Flow– Consolidated Half year ended Half year ended Year ended March 31, PARTICULARS September 30, 2026 September 30, 2025 2026 Unaudited Unaudited (Restated) Audited 1 CASH FLOWS FROM OPERATING ACTIVITIES Profit/ (Loss) before Tax from: Continuing Operations 152.89 59.36 192.67 Discontinued Ope

  30. Slide 30: Cash Flow – Consolidated (contd.)

    Slide 30: Cash Flow – Consolidated (contd.)

    Cash Flow– Consolidated (contd.) Half year ended Half year ended Year ended March 31, PARTICULARS September 30, 2026 September 30, 2025 2026 Unaudited Unaudited (Restated) Audited 2 CASH FLOWS FROM INVESTING ACTIVITIES Payments for Acquisition of Property, Plant and Equipment including Capital Work-

  31. Slide 31: Subsidiaries & Joint Ventures – Key Updates

    Slide 31: Subsidiaries & Joint Ventures – Key Updates

    Titagarh Naval Systems Limited – Wholly Owned Subsidiary (WOS) Subsidiaries & Joint Ventures – Key Updates Ramkrishna Titagarh Rail Wheels Limited – Joint Venture with Ramkrishna Forgings Limited (RKFL) Joint Venture with BHEL – AMC for Vande Bharat (JV Agreement signed 15 Sep 2026)

  32. Slide 32: Update on Titagarh Naval Systems Limited

    Slide 32: Update on Titagarh Naval Systems Limited

    Update on Titagarh Naval Systems Limited • Setting up Brownfield Shipyard at Falta with a total project cost of ~ Rs 610 crores • TNSL received in-principle approval under the Shipbuilding Development Scheme for capital assistance of ~ Rs 129 crores towards plant and machinery for the brownfield exp

  33. Slide 33: Shipbuilding & Maritime Systems (SMS)

    Slide 33: Shipbuilding & Maritime Systems (SMS)

    Shipbuilding & Maritime Systems (SMS) ❑ Diving Support Craft ❑ Fast Patrol Vessel ❑ NIOT

  34. Slide 34: Update on Rail Wheel Project (JV with RKFL)

    Slide 34: Update on Rail Wheel Project (JV with RKFL)

    Update on Rail Wheel Project (JV with RKFL) • Titagarh Rail Systems & Ramkrishna Forgings Consortium received an LOA for Manufacturing and Supplying of Forged Wheels for the Indian Railways. • The Company holds 49 % stake in the Joint Venture. • The JV will establish Asia’s 2nd largest manufacturing

  35. Slide 35: Update on Vande Bharat JV with BHEL

    Slide 35: Update on Vande Bharat JV with BHEL

    Update on Vande Bharat JV with BHEL • Titagarh Rail Systems Limited ("TRSL") and Bharat Heavy Electricals Limited ("BHEL") signed the Joint Venture Agreement on September 15, 2026, to incorporate a new private limited company in New Delhi, with initial paid-up capital of ₹50 lakh, for comprehensive

  36. Slide 36: Shareholding Pattern

    Slide 36: Shareholding Pattern

    CGC TITAGARH ly RAIL SYSTEMS LIMITED Shareholding Pattern

  37. Slide 37: Shareholding Pattern as on 30th September, 2026

    Slide 37: Shareholding Pattern as on 30th September, 2026

    Shareholding Pattern as on 30th September, 2026 Percentage of Holding 7.31% Category No. of Shares % of Holding 11.39% Promoters (*) 54486861 40.46% Mutual Funds 17481633 12.98% 40.46% Resident Individuals 37512459 27.86% Foreign Portfolio Investors 15329974 11.39% Others 9862841 7.31% 27.86% *Promo

  38. Slide 38: Focus on Environment Social & Governance (ESG)

    Slide 38: Focus on Environment Social & Governance (ESG)

    Focus on Environment Social & Governance (ESG) Environment Social Governance • Capacity Installation: Targeted 4 MW • Under the Health & Hygiene theme – • Board oversight with 50% Independent capacity to support manufacturing, Jeevan Nirog provides rehabilitation and Directors including 1 Woman weld

  39. Slide 39: Contact

    Slide 39: Contact

    Name: Maitreyee Mishra Email Id: maitreyee.mishra@titagarh.in Website: www.titagarh.in

Source: NSE filing, Nov 13, 2026