Latrobe Magnesium Limited · ASX:LMG

Latrobe Magnesium — Shareholder Meeting (2018)

10 slides from Latrobe Magnesium's shareholder meeting presentation, 2018

  1. Slide 1: Latrobe Magnesium AGM 2018 Presentation

    Latrobe Magnes um AGM 2018 Presentation David Paterson ASX: CEO LMG

  2. Slide 2: Presentation contents

    Latrobe Presentation contents Magnes um 1. 2018 in review 2. Magnesium market 3. LMG location and site 4. Financial overview 5. Timetable 2

  3. Slide 3: 1. 2018 in review

    1. 2018 in review Latrobe Magnes um  MoU with Yallourn for the supply of ash and successful test work carried out using an acid based process. Next stage is to complete a bankable feasibility study.  On Wednesday this week, the Board announced that a bankable feasibility study will be conducted on

  4. Slide 4: 1. 2018 in review (cont'd)

    Latrobe 1. 2018 in review (cont’d) Magnes um  Term sheet signed with RWE Power for the development of a German magnesium plant and the successful testing of their fly ash. Next stage is testing of their SCM to EU standards and then a collaboration agreement.  Initial discussions underway with anot

  5. Slide 5: 2. Magnesium Market

    Latrobe 2. Magnesium Market Magnes um  Market grew by 100,000 tonnes in 2018 to 1,000,000 tonnes and is expected to double within the next 10 years  Aluminium use is now 70% of market due to aluminum sheet for cars and increasing  China produces 86% of world production and its 2030 car only usage

  6. Slide 6: 3. LMG site

    Latrobe 3. LMG site Magnes um Swop Line from Yallourn Natural Gas Pipeline Swop Line From Hazelwood 320 Tramway Site 6

  7. Slide 7: 3. LMG building

    Latrobe 3. LMG building Magnes um 7 320 Tramway Site Building

  8. Slide 8: 4. Financial overview

    Latrobe 4. Financial overview Magnes um 3,000 Projected Funding tonnes A$M’s R&D Funding 16 Federal and Victorian Grants 12 LMG Equity 12 ---- Total Project Funding 40 == Capex for 3,000 tpa plant estimated at A$37M with a working capital requirement of A$3M. Total funding A$40M. EBITDA estimate in

  9. Slide 9: 5. Timetable

    Latrobe 5. Timetable Magnes um Tasks Timing  Complete Bankable Studies Jun 2019  Complete Funding & Permitting Dec 2019  Construction – Initial plant Dec 2019  Production - Initial plant Dec 2020  Expansion Stage 2 Jul 2021 9

  10. Slide 10: Disclaimer

    Latrobe Disclaimer Magnes um • This presentation may contain forward looking statements that are subject to risk factors associated with the magnesium business. • It is believed that the expectations reflected in these statements are reasonable but they may be affected by a variety of variables and