Boral — Corporate Update (October 2021)
46 slides from Boral's corporate update, October 2021
Slide 1: Community Consultative Committee Peppertree Quarry
Click to edit Master title style Subheader Community Consultative Committee Peppertree Quarry October 2021
Slide 2: Agenda
AGENDA 1. Welcome and introductions 2. Confirmation of minutes and actions 3. Business arising 4. Correspondence 5. Operations over the last 3 months 6. Environmental performance a. Incidents b. Complaints c. Air d. Noise e. Blast f. Water – surface and ground g. Heritage h. Ecology 7. Stakeholder E
Slide 3: Welcome and apologies
01 Welcome and apologies
Slide 4: Confirmation of minutes
O2 — Confirmation of minutes
Slide 5: Business arising
03 Business arising • Nature of the PM2.5 particles to be defined • Update on weather station changes
Slide 6: Correspondence June – Sept 2021
04 Correspondence June – Sept 2021
Slide 7: Correspondence with regulators and stakeholders
Department of Planning, Industry and Environment Approval of consultant for Independent Audit Water management plan issued for comment – Water NSW, DPIE Water, EPA and NRAR Modification 7 approval Request and approval to move product by road due to COVID restrictions EPA - complaint re noise Resourc
Slide 8: Modification 7
Modification 7 Peppertree Quarry CCC Item 4 Correspondence 8
Slide 9: Operations Past 3 months
05 Operations Past 3 months
Slide 10: Operations in the past 3 months
Safety Focus on COVID protocols (split crews, cleaning, Public health order requirements) Overburden Pre works commenced. Pit Update Load and haul contract has commenced in the pit to move rock from the drop cut to the in pit crusher. Will be completed in Dec 21 Processing (STQ) production continuin
Slide 11: Environmental Performance
06 Environmental Performance
Slide 12: Environmental Incidents June to Sept 2021
Environmental Incidents June to Sept 2021 Incidents 2017 - September 2021 8 7 6 5 4 3 2 1 0 ˃ June – nil July - nil August – nil September – nil Peppertree Quarry CCC item 6 Environmental Performance 12
Slide 13: Environmental Complaints July to Sept 2021
Environmental Complaints July to Sept 2021 Complaints 2017 to September 2021 6 5 4 3 2 1 0 ˃ June – nil July - nil August – nil September – 1 – noise Peppertree Quarry CCC item 6 Environmental Performance 13
Slide 14: Air – Dust deposition Gauge D1
Air – Dust deposition Gauge D1 Annual Average goal of 4gm2/month In compliance Annual average below goal at the boundary Peppertree Quarry CCC item 6 Environmental Performance 14
Slide 15: Deposited dust 2017 - 2021
g/m2/month In compliance 10.00 0.00 2.00 4.00 6.00 8.00 1.00 3.00 5.00 7.00 9.00 Jan-2017 Feb-2017 Mar-2017 Apr-2017 May-2017 Jun-2017 Jul-2017 Aug-2017 Sep-2017 Oct-2017 Nov-2017 Annual Average goal of 4gm2/month Peppertree Quarry CCC item 6 Environmental Performance Dec-2017 Jan-2018 Annual averag
Slide 16: Air – Dust Deposition gauge D3
Air – Dust Deposition gauge D3 Annual Average goal of 4gm2/month In compliance Annual average below goal at the boundary Peppertree Quarry CCC item 6 Environmental Performance 16
Slide 17: Air – PM10 annual average
In compliance ug/m3 10.00 20.00 30.00 15.00 25.00 35.00 0.00 5.00 6/01/2019 24/01/2019 11/02/2019 1/03/2019 25/03/2019 18/04/2019 Annual Average goal of 25ug/m3 12/05/2019 Peppertree Quarry CCC item 6 Environmental Performance 5/06/2019 29/06/2019 23/07/2019 Annual average below goal at the boundary
Slide 18: Air – PM10 24 Hour performance
In compliance ug/m3 50 0 150 250 300 100 200 350 6/01/2019 24/01/2019 24 hour goal of 50ug/m3 11/02/2019 1/03/2019 25/03/2019 18/04/2019 12/05/2019 5/06/2019 Peppertree Quarry CCC item 6 Environmental Performance 29/06/2019 23/07/2019 Annual average below goal at the boundary 16/08/2019 9/09/2019 3/
Slide 19: Air – Total Suspended Particulates
In compliance 100.00 200.00 300.00 400.00 500.00 600.00 0.00 4/1/17 3/02/2017 5/03/2017 4/04/2017 4/05/2017 3/06/2017 3/07/2017 Annual Average goal of 90ug/m3 2/08/2017 1/09/2017 1/10/2017 31/10/2017 30/11/2017 Peppertree Quarry CCC item 6 Environmental Performance Annual average below goal at the b
Slide 20: Air – PM2.5
Air – PM2.5 PM2.5 24 hour 2021 PM2.5 45.00 18.00 40.00 16.00 35.00 14.00 30.00 12.00 10.00 25.00 8.00 20.00 6.00 15.00 4.00 10.00 2.00 5.00 0.00 0.00 2/6/2021 3/6/2021 4/6/2021 5/6/2021 6/6/2021 7/6/2021 8/6/2021 2/6/2021 3/6/2021 4/6/2021 5/6/2021 6/6/2021 7/6/2021 8/6/2021 Annual Average goal of 8
Slide 21: Noise – quarterly monitoring
Noise – quarterly monitoring There has been a delay in the Noise monitoring program due to the COVID restrictions Consultants have not been able to come to site and we have limited their movements to minimise the potential for them brining COVID from the greater metropolitan area. Monitoring was und
Slide 22: Blasting - Overpressure
Blasting - Overpressure Over Pressure 2020 - 2021 140 120 100 80 60 40 20 0 north west boundary north east boundary 683 Marulan sth road Pace criteria 1 criteria 2 In Compliance Peppertree Quarry CCC item 6 Environmental Performance 22
Slide 23: Blasting – ground Vibration
Blasting – ground Vibration Vibration 2020 - 2021 12 10 8 6 4 2 0 north west boundary north east boundary 683 Marulan sth road Pace criteria 1 criteria 2 In Compliance Peppertree Quarry CCC item 6 Environmental Performance 23
Slide 24: Surface Water
Surface Water Quarterly monitoring round undertaken in July – September 2021. Next sample round quarter of October – December 2021 sampled Monday 18th October 2021 No issues with water supply or quality over the last 3 months Peppertree Quarry CCC item 6 Environmental Performance 24
Slide 25: Surface water pH
Surface water pH Peppertree Water Samples pH 2012 to 2021 10 9.5 9 8.5 8 pH 7.5 7 6.5 6 5.5 5 T1 dam lower criteria (6.5) higher criteria (8.5) MSth creek U1 barbers creek ˃ Below guideline for July samples Peppertree Quarry CCC item 6 Environmental Performance 25
Slide 26: Surface water - Turbidity
Surface water - Turbidity Peppertree water samples - Turbidity 2012 - 2021 300 250 200 150 NTU 100 50 0 T1 Main dam ANZECC guideline U1 MSth creek Below guideline for July samples Peppertree Quarry CCC item 6 Environmental Performance 26
Slide 27: Surface water – Total dissolved solids
Surface water – Total dissolved solids Peppertree water samples - Total Dissolved Solids 2012 - 2021 1400 1200 1000 800 mg/l 600 400 200 0 date T1 DAM ADWG aesthetic marulan sth creek U1 barbers creek Below guideline for July samples Peppertree Quarry CCC item 6 Environmental Performance 27
Slide 28: Surface water – total Phosphorus
Surface water – total Phosphorus Peppertree Quarry Total Phosphorus (mg/l) 2012 - 2021 0.6 0.5 0.4 m g/l 0.3 0.2 0.1 0 T1 dam marulan sth creek trigger U1 barbers creek Below guideline for July samples Peppertree Quarry CCC item 6 Environmental Performance 28
Slide 29: Surface water - Total Nitrogen
Surface water - Total Nitrogen Peppertree Quarry Total Nitrogen (mg/l) 2014 to 2021 12 10 8 m g/l 6 4 2 0 T1 dam marulan sth creek trigger U1 barbers creek Below guideline for July samples, with the exception of the Main dam Peppertree Quarry CCC item 6 Environmental Performance 29
Slide 30: Environmental Flow
Environmental Flow year total in flow 10% total out flow in compliance comment Aug-2020 49.67 4.96 696.78 yes Rainfall - possible overflow of the V notch weir Sep-2020 0 0 3.11 yes Oct-2020 32.91 3.2 148.71 yes Nov-2020 10 1 379.5 yes Rainfall - possible overflow of the V notch weir Dec-2020 17.1 1.
Slide 31: Ground water
Ground water ˃ Monitoring conducted in April 2021. ˃ results show no changes to the groundwater ˃ Review of the existing wells was undertaken and advice now provided on replacement wells and locations Peppertree Quarry CCC item 6 Environmental Performance 31
Slide 32: Ground water – water levels
Ground water – water levels Peppertree Quarry CCC item 6 Environmental Performance 32
Slide 33: Heritage
Heritage Collation of Artefacts has been postponed for a short period due to the availability of the archaeologist Planning is progressing to return the artefacts to country by the end of the year NAIDOC week community workshops being developed Scar tree relocation being planned Peppertree Quarry CC
Slide 34: Ecology
Ecology Three year plan developed for ongoing rehabilitation and maintenance Rapid Visual assessment to be conducted Thursday 21st October Monitoring plan has been revised Implementation plan being prepared in conjunction with the 3 year plan Hollow assessment undertaken on the SWOE site Peppertree
Slide 35: Stakeholder Engagement
07 Stakeholder Engagement
Slide 36: Stakeholder Engagement
Planning for Marulan Spring festival was cancelled due to COVID Stakeholder engagement plan for 2022 is being prepared Planning for the Marulan Christmas Street fair is underway Peppertree Quarry CCC item 7 Stakeholder Engagement 36
Slide 37: Operations Next 3 months
O8 - Operations Next 3 months
Slide 38: Operations next 3 months
Safety Focus on return to “normal” around operations and COVID management Overburden Pre works commenced. – contract in place with OB contractor Pit Update Shut down over Christmas 23-12-2021 till the 10-01-2022, during this time we will continue to complete maintenance. Processing (STQ) Shut down o
Slide 39: General Business
O9 - General Business
Slide 40: Marulan South State Significant Development
Marulan South State Significant Development conditions of consent have been issued It has been agreed that a joint CCC will be established Process is to advise and seek DPIE approval The Chair to seek nominations for representatives The Chair to advise an seek approval from DPIE on the selection of
Slide 41: Boral rebranding
Boral rebranding Peppertree Quarry CCC item 9 General Business 41
Slide 42: Boral sets target for NET Zero
Boral sets target for NET Zero Boral has set the most ambitious carbon emissions targets in the global construction materials industry1, and has joined the Science Based Targets initiative (SBTi) Business Ambition for 1.5°C and UNFCCC Race to Zero. The new carbon reduction targets mean Boral is comm
Slide 43: General Business
Peppertree Quarry CCC item 9 General Business 43
Slide 44: Other
Other Peppertree Quarry CCC item 9 General Business 44
Slide 45: Next meeting
Next meeting December 2021 Peppertree Quarry CCC item 9 general Business Peppertree Quarry CCC item 6 Environmental Performance
Slide 46: Thanks for your participation
Thanks for your participation 46