3 Corporate Summary Highlights Focussed on developing 100%-owned ‘Vanguard 1’ project located in central Saskatchewan, Canada • Vanguard 1 Project is in the first quartile of all potash producers worldwide: sub-US$40.00/t cash costs • Lowest All-in Cash Costs in North America of US$170.31/t (deliver
Slide 4: Vision – Mission - Values
4 Gensource Potash Corp. Vision – Mission - Values Vision: Mission: Values: Create a series of Achieve food security The core priorities independent, scalable by supplying the world for Gensource are and environmentally with a key integrity, sustainable Potash macronutrient at an forthrightness, pro
Slide 5: Potash: Problem & Opportunity
5 Potash: Problem & Opportunity Supply Side Development of Crop Prices Demand Side Producers Suffer From: A Historical Overview: Customers Suffer From: ❖ Lack of Competition: Potash is ❖ Lack of Competition: Potash supply is 11.5 controlled by oligopolistic controlled by oligopolistic supply-side su
Slide 6: Gensource Value Proposition
6 Gensource Value Proposition To disrupt the existing supply chain by deploying innovative extraction methods and partnering directly 100% Potash 3. JV Partnerships Direct Delivery with potash users 2. Innovative Extraction Method Gensource Potash JVCo. Mineral Reserve Potash Partner Using brackish
Slide 7: High Quality Asset Base
7 High Quality Asset Base Saskatchewan Canada Bankable Feasibility Projects situated in world’s Compelling Project NPV and IRR 1 Study completed largest potash basin May 31, 2017 (unlevered – 100% Equity Base Case) Indicator Pre Sask. Profit Tax Post Sask. Profit Tax Strong local and provincial supp
Slide 8: Drilling & Geology – Reserves & Resources
8 Drilling & Geology – Reserves & Resources Gensource Potash’s ‘Vanguard 1 Area’ Mineral Resources were The mineral resources for the Vanguard 1 Project area have been estimated by Ordinary Kriging techniques using a grid model in estimated based on the principles established by the Guidelines on Ma
Slide 9: Vanguard 1 Cost Breakdown – CapEx
9 Vanguard 1 Cost Breakdown CapEx Breakdown Project economics includes fully drawn contingency expense Item ‘000 CA$ Contingency, Mining, 8.5% 9.1% Mining $ 23,738 Wellfield, 6.2% Wellfield $ 17,304 Process Plant $ 70,610 Project Indirects, Storage & Loadout $ 957 27.9% Process Plant, 25.2% Site Inf
Slide 10: Vanguard 1 Cost Breakdown – OpEx
10 Vanguard 1 Cost Breakdown OpEx Breakdown All-in costs per tonne of $US 95.97 (Ex Works) Cash Margins OpEx, Price/ Net $ Margin % Net $ Margin % $39.57 Shipping , Tonne No Shipping With Shipping $74.35 $225 $129.03 57% $53.68 24% $250 $154.03 62% $79.68 32% Sustaining CapEx, $11.66 $275 $179.03 65
Slide 11: Gensource Versus Traditional Miners
11 Gensource Versus Traditional Miners Vanguard 1 In First Quartile Conversion Cost per Tonne @ Capacity (USD) 200 180 160 140 Sustaining Capex 120 100 Opex 80 60 40 20 0 Source: Randle Green Consulting, CRU, Integer Research, Company Reports, Gensource Potash
Slide 12: Comparative Mining Methods
12 Comparative Mining Methods Conventional Selective Dissolution Specifications Conventional Solution Mining Vanguard 1 Min. Viable Production Rate 2.5 Mt/a 2.0 Mt/a 250 kt/a CapEx per Tonne (USS) $ 1,990 * $ 1,620 * $ 840 ** Operating Costs (US$) $ 80/t * $ 118/t * $ 39.57/t ** Development Time 7-1
Slide 13: Economics
Each module and partnership creates significant cash flows to Gensource Potash Corp, creating a potash streaming company 13 Economics Assumptions Gensource’s small-scale concept facilitates a development timeline of approximately two Resource/Engineering Investment $ 8,000,000 years from constructio
Slide 14: Development Timelines
14 Development Timelines Proposed production horizon less than 3 years 2016 2017 2018 2019 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 PEA / Scoping Study Completed Market Partner JV Vanguard Potash Corp. Announced Exploration Drilling Completed NI 43-101 Resource Update Completed 3D Seismic Completed
Slide 15: Development Upside: Project 2
15 Development Upside: Project 2 Overview Resource Area A second project area, known as the ‘Lazlo Project’, is also The resource in the Lazlo area is rich and widespread, and is an ideal candidate for a selective dissolution operation. located along a well-serviced infrastructure corridor. Located
Slide 16: Management & Board
16 Management & Board Management Directors Mike Ferguson, P. Eng. - President & CEO Mike Ferguson, P. Eng. - President & CEO Led the world-class team that developed Potash One’s Legacy Project, Led the world-class team that developed Potash One’s Legacy the only Saskatchewan greenfield potash develo
Slide 17: Capital Structure
17 Capital Structure 52-Week Stock Performance Market Capitalization $27.0 Million $0.25 Recent Share Price $0.85 $0.20 52 Week Range $0.06 - $0.24 Basic Shares Outstanding 293 M $0.15 Options 27.4 M Warrants 50.1 M $0.10 Broker Warrants 4.0 M Cash Position ~ $800k $0.05 Debt $0 Management, Director
Slide 18: Contact Us
18 Contact Us Mike Ferguson, P. Eng. Rob Theoret, B.Comm., CIM President & CEO CFO mike@gensource.ca rob@gensource.ca 306-974-6414 306-974-6406 Suite 1100, 201 1st Ave. South Website Saskatoon, Saskatchewan www.gensource.ca S7K 1J5
Slide 19: Appendix
Appendix Gensource POTASH CORP
Slide 20: Technical Strength
20 Technical Strength These individuals, together with Mike Ferguson, comprised the core Potash One team responsible for the project’s success Max Ramey, P.Eng. – Solution Mining Solution mining lead for the Potash One - Legacy Project (as well as the Rio Tinto - Potasio Rio Colorado Project in Arge
Slide 21: Existing Mines have Environmental Issues
21 Existing Mines have Environmental Issues Gensource is NOT a conventional Potash Mine Gensource facility is 300 metres by 300 metres Conventional = HUGE environmental footprint ❖ Massive salt tailings stored on surface for indefinite period ❖ Large fresh water consumption ❖ Large demand on utiliti
Slide 22: Selective Dissolution
22 Selective Dissolution Cost effective and efficient recovery method Horizontal Well Pattern Horizontal Cavern for Selective Dissolution ❖ Using brackish formation water, an extraction brine is pumped through horizontal caverns where only KCl (potash) is dissolved ❖ The saturated brine (NaCl and KC
Slide 23: Proven Technique – Intrepid Potash
23 Proven Technique – Intrepid Potash Cane Creek Mine (Moab, UT) - has historically experienced many production challenges but deployed selective dissolution methods to overcome the problems Complex geology ❖ Significant faulting and folding associated with Cane Creek anticline ❖ Cannot be mined usi
Slide 24: Proven Technique – Intrepid Potash
24 Proven Technique – Intrepid Potash Selective dissolution successfully deployed at Cane Creek Mine (Moab, UT) starting in 2006 Pitchfork Well Pattern Before and After Selecting Mining ❖ Inject saturated brine to selectively mine potash – saturated brine targets potash only, salt matrix remains int