Royal Bafokeng Platinum Ltd

Royal Bafokeng Platinum — Technical Presentation (December 2011)

21 slides from Royal Bafokeng Platinum's technical presentation, Dec 2, 2011

  1. Slide 1: Styldrift 1 Site Visit

    Styldrift 1 Site Visit 2 December 2011

  2. Slide 2: Project Geographic Location

    Styldrift 1 Project Geographic Location

  3. Slide 3: Project Location

    Styldrift 1 Project Location

  4. Slide 4: Project Overview and Shaft Infrastructure

    Styldrift 1 Project Overview Shaft Infrastructure Features Description • Twin Vertical Shaft Access • Expansion project › Main shaft (10.5m dia. lined) • 230 ktpm Merensky mine and concentrator › Services shaft (6.5m dia. lined) • Dual shaft access: main shaft, services shaft › Main shaft - 740m bel

  5. Slide 5: Shaft Configuration

    Styldrift 1 Shaft Configuration Shaft Infrastructure Shaft Infrastructure • Production › 230ktpm reef › 45ktpm waste • Injury free mine design • Merensky reef mining focus • UG2 mining being investigated • Room & Pillar (Trackless) – thick and central upper reef Mining Access • Conventional breast –

  6. Slide 6: Mine Design

    Styldrift 1 Mine Design Shaft Sinking Footprint Room & Pillar Scattered Breast Shaft Position 8

  7. Slide 7: Access Methodology - Main Artery

    Styldrift 1 Access Methodology - Main Artery Haulage Haulage Haulage 11.0m 11.0m 9.0m 9.0m 11.0m Ore Body 21.00m 5.00m Boxhole On-Reef Cluster 25m Trucking system 5.00m 3.50m Haulage 18m Orepass Coveyor belt system Haulage 6.50m

  8. Slide 8: Production Profile and Resources and Reserves

    Styldrift 1 Styldrift Mining Production (mtpa) Styldrift Production Profile 4.00 2.69 2.83 2.80 2.73 3.00 2.00 1.67 1.00 0.39 0.09 0.14 0.00 2012 2013 2014 2015 2016 2017 2018 2019 2020 StyldriftMerensky Styldrift Resources and Reserves Merensky UG2 Total Mt 4E g/t 4E Moz Mt 4E g/t 4E Moz Mt 4E Moz

  9. Slide 9: Project Cost and Progress

    Styldrift 1 Project Cost and Progress Capital Budget - Nominal Capital Cash Flow - Nominal ZAR MM Mining Concentrator Total ZAR Millions 3,000 Authorised and Contingency 6,289 1,422 7,711 2,500 2,000 Escalation 3,153 938 4,091 1,500 Total Nominal 9,442 2,360 11,802 1,000 Latest Cost Forecast 9,209 2

  10. Slide 10: Mining Footprint

    Styldrift 1 Mining Footprint

  11. Slide 11: Legal and Permitting

    Styldrift 1 Legal and Permitting • Mining Right Granted March 2008 • EMP Approved March 2008 • Water User Licence Approved April 2010 • Legal Appointments All in place • Social and Labour Plan Approved September 2009

  12. Slide 12: Utilities

    Styldrift 1 Utilities Styldrift Mining Electrical Load Build-up Power Supply • Temporary power : 10 MVA secured from Eskom via 50 Boschkoppie substation 40 • Permanent power: 30 › Eskom budget approved and upfront payment 20 made 10 › Permanent power available by Q1 2014 0 • Emergency power: 3 x 3MV

  13. Slide 13: Project Timetable

    Styldrift 1 Project Timetable Progress (October 2011) Planned % Complete: 24.55% Actual % Complete: 24.96% Major equipment installation Sinking activities commencement

  14. Slide 14: Concentrator

    Styldrift 1 Concentrator Process Plant Design • Pre-Feasibility study in progress – completion planned for Q1 2012 • Concentrator design is for a 230 ktpm plant • Site Location of Concentrator and Tailings facility to be finalized • Feasibility study to commence in March 2012 and completed by June 2

  15. Slide 15: Project Highlights

    Styldrift 1 Project Highlights Completed Activities / Key Dates • Project commencement date – March 2009 • Bulk earthworks complete – June 2010 • Bulk Civils completed – October 2010 • Shaft pre sink commenced – October 2010 • Personnel & Material winder commissioned – March 2011 • Pre sink complete

  16. Slide 16: Optimisation

    Styldrift 1 Optimisation Optimisation study initiated in January 2011 Key components being reviewed are: • Shaft bottom infrastructure layout • Room and pillar mine design • Strike ore handling methodology – truck vs conveyors • Pneumatic vs electric drilling • Access to the UG2 ore horizon and asso

  17. Slide 17: Major Activities Completed – Headgear Erection

    Styldrift 1 Major Activities Completed – Headgear Erection

  18. Slide 18: Major Activities Completed

    Styldrift 1 Major Activities Completed Main Shaft Personnel and Material Winder (5.5m D): Commissioned Main & Service Shafts Stage Winders: Commissioned

  19. Slide 19: Activities In Progress

    Styldrift 1 Activities In Progress Main Shaft – Sinking Progress

  20. Slide 20: Further organic growth in Styldrift II

    Further organic growth in Styldrift II Styldrift II project area • Resource area ± 23 million m2 • Depth 900m – 1,400m, average dip 90 • Average Merensky/UG2 middling 35m Potential size of investment similar to Styldrift I (+ R10 billion) Opportunity will be evaluated through: • Study consisting of

  21. Slide 21: END

    END