  1. Slide 1: Kola DFS Presentation

    Kola DFS Presentation January 2019 1

  2. Slide 2: Cautionary statements

    Cautionary statements This presentation (the “Presentation”) has been prepared and issued by the directors of Kore Potash plc (“Kore” or the "Company" and, together with its subsidiaries, the “Group”). By attending (whether in person or by telephone) or reading the Presentation, you agree to be boun

  3. Slide 3: Company overview

    Company overview Kore is developing its globally significant potash deposits in the Republic of Congo (RoC) Ideally located to supply the important Brazilian agricultural market and high growth African markets District scale development potential with over 6 Bt of potash Mineral Resources1 located 3

  4. Slide 4: The Kola project - one deposit in a large potash district

    The Kola project - one deposit in a large potash district Kola sylvinite Ore Reserves, Mineral Resources and Exploration Target (JORC 2012) Kola is a world class asset with Measured + Indicated long life production potential Mineral Resources1 508 Mt Inferred Mineral Resources1 340 Mt Exploration Ta

  5. Slide 5: Comparing Kola to other MoP projects

    Comparing Kola to other MoP projects Kola is amongst the shallowest MoP Kola amongst the highest grade undeveloped projects globally potash deposits globally • Shaft bottom 270 m below surface • Deposits of comparative grade to Kola are over • Shallow deposit creates opex and capex 1,000 m deep adva

  6. Slide 6: Well situated for key export markets

    Well situated for key export markets Product is planned to be shipped to Brazil and West Coast African markets where Kola potash will netback best value Brazil is a large and growing agricultural producer with low natural soil quality Brazil is one of the three largest US$87.63/t importers of potash

  7. Slide 7: Kola DFS highlights

    Kola DFS highlights Industry leading operating costs: average cost of MoP delivered to Brazil of US$102.47/t, potential to be the lowest cost potash supplier to Brazil NPV110(real) of US$1,452M and IRR1 of 17.2% on an ungeared, attributable basis Long life: nameplate production target of 2.2Mtpa MoP

  8. Slide 8: Kola project configuration

    Kola project configuration • Targeting production of 2.2 Mtpa1 • Shallow: shaft bottom of 270m • 35km to the coast via an overland conveyor and dedicated jetty for export to Brazil and West Africa • 90km via road to port of Pointe Noire for equipment imports 8 1. Refer Kore’s market announcement dat

  9. Slide 9: Kola – low risk, industry standard flowsheet

    Kola – low risk, industry standard flowsheet MINE Pocket Overland Conveyor Conveyor Shaft Continuous Miner Shuttle Car Belt Conveyor Attrition Primary Product Scrubbing Flotation Debrining Product Drying PROCESS PLANT Crushing Salt Sea Product Debrining Disposal Screening Compaction Deslime Raw Ore

  10. Slide 10: DFS in numbers

    Kola DFS in numbers Key statistics (100% basis) Annual cash profile (US$M)2 Y1 – Y5 LoM 800 Unit average average Total LoM 600 MoP production kt 1,829 2,155 71,129 400 200 Granular MoP price - US$M US$/t 360 360 360 Y1 Y3 Y5 Y7 Y9 Y11 Y13 Y15 Y17 Y19 Y21 Y23 Y25 Y27 Y29 Y31 Y33 Y-4 Y-2 (Real, CFR Br

  11. Slide 11: Disruptively low cost of supply into targeted markets

    Disruptively low cost of supply into targeted markets Global Potash Export Cost Curve1 (FOB) US$/t MoP (2022) The DFS demonstrates that Kola potentially will be: • The second lowest cost operation on an export cost basis at US$87.63/t FOB (real 2018) • The lowest cost supplier globally of potash to

  12. Slide 12: Capital cost estimates

    Capital cost estimates Pre-production capital cost estimates1,2 Capex and production volume Cost 1,000 Production 2,500 Description Construction (US$M) 800 2,000 Mining 346 US$ million Process Plant 495 600 1,500 ktpa Roads 63 400 1,000 Marine Facilities 179 200 500 General Infrastructure 309 - - En

  13. Slide 13: Further optimisation of the DFS may yield additional value for shareholders

    Further optimisation of the DFS may yield additional value for shareholders Impact of Potential Improvements Independent consultants have reviewed specific aspects of the project DFS Impact on Economic Evaluation Identified opportunities to further improve the Potential Improvement IRR NPV10 project

  14. Slide 14: Kola Funding Plan

    Kola Funding Plan Kola Project Development Debt: US$1.0 – 1.4B • Pre-production capital of US$2.1B plus funding for working capital will be required Debt • Target debt funding of US$1.0 to 1.4B • Export Credit Agency (ECA) financing expected to ECA comprise large proportion of debt financing mix • D

  15. Slide 15: Kola - Timeline to Production

    Kola - Timeline to Production 2019 2020 Y-5 Y-4 Y-3 Y-2 Y-1 Y1 Competitive EPC negotiations1 EPC Financing Offtake Construction Site Preparation Ground Freezing Shaft Sinking Jetty Construction Conveyor Construction Plant Construction Production Commences 15 1. If Kore exercises its right to seek a

  16. Slide 16: Environment and Permitting

    Environment and Permitting Project close to being fully permitted Mining Convention, which secures the fiscal and operating regime is in place Transshipment license approved Amended Kola Environmental and Social Impact Assessment (ESIA) submitted for approval Mining Convention provides for Republic

  17. Slide 17: Kola Project next steps

    Kola Project next steps French Consortium (FC) contractually obliged to deliver a proposal for an Engineering, Procurement and Construction (EPC) contract within 3 months of the DFS completion Upon receipt of an EPC proposal, the existing contract between the parties provides up to 2 months for Kore

  18. Slide 18: Kola – investment summary

    Kola – investment summary Long life at globally Low Operating Cost Advantageous location significant scale Potential to be: • Initial life of Kola of 33 years • Close to export markets • Industry’s lowest cost potash based on 2.2Mtpa1 MoP • Own jetty and transshipment supplier to Brazil (US$102.47/t

  19. Slide 19: Appendix

    ORE POTASH Appendix RY FROM THE GROUND UP

  20. Slide 20: More potash needed to feed the world

    More potash needed to feed the world The world will need to grow 50% more food … while global arable land per person is by 2050 to feed an anticipated population of declining sharply 9 billion people... 0.4 Hectares per person 0.35 0.3 0.25 0.2 0.15 0.1 1960 1964 1968 1972 1976 1980 1984 1988 1992 1

  21. Slide 21: Potash supply and demand

    Potash supply and demand 2017 Supply Total annual production of potash West Southeas (MoP) is around 66 Mtpa t Asia Europe 4.0 Mt 0.4 Mt East Asia 7.1 Mt At present this supply is largely met by North existing major suppliers including: America 65.0 Mt FSU 21.8 Mt 23.5 Mt • Urakali – 12.2 Mtpa • Nut

  22. Slide 22: Potash historical prices

    Potash historical prices 850 750 650 550 US$/t 450 US$360/t 350 250 150 Nov-04 Sep-07 Jul-10 May-13 Mar-16 Jan-19 Vancouver FOB Brazil Potash CFR Granular Source: Bloomberg 22

  23. Slide 23: Kore's broader potash portfolio

    Kore’s broader potash portfolio Dougou Extension Sylvinite Deposit • 232 Mt Mineral Resources1 • Grade 38.1% KCl • Contains some very high grade areas – 57 to 60% KCl • Mining licence granted, mining convention signed • Potential to provide feed to extend life or increase scale at Kola Dougou Carnal

  24. Slide 24: Ore Reserves

    Ore Reserves Kola Sylvinite Ore Reserves (gross 100% basis) Ore Reserves KCl grade Mg Insolubles Classification (Mt) (% KCl) (% Mg) (% Insol.) Proved 61.8 32.1 0.11 0.15 Probable 90.6 32.8 0.10 0.15 Total Ore Reserves 152.4 32.5 0.10 0.15 Notes: • The Kola Ore Reserves Estimate is reported in accord

  25. Slide 25: Mineral Resources — Sylvinite

    Mineral Resources — Sylvinite Sylvinite deposits (gross 100% basis) Contained KCl Mineral Resource category Million Tonnes Grade KCl % Million tonnes Kola Sylvinite Measured 216 34.9 75 Indicated 292 35.7 104 Sub-total (Measured + Indicated) 508 35.4 180 Inferred 340 34.0 116 TOTAL 848 34.8 295 Doug

  26. Slide 26: Mineral Resources — Carnallite

    Mineral Resources — Carnallite Carnallite deposits (gross 100% basis) Contained KCl Mineral Resource category Million Tonnes Grade KCl % Million tonnes Dougou Carnallite Measured 148 20.1 30 Indicated 920 20.7 190 Sub-total (Measured + Indicated) 1,068 20.6 220 Inferred 1,988 20.8 414 TOTAL 3,056 20

  27. Slide 27: Exploration Targets

    Exploration Targets The potential quantity and grade of an Exploration Target is conceptual in nature and is an approximation, and is expressed as an expected range of tonnes and grade. There has been insufficient exploration at Kola South and DX North to estimate Mineral Resources and it is uncerta

  28. Slide 28: DFS delivery team

    Kola DFS delivery team Scope of DFS Responsibility Project Management Geology and Mineral Resource Estimate Geotechnical and Hydrogeology Mining and Shafts Processing and Metallurgical Testwork Infrastructure and Utilities Construction Marine and Transhipment Environmental Marketing 28

  29. Slide 29: Kola Mineral Resource classification

    Kola Mineral Resource classification 29

  30. Slide 30: Kola site layout

    Kola site layout 30 Note: Refer Kore’s market announcement dated 29 Jan 2019 entitled ‘Kola Definitive Feasibility Study’

  31. Slide 31: Kola opex detail

    Kola opex detail Cost Category Real 2018 costs (US$/t MoP) Mining Cost 21.70 Processing Cost 25.77 General infrastructure Cost 4.57 Owners Cost 9.67 Mine Gate Operating Costs 61.71 Sustaining Capex 10.98 Product Realisation Charges and Allowances 1.89 Royalties 8.67 Ex Works Cost 83.25 Logistics to

  32. Slide 32: Board of Directors

    Board of Directors David Hathorn Chairman Brad Sampson Chief Executive Officer David was the CEO of the Mondi Group between 2000 and May Brad, a qualified mining engineer, has more than 25 years’ 2017 having joined the group in 1991. Prior to the demerger of resources industry experience across nume

  33. Slide 33: Corporate snapshot

    Corporate snapshot Key shareholders KP2 AIM share price / volume 18 25 Shareholder % interest 16 14 20 Volume (Millions) Princess Aurora Company Pte Ltd (SGRF) 19.02% Share price (p) 12 15 Sociedad Quimica y Minera (SQM) 17.52% 10 8 Harlequin Investments Ltd 12.02% 10 6 Dingyi Group Investments Ltd