Suncor Energy Inc. · TSX:SU

Suncor Energy — Corporate Update (October 2015)

17 slides from Suncor Energy's corporate update, Oct 1, 2015

  1. Slide 1: Adelaide Community Liaison Committee Meeting #4

    Due to changes to the Competition Act, pending regulatory guidance, this document is provided for historical En raison des changements apportés à la Loi sur la concurrence, en attendant l'orientation réglementaire, ce document information purposes only and does not constitute an active or current re

  2. Slide 2: Agenda

    Agenda • Welcome: agenda and goals • Safety moment • Introductions • Follow-up from Meeting #3 • Project Update • Remediation • Sound testing • Post-Construction wildlife monitoring • Community Q&A • Future communications • Contacting Suncor • Project information/updates to the community • Recogniti

  3. Slide 3: Safety Moment - Hunting Safety

    SAFETY MOMENT- HUNTING SAFETY How to Prepare • Make sure your Firearm is working properly. • If you are traveling by ATV or other utility vehicle, make sure you are aware with ATV safety tips. • Make sure you have all the required licenses. • Let a family or friend know where you are going exactly a

  4. Slide 4: Safety Moment - Hunting Safety

    SAFETY MOMENT- HUNTING SAFETY Hunting on Private property and Near Infrastructure • Always get landowner permission in writing and keep a copy with you at all times. This protects you and the Landowner in the event of an incident. • Carry extra insurance like Personal Public Liability Insurance to p

  5. Slide 5: Introductions

    INTRODUCTIONS CLC Members Suncor • Henry Aukema • Jason Weir- Operations Supervisor • Eric Denison • Chris Scott- Project development • Frank Devet • Jocelyn Kelln- Stakeholder and Aboriginal • Rolanda Elijah (for Fallon Burch) Relations • Donna Hornblower • Dean Jacobs • Jocelyn Kelln • Brian Lima

  6. Slide 6: Follow-up from CLC Meeting #3

    FOLLOW-UP FROM CLC MEETING #3 Provide a comparison of decibel levels to everyday examples 6

  7. Slide 7: Follow-up from CLC Meeting #3

    FOLLOW-UP FROM CLC MEETING #3 Request to continue sound testing for one full year past commercial operating date. Request to meet an additional time once all sound testing has been completed. • Has been added to agenda 7

  8. Slide 8: Adelaide Update

    ADELAIDE UPDATE Completed and ongoing work Upcoming Work • Beginning in October, we will be changing • 500hr and annual substation maintenance the main bearings on two turbines in now complete • This will require a large standing crane, • Annual maintenance is ongoing and we similar to the ones you

  9. Slide 9: Monitoring and Mitigation: Acoustics: Compliance at Homes

    MONITORING AND MITIGATION Acoustics: Compliance at Homes • Noise measurements began on April 7th 2015 at three non participating residences within the project area. • Measurements at one residence are completed and the facility was determined to be in compliance with Ministry of Environment limits •

  10. Slide 10: Monitoring and Mitigation: Acoustics: Compliance of Equipment

    MONITORING AND MITIGATION Acoustics: Compliance of Equipment Substation Transformer: • Testing of the main transformer was completed in January 2015 in accordance with REA • The main transformer was found to be 89 dBA and no tonality was observed. This is well below the 101 dBA limit specified in th

  11. Slide 11: Monitoring and Mitigation: Birds and Bats

    MONITORING AND MITIGATION Birds and Bats • Monitoring is required for three years following the start of operations • Monitoring at 10 turbine sites out of 18 began in April of 2015 and will conclude in November of 2017, dependent on the outcomes • Trained biologists conduct regular sweeps of the ar

  12. Slide 12: Complaints and Questions

    COMPLAINTS AND QUESTIONS Contact • Call: 1-866-344-0178 Suncor • Email: adelaide@suncor.com Immediate • Investigation launched by actions site operator • You will be contacted by a project representative Investigation • A one-on-one meeting may be required • Discuss the outcomes of the Resolution in

  13. Slide 13: Where to Get Information

    Where to get information Website Email Telephone www.suncor.com/ adelaide@suncor.com 1-866-344-0178 adelaidewind 13

  14. Slide 14: What's Next?

    What’s Next? ~

  15. Slide 15: Future Project Updates

    FUTURE PROJECT UPDATES How would you like to stay in touch? Let us know at adelaide@suncor.com or by calling 1-866-344-0178 15

  16. Slide 16: Future Communications

    FUTURE COMMUNICATIONS KEEP UP TO DATE • Suncor Connections 16

  17. Slide 17: Thank You!

    THANK YOU! 17 SUNCOR

Suncor Energy — Corporate Update (October 2015) on 6ix