  1. Slide 1: Agency Consultation Meeting

    Agency Consultation Meeting Oakdale West Estate February 2022 1

  2. Slide 2: Overview

    Overview Welcome and Introductions Upcoming Developments Project Update – OWE Project Update – Buildings Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2

  3. Slide 3: Welcome and Introductions

    Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Dan Thompson Carl Vincent Caitlin D’Arcy Kiera Plumridge Alasdair Cameron Kate McKinnon Lachlan O’Reilly Luke Ridley 3

  4. Slide 4: Oakdale West Estate site plan

    + REFER TO DRAWING OAK MPO3 FOR CONTINUATION oodmar ‘OAKDALE SOUTH Emme neasentn Lot 12 0P1178389 Katie Oo ‘rage Re 5600 Enpraus Cate Keay RE 8400 Oakdale West Estate - MOD 9 PASSES E thc [ ptt To P.0003 ) Site Area Schedule Total She Area 154.12 ha Les ‘Non Devote Land 2108 he Ensemerss| 2238 he Fe

  5. Slide 5: Upcoming Developments

    Upcoming Developments Current Development Application Status • New PCC DA for Building 3C – to be submitted April 2022 5

  6. Slide 6: Upcoming Developments

    Upcoming Developments • New PCC DA for Building 5A – to be submitted April 2022 6

  7. Slide 7: Upcoming Developments

    Upcoming Developments • New PCC DA for Amenities Lot – to be submitted April 2022 7

  8. Slide 8: Progress To Date & Upcoming Works – Building 1A

    Progress To Date & Upcoming Works – Building 1A • Site Commencement 8th July 2020 • Installation of Site Sediment Control Measures • Completion of Trailer Wash • Cladding At 95% Complete • Internal Dock Levellers Have Commenced Being Cast • Internal Façade Building Closure 8

  9. Slide 9: Progress To Date & Upcoming Works – Building 1B/1C

    Progress To Date & Upcoming Works – Building 1B/1C • Site Commencement 20th August 2021 • Installation of Site Sediment Control Measures • Precast Panels Complete • In-Ground Stormwater Installation Progressing • Warehouse Structural Steel Installation Complete • Concrete Pours to External Hardstand

  10. Slide 10: Progress To Date & Upcoming Works – Building 2A

    Progress To Date & Upcoming Works – Building 2A • Site Commencement 5th January 2022 • Installation of Site Sediment Control Measures • In-Ground Stormwater Drainage Commencement • Foundations forecast to Commence February 2022 • Structural Steel Delivery and Erection Commencement • Bulk Excavation

  11. Slide 11: Progress To Date & Upcoming Works – Building 2B

    Progress To Date & Upcoming Works – Building 2B • Site Commencement 1st June 2020 • Development Achieved Practical Completion 22nd December 2021 • Building 2B is now operational as of 2nd February 2022 when outbound operations commenced 11

  12. Slide 12: Progress To Date & Upcoming Works – Building 3A

    Progress To Date & Upcoming Works – Building 3A • Site Commencement 23rd August 2021 • Installation of Site Sediment Control Measures • Warehouse Structural Steel installation • Warehouse Cladding installation • External hardstand preparation and installation • Main Office Construction 12

  13. Slide 13: Progress To Date & Upcoming Works – Building 3B

    Progress To Date & Upcoming Works – Building 3B • Site Commencement 15th December 2021 • Installation of Site Sediment Control Measures • Bulk Earthworks pad trimming and levelling • In-ground stormwater service installation • Warehouse Structural Steel installation 13

  14. Slide 14: Progress To Date & Upcoming Works – Building 4E

    Progress To Date & Upcoming Works – Building 4E • Site Commencement 13th November 2021 • Installation of Site Sediment Control Measures • Structural Steel Erection Commenced • In-Ground Stormwater Commencement • Bulk Earthworks pad trimming and levelling 14

  15. Slide 15: Progress To Date & Upcoming Works - OWIE

    Progress To Date & Upcoming Works - OWIE Progress to Date: • Road 8 service installation and road construction works completed and dedication process to council is underway • Precinct 3 & 4 Bulk Earthworks and retaining walls are nearing completion • Lot 4A Right of way construction has commenced an

  16. Slide 16: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1-4 TOTAL 42 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – JUN) 11 2021 QTR 7 (JULY – SEP) 12 2021 QTR 8 (OCT - DEC) 15 2022 QTR 9 (JAN-FEB Part) 5 TOTAL TO DATE 94 Copyright © ErSed 2011

  17. Slide 17: ER Inspections and Audits: SSD7348

    ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD NIL Copyright © ErSed 2011

  18. Slide 18: Environmental Performance: SSD7348

    ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES OR INCIDENTS NIL Copyright © ErSed 2011

  19. Slide 19: Environmental Performance: SSD7348

    ENVIRONMENTAL PERFORMANCE: SSD7348 COMPLAINTS NIL Copyright © ErSed 2011

  20. Slide 20: EC Inspections and Audits- SSD10397

    EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY –DEC 2020 7 JANUARY 21 0 FEBRUARY 21 1 MARCH 21 5 APRIL 21 1 MAY 21 1 JUNE 21 2 (1 Inspection + 1 Audit) JULY 21 0 AUG 21 2 SEPT 21 0 OCT 21 1 NOV 21 1 DEC 21 1 & FINAL TOTAL 22 Copyright © ErSed 2011

  21. Slide 21: Environmental Performance- SSD10397

    ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTHLY REPORTS INCIDENTS NIL NON COMPLIANCES NIL Copyright © ErSed 2011

  22. Slide 22: Environmental Performance- Other Lots

    ENVIRONMENTAL PERFORMANCE- OTHER LOTS INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTHLY REPORTS OTHER LOTS INSPECTIONS GENERALLY MONTHLY LOT 1BC LOT 2A LOT 3AB LOT 4E INCIDENTS AND NON COMPLIANCES NIL Copyright © ErSed 2011

  23. Slide 23: Safety

    Safety There have been no safety incidents to report since the last meeting. 23

  24. Slide 24: Consultation and Community Interactions

    Consultation and Community Interactions There have been no consultation occurrences to report since the last meeting. 24

  25. Slide 25: Communications and Consultation Channels

    Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E

  26. Slide 26: Stakeholder Feedback & Questions

    Stakeholder Feedback & Questions 26