Transurban Group Ltd. · ASX:TCL

Transurban — Investor Presentation (May 2020)

34 slides from Transurban's investor presentation, May 4, 2020

  1. Slide 1: New M5–St Peters Interchange, Sydney

    NEW M5–ST PETERS INTERCHANGE, SYDNEY

  2. Slide 2: Disclaimer

    DISCLAIMER This publication is prepared by the Transurban Group comprising Transurban Holdings Limited (ACN 098 143 429), Transurban Holding Trust (ARSN 098 807 419) and Transurban International Limited (ACN 121 746 825). The responsible entity of Transurban Holding Trust is Transurban Infrastructur

  3. Slide 3: Agenda

    AGENDA 04 TRADING UPDATE AND OUTLOOK 16 TRAFFIC INSIGHTS X 27 QUESTION AND ANSWER SESSION SCOTT CHARLTON DARRYN PATERSON EXECUTIVE COMMITTEE CEO GM STRATEGY AND TRAFFIC AND SENIOR LEADERS INVESTOR BRIEFING | 4 MAY 2020 3

  4. Slide 4: Clear Priorities

    CLEAR PRIORITIES Transurban Above all else, we Our roads are fully We have enhanced We continue to operates essential will do everything operational and our financial operate our infrastructure and we can to keep our we will continue to support for business safely is clear on its employees, get peop

  5. Slide 5: Traffic Update

    TRAFFIC UPDATE • COVID-19 traffic impacts observable from early Recent traffic data (ADT % change)3 March with traffic deteriorating then improving Week in the second half of April1 commencing 1 Mar 8 Mar 15 Mar 22 Mar 29 Mar 5 Apr 12 Apr 19 Apr 26 Apr2 Sydney (1%) (2%) (10%) (29%) (42%) (51%) (51%)

  6. Slide 6: Customers

    CUSTOMERS • Transurban is supporting those customers in most need throughout this crisis Toll credit initiative • Providing financial support to our customers who are on the frontline1 in addition to those • Providing financial support to experiencing hardship as a result of COVID-19, applied throug

  7. Slide 7: People and Operations

    PEOPLE AND OPERATIONS • Transurban is maintaining employment for its direct workforce and thousands of A long-term focus on flexible working, subcontractors to operate our assets, deliver our major projects, and come out the other underpinned by a significant investment side of the COVID-19 crisis i

  8. Slide 8: Delivery Update

    DELIVERY UPDATE Transurban continues to work with contractors and governments to deliver its portfolio of large-scale, highly complex projects, keeping thousands of people in local jobs and supporting the supply chain through this crisis NORTHCONNEX NEW M5 WEST GATE TUNNEL1 • Works continuing across

  9. Slide 9: West Gate Tunnel Progress Video

    WEST GATE TUNNEL PROGRESS VIDEO

  10. Slide 10: Capital Position

    CAPITAL POSITION • Sufficient liquidity to meet capital Transurban expects the 2H20 distribution FREE CASH CALCULATION requirements and debt refinancing will be declared in late June 2020 and paid in obligations to end of FY21 August 20202 Cash flows from operating activities (refer Group Statutory

  11. Slide 11: Treasury Management

    TREASURY MANAGEMENT Our consistent investment thesis is underpinned by concession agreements and remains critical to ensuring that Transurban has continued access to capital markets Transurban credit ratings Transurban debt covenants • Commitment to maintain strong investment grade credit ratings •

  12. Slide 12: Leadership

    LEADERSHIP • Leadership operating model to position Executive Committee Transurban for the future • Consolidation and expansion of executive Chief Financial Officer Adam Watson positions as well as increasing capability to take advantage of emerging opportunities: Group Executive, Global search Part

  13. Slide 13: Opportunity Pipeline

    OPPORTUNITY PIPELINE Increased need for private-sector investment to fund infrastructure and drive growth on the other side of COVID-19 Potential market opportunities • Government-owned 49% WestConnex minority interest (Sydney) • Western Harbour Tunnel (Sydney) • Coomera Connector (Brisbane) • Maryl

  14. Slide 14: Sustainability

    SUSTAINABILITY Transurban is recognised as a global sustainability leader in the infrastructure and transport sectors and is increasingly integrating sustainability into all aspects of business strategy, planning and operations Goals Subject areas Priorities and programs Recognitions and People • He

  15. Slide 15: Summary

    SUMMARY • Transurban continues to prioritise the health and safety of our employees, contractors and customers through this period • Our roads remain fully operational, playing an essential function to move people, goods and services where they need to go during this time of crisis • Traffic impacts

  16. Slide 16: Transurban Traffic Insights

    Transurban TRAFFIC INSIGHTS DARRYN PATERSON—GM STRATEGY AND TRAFFIC

  17. Slide 17: Theoretical Traffic Impact Timeline

    THEORETICAL TRAFFIC IMPACT TIMELINE INITIAL IMPACT SUPPRESSION PEAK IMPACT STAGED RECOVERY STATUS QUO Impacts based on Increasing Sustained Recovery period characterised by: Post COVID-19 situation; observed performance on government period of • Progressive and targeted unwinding where economic reco

  18. Slide 18: Observed Impacts to Date

    OBSERVED IMPACTS TO DATE • Impacts to traffic on Transurban’s assets observable from the beginning of March with rapid deterioration through the month • Through April, government-mandated restrictions remained stable resulting in a gradual stabilisation of traffic • Assets highly utilised by the log

  19. Slide 19: Traffic Impact Insights

    TRAFFIC IMPACT INSIGHTS Large vehicle traffic more Weekly traffic performance by vehicle class1 • Weekend traffic impacts more resilient to government 80% significant due to higher levels restrictions given the LEGEND of discretionary travel relative 70% ongoing need for freight Large Vehicle ADT to

  20. Slide 20: Traffic Impact Insights

    TRAFFIC IMPACT INSIGHTS • Congestion an inexact proxy for traffic with a disproportionate relationship between the two Trip generation across our markets measures driven by diverse reasons for travel • High levels of traffic don’t necessarily result in high levels of congestion Trip sources4 – Conge

  21. Slide 21: Transurban Relative to Other Global Toll Roads

    TRANSURBAN RELATIVE TO OTHER GLOBAL TOLL ROADS • Toll roads in other countries which were Performance of other global toll roads1,2 impacted earlier by COVID-19 showing 30% signs of stabilisation and initial recovery Initial ban on gatherings 15/3 Impacted by timing of Easter holidays in 2020 Impact

  22. Slide 22: Early Signs of Recovery in China

    EARLY SIGNS OF RECOVERY IN CHINA • China showing signs of recovery as lockdown measures are Congestion levels in Chinese cities1 gradually removed LEGEND BEIJING SHANGHAI 2019 average – Key business indicators showing positive signs across major 80% 80% 16-Mar CONGESTION LEVEL industries 60% 60% – R

  23. Slide 23: Stabilisation and Staged Recovery Considerations

    STABILISATION AND STAGED RECOVERY CONSIDERATIONS • Australia’s progress in containing the Staged recovery considerations outbreak has exceeded the • The removal of restrictions is expected to be staged with the rate of traffic recovery expectations of health officials as contingent on the sequence a

  24. Slide 24: Longer-Term Considerations

    LONGER-TERM CONSIDERATIONS • Transurban has been considering Potential factors reducing traffic growth Potential factors increasing traffic growth potential long-term changes to • Near-term macro economic factors are • The enforcement or preference for transport for a long period and has expected to

  25. Slide 25: Summary

    Transurban SUMMARY SCOTT CHARLTON—CEO

  26. Slide 26: Summary

    SUMMARY Continued focus Transurban roads Enhanced financial Sufficient liquidity Early signs of on the health and are fully support for in place to meet traffic stabilisation safety of our operational and customers and capital and debt with Transurban employees, transporting other members of refinan

  27. Slide 27: Questions and Answers

    QUESTIONS AND ANSWERS

  28. Slide 28: Investor Enquiries

    Transurban INVESTOR ENQUIRIES Tess Palmer Head of Investor Relations +61 458 231 983 MEDIA ENQUIRIES Sarah Chapman Manager, Media and Communications +61 400 841 898

  29. Slide 29: Supplementary Information

    SUPPLEMENTARY INFORMATION

  30. Slide 30: Government Responses

    GOVERNMENT RESPONSES Australia (Melb / Syd / Bris) USA (Greater Washington Area) Canada (Montreal) Measures across the eastern seaboard have been substantially USA Canada coordinated through national directives MANDATORY GOVERNMENT MEASURES 11 March 2020 16 March 15 March 2020 International travel (

  31. Slide 31: Traffic Update

    TRAFFIC UPDATE • Traffic data impacted by the following Recent traffic data (ADT % change)1 events during the period: – Public holidays: Week commencing 1 Mar 8 Mar 15 Mar 22 Mar 29 Mar 5 Apr 12 Apr 19 Apr 26 Apr2 • Easter weekend: 10-13 April 2020 Sydney (NSW) (1%) (2%) (10%) (29%) (42%) (51%) (51%

  32. Slide 32: Treasury Management

    TREASURY MANAGEMENT Ratings agency updates since COVID-19 outbreak1 Transurban debt covenants • Moody’s affirmed the Transurban Finance Company Pty Limited Distribution rating of ‘Baa1’ and Stable outlook Debt Default lock-up 31 December Asset covenant2 threshold threshold 2019 • S&P affirmed the Tr

  33. Slide 33: Leadership

    LEADERSHIP Simon Moorfield Group Executive, Customer and Technology Simon joins Transurban Group from AGL, where he was EGM Future Business & Technology and Chief Information Officer (CIO). He has over 25 years’ experience in technology, innovation and transformation gained across roles held in Aust

  34. Slide 34: Glossary

    GLOSSARY TERM DEFINITION TERM DEFINITION 95 95 Express Lanes GHG Greenhouse gas 395 395 Express Lanes GRESB Global Real Estate Sustainability Benchmark 495 495 Express Lanes GROUP Transurban Group 1H/2H First or second half of a financial year Greater Washington Area meaning northern Virginia, Washi

Transurban Group — Investor Presentation (May 2020) on 6ix