  1. Slide 1: Northern Territory Mining

    NORTHERN TERRITORY MINING For personal use only

  2. Slide 2: Outline

    Outline For personal use only  Scoping Study Results  Key Drivers of Project Economics  Feasibility Studies  Resource and Exploration drilling programs 2

  3. Slide 3: Location

    Location For personal use only Transport route from Jervois  221km unsealed road (Plenty Hwy)  73km bitumen (Plenty Hwy)  1,300km rail to port of Darwin 3

  4. Slide 4: Project History

    Project History For personal use only  First discovered 1928  Plenty River Mining 1980-83 – Mining Green Parrot Lead deposit  MIM – Deeper drilling  Reward Minerals – RC drilling on several prospects  Kentor Gold – 2011& 2012 Drilling Programs – Resource Updates 2011,12,13 – Scoping Study – Jan

  5. Slide 5: Post Scoping Study

    Post Scoping Study For personal use only Cost Reduction Revenue Increase  Construction – Value  Copper, Silver, Gold engineering study concentrate –  Power – Value engineering Remove/reduce penalties study  Improved Recoveries  Resource upgrade and increase Potential New Products  Copper catho

  6. Slide 6: Construction - Value Engineering Study

    Construction - Value Engineering Study For personal use only Capital Cost Breakdown  Reduced capital cost to 1.5Mtpa A$m ∆ A$m A$185.5m Construction Indirects 14.9 14.4 29.3  Increases 58 Process Plant Costs 59.1 -1.1 – camp rental for construction Reagents & Plant period 10.7 -1.2 9.5 Services 

  7. Slide 7: Magnetite Concentrate

    Magnetite Concentrate For personal use only  Ore is hosted in Magnetite schist  Magnetic separation of tails – ~ 25% of tails mass  Regrind produces – high grade concentrate +70%Fe – Low impurity  Silica ~1.3%  Phosphorous ~0.004%  Alumina ~0.6%  Sulphur ~0.3% (higher than spec)  Possible Tu

  8. Slide 8: Copper Oxide Resource

    Copper Oxide Resource For personal use only Assessing feasibility of copper heap leach in advance of flotation • High average grade • Good exploration potential • Historical test work successful Jan 2013 Resource kT Cu % Ag g/t Marshall/Reward Oxidised 196 1.43 42.5 Partially Ox. 829 1.71 45.6 Bellb

  9. Slide 9: Bismuth

    Bismuth For personal use only  Some areas of the deposit have elevated bismuth  Leach tests on the copper concentrate with NaCl and H2SO4 addition  Tests on concentrate with the highest bismuth levels were very successful  Further bismuth leach evaluation will be conducted. 100 Metal Extraction

  10. Slide 10: Sustainability

    Sustainability For personal use only  Environmental surveys in July 2012 and a contrasting survey in April 2013  AAPA clearance process is being conducted now  Preliminary meeting held with Central Land Council (CLC) in 2012. Further meetings planned  Draft Notice of Intent (NOI) is prepared 10

  11. Slide 11: Resource Development

    Resource Development For personal use only Identified Exploration Potential adjacent to existing resource Outcropping Copper Ore 11

  12. Slide 12: 2012 Development drilling

    2012 Development drilling For personal use only Contained Copper Indicated Inferred TOTAL  13.5Mt @ 1.3% copper 25.8g/t Ag Marshall/Reward 68,166 43,613 111,779  13% increase in contained copper Bellbird 33,073 16,564 49,637  20% increase contained silver Green Parrot 7,000 7,000 Bellbird North 2

  13. Slide 13: Marshall - Reward Long Section

    Marshall - Reward Long Section For personal use only 1.2 km 0.5 km 13

  14. Slide 14: Marshall Reward Drilling

    Marshall Reward Drilling For personal use only  Step-out drilling targeting significant increase and upgrade of resource  Program 1 (white) – 3,395m RC – 1,395m Diamond  Program 2 (red) – Phase 1  7,748m RC  2,950m Diamond – Phase 2  5,789m RC  2,754m Diamond 14

  15. Slide 15: Marshall-Reward Planned Drilling 2013-14

    Marshall-Reward Planned Drilling 2013-14 For personal use only Red blocks – Indicated Yellow blocks - Inferred 15

  16. Slide 16: Bellbird Long Section

    Bellbird Long Section For personal use only 800 m 400 m 16

  17. Slide 17: Bellbird Planned Drilling 2013-14

    Bellbird Planned Drilling 2013-14 For personal use only Long Section  Previously only 7 holes below 200m  Program 1 (white) – 3,053m RC – 210m Diamond  Program 2 (red) – Phase 1  4,037m RC  659m Diamond – Phase 2  2,677m RC  1,201m Diamond Red blocks – Indicated Yellow blocks - Inferred Plan

  18. Slide 18: Exploration - Bellbird

    Exploration - Bellbird For personal use only 2012 Kentor Drilling  Mineralisation open to north  Best gold assays on northern most line  6m @ 1.2% copper, 10.3g/t silver and 12.43g/t gold from 64 m (down hole), including • 2m @ 2.3% copper, 21g/t silver and 35.2g/t gold from 65 m 18

  19. Slide 19: Exploration - Bellbird

    Exploration - Bellbird For personal use only Geophysics – IP  MIM completed IP in 1999- 2001  Good correlation between Chargeability and known mineralisation  Several strong Chargeability anomalies untested 19

  20. Slide 20: Exploration - Reward North

    Exploration - Reward North For personal use only 2011 Kentor Drilling Reward Extension  72m @ 3.3% Cu, 51.2 g/t Ag, 1.16 g/t Au from 414m (Hole RJ169) 2012 Kentor Drilling  8.0m @ 4.8% Cu, 62.1g/t Ag, 0.35g/t Au from 502m (Hole RJ204)  9.05m @ 4.9%Cu, 66.2g/t Ag, 1.22g/t Au from 509m (Hole RJ204W

  21. Slide 21: Exploration – Marshall & Green Parrot

    Exploration – Marshall & Green Parrot For personal use only Green Parrot Potential extension to the North  32m @ 1.1% Cu, 1.2% Pb, 1.4% Reward Eastern Zn, 60.4 g/t Ag, 0.12g/t Au from Zone surface (Hole RJ242) Marshall Green Parrot Extension Marshall Extension  Potential extension to the South Rew

  22. Slide 22: Exploration Potential

    Exploration Potential For personal use only Chubko Prospect  Discovered due to ASTER work conducted by the NTGS in collaboration with the CSIRO led Centre of Excellence for 3D Mineral Mapping  ASTER (Advanced Space-borne Thermal Emission and Refraction Radiometer) Morley Prospect  Field mapping a

  23. Slide 23: PFS Timetable

    PFS Timetable For personal use only 2014 July Aug Sept Oct Nov Dec Feb ACTIVITY Jan Prefeasibility Study (PFS) DFS → Environ. Baseline Studies, Impact Assessment Environmental Permits & Approvals Community & CLC Engagement Surveys Resource Drilling Resource Upgrade Mine Design, Planning & Optimisati

  24. Slide 24: Jervois – The future

    Jervois – The future For personal use only  Drilling planned to commence Aug 2013  Targeting a significant increase in Resource  Resource update targeted for Dec 2014  Further exploration drilling to test high priority targets  Scoping study of oxide copper resource  Complete Pre-Feasibility S

  25. Slide 25: For more information contact

    For more information contact For personal use only Simon Milroy on +61 7 3071 9003 or visit www.kentorgold.com ASX Code: KGL Level 9, 40 Creek Street, Brisbane, QLD, AUSTRALIA 4000 Fax: +61 7 3071 9008 Forward-Looking Statements: This presentation includes certain “Forward-Looking Statements”. All s