Rio2 Limited · TSX:RIO

Rio2 — Investor Presentation (September 2026)

31 slides from Rio2's investor presentation, September 2026

  1. Slide 1: Building a Leading Latin American Miner

    Building a Leading Latin American Miner September 2026 0

  2. Slide 2: Reader Advisory

    Reader Advisory Cautionary Statement Regarding Forward-Looking Statements This presentation contains certain information that may constitute “forward-looking information” and “forward-looking statements” within the meaning of applicable securities laws. All statements other than statements which are

  3. Slide 3: Company Snapshot

    Company High Quality Operations Peru • Fenix Gold mine in Chile Snapshot • Condestable mine in Peru Scale and Growth • Fenix Gold Phase 1: 100 kozs Au per year1 Rio2 Office • Fenix Gold Phase 2: 300 kozs Au per year2 • Condestable: 26 kt CuEq per year (or ~80 kozs AuEq)3 • Low capital expansion pote

  4. Slide 4: The Team

    The Team Board of Directors Executive Management Executive Chairman President & CEO CFO SVP Corporate SVP Geology SVP Finance SVP Mining Construction Strategic Finance Mining Development Management Communications Geology Communications IT Administration Corporate Legal & Social HR Environment Govern

  5. Slide 5: H1 2026 Highlights

    Fenix Gold Ramp-up Progress - Key Constraints overcome - Winter arrives early • Water transport continues to perform to expectations; water consumption has been about 25% below planned levels due to higher humidity in mined material vs expected. • Operators and truck issues resolved with operations

  6. Slide 6: Corporate Snapshot

    Corporate Snapshot Capitalization and Balance Sheet Share Price Performance Relative Performance Over the Last Two Years Share Price (as at September 18, 2026) C$ $3.64 $4.50 22.5 Rio2: 487% Basic shares outstanding M 550.8 -- vs – FDITM shares outstanding M 566.5 $4.00 GDJX: 169% and Gold Price: 71

  7. Slide 7: Q3 Monthly Production

    Tonnes Ounces Q3 Monthly Production 60,000 July 700 50,000 600 40,000 500 400 30,000 Gold Production 2026 - Fenix Gold (oz) 20,000 300 200 8,000 10,000 100 7,000 - - 7,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 6,000 Day 6,000 August 50,000 700 5,000 4,60

  8. Slide 8: High Quality Portfolio

    High Quality Portfolio FENIX GOLD | CORNERSTONE OPERATION CONDESTABLE | CASH FLOW GENERATOR Construction Annual Production1 Expanded Production 2 Operating History Annual Production Expansion Potential Complete Phase 1: 100 kozs Phase 2: 300 kozs +60 years, consistent ~20 ktpa Cu3 8.4 ktpd to 12 ktp

  9. Slide 9: Significant Growth and Scale

    Significant Growth and Scale Annual Gold Eq. Production Scale (kozs) Annual Mine EBITDA (US$M)4 77 kozs AuEq (26 kt CuEq)2 Phase 2 Expansion3 80,000 tpd 300 kozs 77 kozs AuEq (26 kt CuEq)2 Phase 1 1 Phase 1 1 20,000 tpd 20,000 tpd 100 kozs 100 kozs 1. Based on the average of 2027 to 2030 from the Fe

  10. Slide 10: Metal Price Leverage

    Metal Price Leverage Mine NPV (US$B)1 Annual Mine EBITDA (US$M)2 1. Based on the stated NPVs from the Fenix and Condestable TRs (assessed at January 1, 2026). Excludes the impact of the streams and prepay 2. Non-IFRS financial measure. Based on the average of 2027 and 2028 from the Fenix and Condest

  11. Slide 11: The Growth Plan

    The Growth Plan MILESTONE 2026 2027 2028 2029 2030+ Ramp-Up Production of ~100 kozs1 per year based on initial ore mining rate of 20,000 tpd Phase 1 Production 20ktpd Phase 2 Q4 2026 Pre-Feasibility Study Near Mine Q1 2027 Exploration Mineral Reserve and Q3 2027 Resource Update Phase 2 Engineering P

  12. Slide 12: 11

    11

  13. Slide 13: The Newest Gold Mine in Chile

    The Newest Gold Mine in Chile One of the largest gold heap leach mines in the Americas • Construction is complete – on time and on budget On Track Toward • First gold pour occurred in January 2026 Ramp-Up • Ramp-up during 2026 to be achieved, 100 kozs/yr1 in 2027 • The only 100% oxide gold project i

  14. Slide 14: Mine Update Photos

    Mine Update Photos 1 2 3 1 2 3 4 5 1. LEACH PAD 2. MINING AT FENIX SOUTH 3. OPERATIONS INFRASTRUCTURE COVERED IN SNOW 4. CLEARING HAUL ROADS 5. LEACH PAD REPAIRS

  15. Slide 15: Massive Outcropping Oxide Orebody

    Massive Outcropping Oxide Orebody 14

  16. Slide 16: Resource Growth Potential

    Resource Growth Potential CONCEPTUAL DRILLING TARGETS 15

  17. Slide 17: Phase 2 Water Supply

    Phase 2 Water Supply The future water source for the expansion of the Fenix Gold mine will be DESAL Fenix Gold has signed memoranda of understanding with potential desal suppliers, undertaking studies to evaluate the expansion or construction of desalination plants, construction of pipelines and ass

  18. Slide 18: Condestable

    DESTABLE

  19. Slide 19: A Solid Operation with Upside

    A Solid Operation with Upside • Located 90 km south of Lima, Peru; 100 km from the Port of Callao near Lima • Established operating history of over 60 years – a stable, proven asset Proven • Underground mine and 8,400 tpd plant producing a clean concentrate with no penalties Operation • Strategicall

  20. Slide 20: Condestable Photos

    Condestable Photos 1 1.CONDESTABLE SITE OVERVIEW 19

  21. Slide 21: Condestable Photos

    Condestable Photos 2 2. CONDESTABLE PROCESS PLANT

  22. Slide 22: Condestable Photos

    Condestable Photos 4 5 6 7 4. THE UNDERGROUND ADIT TO THE MINE 5. DRILLING OPERATIONS – SIMBA. 6. LOADING OPERATIONS 7. CRUSHER 21

  23. Slide 23: Deposits and Depth Potential

    Deposits and Depth Potential 22

  24. Slide 24: Base Operating Scale and Expansion Potential

    Base Operating Scale and Expansion Potential Technical Report Copper Production Profile (kt) 1 2022: Expansion Completed (7 ktpd to 8.4 ktpd) Technical Report Projection (Based on Reserves at 8.4 ktpd) Underground Expansion2 Potential Open Pit Development • Targeting an increase in permitted capacit

  25. Slide 25: Exploration Potential

    Exploration Potential • Reserves currently capture ~47% of M&I resources • Line-of-sight to reserve life extension: • Opportunities near current operating areas – Condestable Norte, Cerro Pacay, Cerro Perico, and Vinchos are the focus for near-term drilling • Operations historically mine outside of

  26. Slide 26: Kalzas Tungsten Project - Yukon

    Kalzas Tungsten Project - Yukon • Project originally in Prospector Resources – the shell company that became Rio2 Limited. • Rio2 geologists completed a field visit in May 2026. • An independent NI 43-101 technical report has been completed using available historical data. • Detailed geological mapp

  27. Slide 27: www.rio2.com

    TSX: RIO | OTCQX: RIOFF | BVL: RIO www.rio2.com 26

  28. Slide 28: Appendix

    Appendix RIO~

  29. Slide 29: Fenix Gold | Reserves and Resources

    Fenix Gold | Reserves and Resources Mineral Reserve and Resources Tonnes Grades Contained Metal Category Mt g/t Au kozs Au Proven Reserves 63.2 0.50 1,022 Probable Reserves 51.5 0.45 750 Total Reserves 114.7 0.48 1,772 Measured Resources 123.3 0.42 1,671 Indicated Resources 266.0 0.36 3,086 M&I Reso

  30. Slide 30: Condestable | Reserves and Resources

    Condestable | Reserves and Resources Mineral Reserve and Resources Tonnes Grades Contained Metal Category Mt % Cu g/t Au** g/t Ag kt Cu kozs Au** kozs Ag Proven Reserves 18.3 0.72 0.17 4.92 131 98 2,888 Probable Reserves 18.2 0.75 0.13 3.64 136 79 2,136 Total Reserves 36.5 0.73 0.15 4.28 268 177 5,0

  31. Slide 31: Summary of Streams and Flexible Prepay

    Summary of Streams and Flexible Prepay Fenix Gold Condestable Wheaton Precious Metals: Stream Franco-Nevada: Stream • US$50 million upfront deposit • US$175 million upfront deposit • 6.0% of gold production until 90 kozs have been delivered under the base stream and • Phase 1: the flexible prepay (s

Rio2 — Investor Presentation (September 2026) on 6ix