Santos Limited · ASX:STO

Santos — Corporate Update (June 2014)

44 slides from Santos's corporate update, Jun 25, 2014

  1. Slide 1: GLNG Investor Visit

    GLNG Investor Visit 25-26 June 2014

  2. Slide 2: Disclaimer and important notice

    Disclaimer and important notice This presentation contains forward looking statements that are subject to risk factors associated with the oil and gas industry. It is believed that the expectations reflected in these statements are reasonable, but they may be affected by a range of variables which c

  3. Slide 3: Project overview

    Project overview Integrated LNG project on track for first LNG in 2015 Location Queensland, Australia Santos (30% and operator), PETRONAS, Total and Project partners KOGAS • Drilling ~800 CSG wells over 2011-15, in addition to existing pre-FID wellstock • Existing and sanctioned gross upstream compr

  4. Slide 4: Safety performance

    Safety performance Over 68 million hours worked since FID, including 17 million hours worked to date in 2014 2014 YTD lost time injury (LTI) frequency rate 0.35 per million hours worked Recent milestones for the workforce include: ─ 7 million hours without an LTI achieved at the module yard in Batan

  5. Slide 5: Project progress

    Project progress Strong construction progress across the integrated project in 2014 Gas LNG plant and Gas supply transmission port pipeline Over 560 wells drilled since FID Marine crossing tunnel is All 82 Train 1 modules set complete ─ Fairview average well capacity 11 of 29 Train 2 modules set inc

  6. Slide 6: Upstream

    Upstream Santos We have the energy.

  7. Slide 7: Fairview field performance

    Fairview well performance Performance of Fairview wells continues to exceed expectations – average gas capacity of 2.2 TJ/day per well Reservoir performance better Fairview well performance as at 31 May 2014 183 wells connected than expected Optimum gas Optimum water Total gross field well capacity

  8. Slide 8: Fairview field performance

    Fairview field performance Deliverability of existing wells continues to exceed expectations and well performance demonstrates high turn down ratios Fairview 118 well - actual production Large number of free flow Gas Water (bbl/day) gas wells adds turn down (TJ/day) capability 7.5 7,500 Shut-in with

  9. Slide 9: Roma well performance

    Roma well performance Roma wells online and dewatering, supporting individual well capacity of 0.5 TJ/day 52 development wells online: Roma well performance as at 31 May 2014 − 22 development wells that are dewatering into the Roma Hub 2 Optimum gas Optimum water capacity (TJ/day) capacity (bbl/day)

  10. Slide 10: Drilling and completions

    Drilling and completions Continuing to drive down well costs Over 560 wells drilled since FID Over 30% reduction in drilling and completion costs per well since FID ─ Average 2013 D&C cost of $1.35 million per development well (30% wells drilled in Fairview, 70% drilled in Roma) Current fleet of 6 d

  11. Slide 11: Upstream infrastructure

    Upstream infrastructure Integrated upstream development with connections to APLNG and QCLNG Wallumbilla 11 | GLNG INVESTOR VISIT - JUNE 2014

  12. Slide 12: Upstream construction

    Upstream construction Hub construction is nearing completion 160 TJ/day gross gas capacity Fairview Hub 5 4 ML/day water handling facilities Commissioning is underway 250 TJ/day gross gas capacity 20 ML/day water handling facilities Fairview Hub 4 Hub construction >98% complete and commissioning wil

  13. Slide 13: Fairview Hub 5

    Fairview Hub 5 Hub 5 has been handed over to the commissioning 160 TJ/day capacity team, focus is on commissioning the GTAs, GTCs and nodal compressors Fairview Hub 5 – 160 TJ/day gross gas capacity and 4 ML/day water handling facilities 13 | GLNG INVESTOR VISIT - JUNE 2014

  14. Slide 14: Fairview Hub 4

    Fairview Hub 4 Hub 4 construction is >98% complete, with 250 TJ/day capacity commissioning to commence in the coming weeks Fairview Hub 4 – 250 TJ/day gross gas capacity and 20 ML/day water handling facilities 14 | GLNG INVESTOR VISIT - JUNE 2014

  15. Slide 15: Roma Hub

    Roma Hub 2 Hub 2 construction is >97% complete – focus on 145 TJ/day capacity handover of sub-systems for commissioning Roma Hub 2– 145 TJ/day gross gas capacity and 10 ML/day water handling facilities 15 | GLNG INVESTOR VISIT - JUNE 2014

  16. Slide 16: Pipeline compressor station (PCS)

    Pipeline compressor Construction of the pipeline compressor station is station (PCS) complete and commissioning has commenced Connection point to the gas transmission pipeline to Gladstone PCS is the collection point for all of GLNG’s upstream gas infrastructure, including: ─ Existing hubs (CS1, CS2

  17. Slide 17: Roma underground storage (RUGS)

    Roma underground RUGS provides significant gas storage capacity storage (RUGS) adjacent to the Wallumbilla gas hub Gas storage in three depleted conventional Roma gas fields: Pleasant Hills, Grafton Range and Pickanjinnie 7 injection wells on-line Injection/withdrawal rate 75 TJ/day Capacity >50 PJ

  18. Slide 18: Incremental gas supply and infrastructure projects

    Incremental gas supply Investing in incremental field development and and infrastructure infrastructure projects In addition to the project scope approved at FID, the following projects have been sanctioned: ─ Fairview Eastern Flank ─ Fairview Infill ─ Roma West Phase 2A ─ CRWP Loop ─ Upstream elect

  19. Slide 19: Fairview Eastern Flank

    Fairview Eastern Flank Brownfield development that utilises the existing capacity at Fairview Hub 4 Sanctioned in November 2013 Comprises the development of 2P reserves in the Bandanna coals along the eastern flank of the Fairview field Development includes: − Drilling and completion of 71 new wells

  20. Slide 20: Fairview Infill

    Fairview Infill Drilling of infill wells in the core Fairview area, which will result in 1-kilometre well spacing across the current development area Sanctioned in December 2013 Brownfield development - will use the existing compression and water management facilities Development includes: − Drillin

  21. Slide 21: Roma West Phase 2A

    Roma West Phase 2A Incremental Roma field development Sanctioned in June 2014 Development includes: − Drilling, completion and connection of 88 wells − Completion and connection of 6 pilot wells − Approximately 100 kilometres of gas gathering, water gathering, fibre optics and power distribution − T

  22. Slide 22: CRWP Loop

    CRWP Loop Construction of 120-kilometre CRWP Loop more than 40% complete Sanctioned in April 2013 Comet Ridge to Wallumbilla pipeline (CRWP) looping will increase the capacity of the existing pipeline to 910 TJ/day Follows the existing CRWP easement Construction progress: ─ Clear & grade 80% complet

  23. Slide 23: Capital expenditure and opex guidance

    Capital expenditure and US$18.5 billion1 capex from FID to the end of 2015 opex guidance 2016-20 average capex estimate A$1 billion pa Vast majority of 2016-20 expenditure is the upstream, and Capital expenditure estimate includes: FID to end of ─ Drilling and completion of new wells (~200–300 per a

  24. Slide 24: Third party gas supply

    Third party gas supply Third party gas generates significant value for the project Attractive oil-linked Supplier Quantity TJ/day Starts Term Delivery point Price basis gross margins Santos portfolio 750 PJ 140 2015 15 years Wallumbilla Oil-linked ‘Horizon’ Provides operational Origin 365 PJ 100 201

  25. Slide 25: Produced water

    Produced water Our aim is to maximise re-use of produced water Uses of Roma produced water Uses of Fairview produced water Irrigation 45% Irrigation 10% 5% Managed aquifer recharge Release to Dawson 7% 50% River 3% Brine Brine 35% Dust suppression/ 45% Dust suppression/ construction construction Rom

  26. Slide 26: Economic benefits and community investments

    Economic benefits and We strive to be a valued and respected member of the community investments local communities which host our activities $8.9 billion worth of work to businesses across Australia, including $5.1 billion to Queensland businesses A further $50 million invested into community initia

  27. Slide 27: Gas transmission pipeline

    Gas transmission pipeline Pipeline push through the marine crossing tunnel

  28. Slide 28: Gas Transmission Pipeline

    Gas Transmission Pipeline Hydrotesting and de-watering complete, final drying in progress 42 inch diameter 420-kilometre pipeline Strong progress as pipeline draws to completion: ─ All of the 420-kilometre pipeline is in the ground, hydrotested and de- watered ─ Marine crossing tunnel is complete ─

  29. Slide 29: Interconnect with QGC pipeline

    Interconnect with The Mt Larcom interconnect has been completed and QGC pipeline pre-commissioned, and construction is complete on the Curtis Island interconnect Allows for one train’s volume of gas to flow from one project to the other, enabling projects to buy, sell or swap gas Links both pipeline

  30. Slide 30: Pipeline commissioning and operations

    Pipeline commissioning Commissioning of the pipeline is planned to and operations commence in Q3 2014 Commissioning team in place Operations ─ Day-to-day control from Brisbane Operations Centre ─ Team in place who will participate in the commissioning activities ─ Integrated with existing Operations

  31. Slide 31: LNG plant and port

    LNG plant and port Overhead view of GLNG LNG plant, 30 May 2014

  32. Slide 32: Curtis Island workforce

    Curtis Island workforce Focused on construction completion Approximately 3,400 people currently working on the GLNG plant and port GLNG camp accommodation for 1,680 people on Curtis Island Operational workforce of 160 required to run the LNG plant and port GLNG plant, May 2014 32 | GLNG INVESTOR VIS

  33. Slide 33: GLNG plant site, Curtis Island

    GLNG plant site, Curtis Two-train LNG plant with a nameplate capacity of Island 7.8 mtpa GLNG plant site, May 2014 Utilities Area Includes Central Control Camp Building Accommodation 1,680 beds Gas Inlet and Refrigerant Storage Material Offloading Facility Train 2 3.9 mtpa nameplate capacity Flare T

  34. Slide 34: LNG Train 1

    LNG Train 1 All 82 Train 1 modules set, work continues on cable pulling and piping hook-up LNG Train 1, May 2014 34 | GLNG INVESTOR VISIT - JUNE 2014

  35. Slide 35: LNG Train 2

    LNG Train 2 11 of 29 Train 2 modules set, 7 modules in transit to site and 11 under assembly in Batangas LNG Train 2, May 2014 35 | GLNG INVESTOR VISIT - JUNE 2014

  36. Slide 36: Outside Battery Limits Utilities Area

    Outside Battery Limits Train 1 utilities area construction substantially Utilities Area complete and Train 2 utilities well underway OSBL Utilities Area, May 2014 36 | GLNG INVESTOR VISIT - JUNE 2014

  37. Slide 37: LNG tanks

    LNG tanks LNG tanks progressing well – hydrostatic testing of first tank planned for early July LNG Tank B (foreground) and Tank A (background) with combined capacity of 280,000 m 3, May 2014 37 | GLNG INVESTOR VISIT - JUNE 2014

  38. Slide 38: LNG loading jetty

    LNG loading jetty Over 95% complete with the installation of quick release mooring hooks, capstans, fenders, vessel access gangway tower and loading arms completed LNG jetty, 360 metres long and suitable for ships with capacity up to 220,000m3, May 2014 38 | GLNG INVESTOR VISIT - JUNE 2014

  39. Slide 39: Commissioning and operations

    Commissioning and Teams recruited and commissioning plans in place operations Integrated Bechtel/GLNG commissioning and start-up team mobilising on site LNG plant commissioning team includes GLNG operators Experienced GLNG partner secondees working in key commissioning and start-up coordination role

  40. Slide 40: GLNG milestones

    GLNG Significant milestones achieved over last 12 months; GLNG remains on track for first LNG in 2015 Milestone Date Marine crossing tunnelling commenced April 2013 First LNG tank roof raise completed June 2013 Second LNG tank roof raise completed September 2013 Dredging complete September 2013 Hydr

  41. Slide 41: Reference slides

    Reference slides Voyage 24, carrying four modules, leaving Batangas for Curtis Island. The module yard team has now despatched 18 of 29 Train 2 modules and 100 of 111 modules overall.

  42. Slide 42: Curtis Island, 31 May 2014

    Curtis Island, 31 May 2014 APLNG QCLNG GLNG 42 | GLNG INVESTOR VISIT - JUNE 2014

  43. Slide 43: GLNG capex summary

    GLNG capex summary FID to Dec 2013 Capex estimate from FID 2013 capex capex until the end of 2015 $billion A$1 A$1 US$2 A$3 LNG project capex (100%) 5.7 13.7 18.5 20.7 Santos 30% share 1.7 4.1 5.6 6.2 Non-LNG project capex (Santos 30% share) Domestic stay in business 0.04 0.10 SIB capex for GLNG’s d

  44. Slide 44: Contact information

    Contact information Head Office Adelaide Andrew Nairn Ground Floor, Santos Centre Group Executive Investor Relations 60 Flinders Street Direct: + 61 8 8116 5314 Adelaide, South Australia 5000 Email: andrew.nairn@santos.com GPO Box 2455 Andrew Hay Adelaide, South Australia 5001 Telephone: +61 8 8116

Santos — Corporate Update (June 2014) on 6ix