Slide 4: 2018 Highlights
2018 Highlights Excellent Advancing Disciplined Capital Performance Projects Management – overall safety performance – Candelaria low-risk high- – early redemption of better than target for sixth return investments on remaining high yield notes consecutive year schedule and budget – actively assessi
Slide 5: Summary Results
Summary Results 2018 Full-Year Results Production – 199,630 t of copper – 152,041 t of zinc – 17,573 t of nickel – 31,184 t of lead $1,726M in Revenue – 64% copper – 17% zinc – 9% nickel – 3% lead 55 New Candelaria Haul Trucks
Slide 6: Financial Highlights
Financial Highlights Realized Metal Prices 1 2018 2017 Δ Copper $2.79/lb $2.98/lb (6%) Nickel $5.64/lb $4.84/lb 17% Zinc $1.25/lb $1.37/lb (9%) Summarized Financial Results 2 2018 2017 Δ Revenue $1,726M $2,077M (17%) Gross Profit $437M $820M (47%) Attributable Net Earnings from Continuing Operations
Slide 7: Candelaria
Candelaria Met Annual Guidance Copper Production & Cash Cost Outlook (100% basis; kt & $/lb Cu, net of by-product credits) – produced 134,578 t of copper at $1.68/lb cash cost – moved 72.3 Mt of waste from open pit 175-185 – North Sector UG production at ~10,200 tpd, an 11% 165-175 increase over the
Slide 8: Candelaria Open Pit – Phase Pushback
Candelaria 8 Candelaria Open Pit – Phase 10 Pushback – Early February 2019
Slide 9: Candelaria
Candelaria Fleet Reinvestment, Mill Optimization and South Sector Development Progressing Well – ~60% of new open pit mine fleet received and in service. Remaining equipment to be delivered mainly in 2019 – >95% of Mill Optimization Project equipment orders placed and construction >40% completed at
Slide 10: Neves-Corvo
Neves-Corvo Excellent Mine and Mill Performance – produced 45,692 t of copper and 75,435 t of zinc at $1.28/lb copper cash cost Copper, Zinc Production & Cash Cost Outlook (kt & $/lb Cu, net of by-product credits) – improved mine productivity and mill throughput both contributed to significant perfo
Slide 11: ZEP – Underground Construction
ZEP – Underground Construction Top of Crusher Chamber Transfer Point #3 Turnover Station Conveyor #3 11
Slide 12: ZEP – Zinc Plant Construction
ZEP – Zinc Plant Construction Zinc Plant Construction – Early February 2019 12
Slide 13: ZEP – Surface Construction
ZEP – Surface Construction New Zinc Plant Construction – Early February 2019 Flotation Cell Installation in Existing Plant 13
Slide 14: Eagle & Eagle East
Eagle & Eagle East Robust Performance – produced 17,573 t of nickel and 17,974 t of Nickel, Copper Production & Cash Cost Outlook copper at $1.01/lb nickel cash cost (kt & $/lb Ni, net of by-product credits) – lower head grades as per mine sequencing ahead of Eagle East coming online 19-22 16-19 18
Slide 15: Zinkgruvan
Zinkgruvan Improved Grades and Mill Throughput – produced 76,606 t of zinc,1,386 t of copper Zinc Production & Cash Cost Outlook and 24,613t of lead at $0.34/lb zinc cash cost (kt & $/lb Zn, net of by-product credits) – Q4 2018 zinc production was the best quarter of the year on improved zinc ore he
Slide 16: 2019 Capital & Exploration Expenditure Guidance
2019 Capital & Exploration Expenditure Guidance Capital Expenditures Capital Expenditures 1 (US$M) – unchanged from previous guidance Capitalized Stripping2 130 Los Diques TSF 10 Exploration – aggressive in-mine and near-mine programs New Mine Fleet Investment 75 – $80M to be invested in 2019 in exp
Slide 17: Increasing Production Profile
Increasing Production Profile1 (kt) Copper Zinc Nickel Forecast 7% CAGR primarily on improved Forecast ~55% increase primarily on Eagle East planned on-line in Q4 2019 Candelaria mine plan and low-risk investments Neves-Corvo Zinc Expansion Project 251 241 246 19 18 231 16 210 15 232 16 218 227 195
Slide 18: Capital Allocation Priorities
Capital Allocation Priorities Invest in low-risk, high-return brownfield expansion projects and exploration Maintain regular dividend Keep a flexible balance sheet to move quickly on compelling growth opportunities Consider other returns of capital to shareholders from time-to-time – announced Norma