Companhia Energetica de Minas Gerais SA · BMFBOVESPA:CMIG3
Companhia Energetica de Minas Gerais SA — UBS Presentation (March 2012)
134 slides from Companhia Energetica de Minas Gerais SA's conference presentation, March 2012

Slide 1: Successful Strategy
Successful Strategy Performance reflects balanced portfolio structure March, 2012

Slide 2: Disclaimer
Disclaimer Some statements and estimates in this material may represent expectations about future events or results that involve risks and uncertainties known and unknown. There is no guarantee that the events or results referred to in these expectations will occur. These expectations are based on p

Slide 3: Brazil's Leading Power Utility
Brazil’s Leading Power Utility Integrated Growth in Market cap Role in Power EBITDA of US$ industry Utility in 2005-10 15.9(1) B. Brazil (2) Leading #1 +49% #1 consolidator In the Power Industry since 1952 (1) As of March 21th, 2012 (2) In the Power Industry 3

Slide 4: Cemig: Strength in Numbers
Cemig: Strength in Numbers (1) Number of power plants 66 Total installed capacity 6,925 MW Locations in Minas Gerais State 5,415 Size of concession area vs. France Larger Electricity Distribution lines 485,046 km Power Transmission lines 9,871 km (1) As of September 30, 2011 4

Slide 5: Cemig at a Glance
Cemig at a Glance ● Based in State of Minas Gerais, controlling shareholder – growing throughout Brazil and Chile ● Strong financial profile: – 2010 - Net revenues: R$ 12.9B EBITDA: R$ 4.5B – 9M2011 - Net revenues: R$ 11.5B EBITDA: R$ 4.0B ● Highest liquidity in the sector – listed on 3 stock exchan

Slide 6: The Cemig Story – Agenda
The Cemig Story – Agenda The positioning The performance The growth 6

Slide 7: Cemig is Uniquely Positioned
Cemig is Uniquely Positioned 1 The Brazil advantage 2 Unmatched scale 3 Diversified portfolio 4 Leader in renewable energy 5 Strong governance 7

Slide 8: An Emerging Powerhouse Economy
1 BRAZIL ADVANTAGE An Emerging Powerhouse Economy Latin American economy #1 Ranking of economy in world #6 GDP 2011 US$2.5 Trillion GDP growth 2011 2.7% Population 191M Power industry net revenue - 2010 >US$145 Billion Investment grade by Moody’s, Fitch and S&P 8

Slide 9: Largest Integrated Utility in Brazil
2 UNMATCHED SCALE Largest Integrated Utility in Brazil #1 #3 #3 #1 Electricity Largest power Largest power Integrated + + distributor* transmission generation utility group group Power Generation RR AP Power Generation (under construction) Power Transmission AM MA Power Transmission (under construct

Slide 10: Diversified, Low Risk Business Portfolio
3 DIVERSIFIED Diversified, Low Risk Business Portfolio Breakdown of EBITDA 2010 3Q11 38% 34% 48% 46% 15% 20% Power Generation Power Transmission Power Distribution and Others Most of revenues are inflation protected 10

Slide 11: Leader in Renewable Hydro Power Energy
4 RENEWABLE LEADER Leader in Renewable Hydro Power Energy Power Generation by Source 5.7% 17% 2% 14% 76.9% 98% 68% 2.5% 14.9% 2% World 08 Brazil 10 Cemig 10 Fossil Source Fuels Nuclear Hydro Others 11 Source: EPE [BEN 2011 – Preliminar Results and IEA [KeyWorld EnergyStatistics-2010]

Slide 12: Best-in-Class Corporate Governance
5 GOVERNANCE Best-in-Class Corporate Governance Minas Gerais, controlling shareholder – a positive influence – one of fastest growing, investor-friendly states in Brazil – growth and profitability interest aligned with minority shareholders – 6 from a total of 14 members are appointed by minority sh

Slide 13: The Cemig Story – Agenda
The Cemig Story – Agenda The positioning The performance The growth 13

Slide 14: Growth in EBITDA
Growth in EBITDA R$ billion 5.1** 4.6 4.5 4.1 4.1 EBITDA Margin: 42% 3.1 3.2 4.1 9M11 2005 2006 2007 2008 2009* 2010* 2011* (*) Reflect the adoption of IFRS ( International Financial Reporting Standards) (**) Last 12 months’ Ebitda 14

Slide 15: Net Income Continues to Expand
Net Income Continues to Expand R$ million 2,378** 2,258 2,134 1,887 1,719 1,744 1,662 Net Margin:15% 1,706 9M11 2005 2006 2007 2008 2009* 2010* 2011* (*) Reflect the adoption of IFRS ( International Financial Reporting Standards) (**) Last 12 months’ Ebitda 15

Slide 16: Attractive and Secure Dividend Payout
Attractive and Secure Dividend Payout (1) Dividend Payout Dividend Yield (% of Net Income) (%) 11 81 9 6 6 50 50 50 2007 2008 2009 2010 2008 2009 2010 2011 Dividends paid in 2010 reach R$ 1.8 billion • Ordinary dividends R$ 931mn, paid in equal parts in June and December 2010 • Extraordinary dividen

Slide 17: Strong Balance Sheet to Support Growth
Strong Balance Sheet to Support Growth ( September 30th, 2011) Net debt to EBITDA 2.0X Debt in foreign currency(*) 1% Cash on hand R$3.9B Net Revenue 3Q11 R$ 4.1B *Net of financial hedging 17

Slide 18: EBITDA guidance
EBITDA guidance EBITDA guidance(1) 2011-2015 R$ million Year Lower limit Upper limit 2011 5,012 5,616 2012 5,074 5,838 2013 4,707 5,416 2014 5,123 5,895 2015 5,302 6,097 Consolidated includes the amounts of the holding company and affiliated companies (1) Constant currency as of June 2011. 18

Slide 19: The Cemig Story – Agenda
The Cemig Story – Agenda The positioning The performance The growth 19

Slide 20: Clear Long Term Goals
Clear Long Term Goals Current Share of Brazil Long Term Goal Markets 20% 13%* 12% 7% 6% Electricity Distribution Power Generation Power Transmission Share of Natural Gas ALL power markets Distribution Brazilian generation market – (% of total installed capacity) Brazilian transmission market – (% of

Slide 21: Target Ebitda contribution by business in the long run
Target Ebitda contribution by business in the long run CIA. ENERGÉTICA DE MINAS GERAIS Power Power Electricity Natural Generation Transmission Distribution Gas Distribution Telecom Services 40% 20% 40% 21

Slide 22: Growth Drivers
Growth Drivers 1 Leverage price increases $ 2 Improve operating efficiency 3 Geographic expansion 22

Slide 23: Record of Successful Acquisitions
GROWTH DRIVER #2 Record of Successful Acquisitions Business Model for Growth ● Partnerships with Equity Investment Funds (FIPs) in recent acquisitions (Terna and Light) create a new growth driver ● Structuring of partnerships with FIPs produces a growth strategy that optimizes capital needs ● Innova

Slide 24: Clear Priorities for 2012
Clear Priorities for 2012 1 Execute cost reductions 2 Integrate Taesa and Light acquisitions Priorities 3 Participate in green fields 4 Select new acquisitions 24

Slide 25: Why Invest in Cemig
Why Invest in Cemig Leading power utility in Brazil Powerful drivers fueling growth Sound Balance Sheet Consistent profitable track record Strong Dividend Policy World Leader in Sustainability 25

Slide 26: Appendix
CLMIG A Melhor Energia do Brasil. Appendix 26

Slide 27: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 27

Slide 28: Brazilian GDP growth is driven by domestic market
Brazilian GDP growth is driven by domestic market Economics Largest Latin America economy 6th largest world economy BRAZIL GDP (2011): US$ 2.5 trillion (+2.7%) Electric Power Industry Inhabitants: 191 million Area: 8.5 million km2 Power Generation Currency(1): Reais (BRL) – US$1 = R$ 1.83 Installed

Slide 29: Companies and Consortia of the Cemig Group
Companies and Consortia of the Cemig Group 107 Companies - 15 Consortias - 1 Equity Investment Funds At December 24th, 2011 Key Transmission companies Distribution companies Generation companies Wind power companies Generation consortia Non-profit Distribution of gas Telecoms Trading Holding company

Slide 30: Strong shareholders base assures liquidity
Strong shareholders base assures liquidity North America EUROPA Luxembourg Jersey Germany ASIA Canada México UK Holland Belgium Brunei United States Spain France Austria Singapore Switzerland Norway Portugal South Korea Ireland Denmark Poland Japan Guernsey Italy Romania Malasia Sweden Taiwan Centra

Slide 31: Cemig: a global investment option
Cemig: a global investment option Non-Brazilian investors as % of free float* 60% 26% 24% 31% 40% 32% 32% 20% 33% 35% 21% 22% 26% 0% 2007 2008 2009 2010 2011 ADR Bovespa Preferred Share * Free float = all shares in circulation except those held by the State of Minas Gerais. • The percentage of non-B

Slide 32: The blend of shareholders provides long term perspective
The blend of shareholders provides long term perspective Our shareholder diversity provides a global business Total Shares management vision focused on sustainability of the company's activities ON PN 44% 56% Listed in major stock exchanges BOVESPA (Brazil) 5% 11% ON NYSE (USA) LATIBEX (Spain) 33% 5

Slide 33: Corporate Governance: implementation of best practices
Corporate Governance: implementation of best practices Highlights Code of ethics; 6 BoD members appointed by minority shareholders; Shareholders BoD approves all investments above R$14mn; BoD approves nomination of external auditors; Executive Board coordinates external auditor selection process (in

Slide 34: Leadership in sustainability, a core value at Cemig
Leadership in sustainability, a core value at Cemig • Social and Environmental responsibilities • Long-term vision commitment • To guarantee the preservation of our activities • Prevent undue costs to be passed to the society through a balanced relationship with the environment and the community • R

Slide 35: Why is Cemig Sustainable?
Why is Cemig Sustainable? 1. Financial Strength 2. Strategic Management 3. Commitment to clients 4. Profitable Investments 5. Technological Innovation 6. Commitment to stakeholders 7. Dedication towards the environment 8. Focus on Renewables 9. Care for human capital 10.Social Responsibility 35

Slide 36: Global Compact
Global Compact In 2009 Cemig joined the Global Compact and published its “Corporate Social Responsibility” handbook. The principles of the Global Compact 1. Businesses should support and respect the protection of internationally proclaimed human rights in their area of influence; and 2. make sure th

Slide 37: The Largest Integrated Power Utility in Brazil
The Largest Integrated Power Utility in Brazil Power Generation Free Customers 6,925 MW of capacity 25% share Power Transmission 9,871 Km Retail Electricity Distribution Largest distribution 485,046 Km company 37

Slide 38: EBITDA Guidance 2011-2012
EBITDA Guidance 2011-2012 Cemig D Cemig GT – Consolidated Lower Upper Lower Upper Year Year limit limit limit limit 2011 1,451 1,773 2011 2,603 3,182 2012 1,466 1,792 2012 2,716 3,319 Holdings Limite Limite Ano Inferior Superior 2011 944 1,153 2012 1,064 1,300 Million R$ in constant prices as of Jun

Slide 39: Net Income and Ebitda per company
Net Income and Ebitda per company (R$ Million) Net Income per Company Company 3Q11 2Q11 1Q11 9M11 % Cemig Geração/Transmissão(*) 320 223 206 749 44% Cemig Distribuição 221 170 143 534 31% Light 0 12 43 55 3% Gasmig 13 13 21 47 3% TBE 46 37 47 130 8% TAESA 157 42 40 239 14% Others -100 26 26 -48 -3%

Slide 40: Financial Highlights
Financial Highlights Income Statement – consolidated 3Q11 2Q11 1Q11 9M11 (R$ million) Net Revenue 4,047 3,659 3,387 7,046 EBITDA 1,501 1,267 1,292 2,559 EBITDA Margin % 37% 35% 38% 36% Net Income 657 523 526 1,049 Net Margin % 16% 14% 16% 15% Balance Sheet – consolidated 3Q11 2Q11 1Q11 9M11 (R$ mill

Slide 41: Debt profile lengthened with reduction of costs
Debt profile lengthened with reduction of costs Maturities timetable (R$ Million) Emission of debentures has promoted Average tenor: 3.3 years the lengthened of our debt from 3 to 3.3 years 3.708 Average cost of debt (real terms) 2.793 6,8 6,8 7,1 7,3 7,4 2.350 5,7 6,2 5,4 5,3 1.520 1.460 1.102 655

Slide 42: Financial discipline to lower debt cost and reduce FX exposure
Financial discipline to lower debt cost and reduce FX exposure Main indexors – 3Q11 Main Creditors (R$ million) – 3Q11 Finel/RGR Others 3% Dolar Debentures Holders 6,072 6% 1% Banco do Brasil 3,709 URTJ BNDES 1,502 IGP-M 820 3% 12% Banco Itaú BBA(*) Bradesco(*) 589 IPCA 16% Unibanco 226 CDI 59% Elet

Slide 43: Superior credit capacity recognized by the major rating agencies
Superior credit capacity recognized by the major rating agencies AA(bra) Cemig H, Cemig GT and Cemig D National scale Investment Grade Speculative Grade AA+ AA AA- A+ A A- BBB+ BBB BBB- BB+ BB BB- B+ B B- CCC CC C RD D Aa1.br Cemig GT and Cemig D National scale Aa2.br Cemig H National scale Investme

Slide 44: Opportunities of raising funds to finance expansion
Opportunities of raising funds to finance expansion Cemig is ready to enjoy market liquidity Local Bank Market Local Capital Market Debt rollover Debêntures are the major source of funds for investment (long term and inflation indexed) Assignment of receivables Securitizations Project Finance (Cemig

Slide 45: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 45

Slide 46: Long Term Strategic Plan addresses sustainable growth
Long Term Strategic Plan addresses sustainable growth… Broadening of CEMIG's area of activity, focusing on the electric industry Growth within Brazil's geographical area First steps towards international investments Expansion in line with Brazilian regulatory limits and sustainable growth Invest onl

Slide 47: Investment policy to guarantee sustainable growth
…Investment policy to guarantee sustainable growth • Pillars of our activity: • Focus on electricity sector and related activities • Profitability: return compatible with each business • Partnerships with strategic investors: corporate governance • Growth through new projects, long-term vision • Opp

Slide 48: Strategic Plan Results
Strategic Plan Results Power Generation Power Transmission lines - km 103% 80 9.871 142 44 76 4.856 470 164 2004 In 2011* 16% 6.925 Sub-transmission lines -km 5.949 8% 17.367 16.086 2004 2005 2006 2007 2008 2009 2010 In 2011 2004 In 2011 Electricity Distribution lines -km Our power matrix ensures hi

Slide 49: Strategic Plan Results
Strategic Plan Results Net margin (%) Ebitda margin (%) 38 40 38 37 20 17 17 18 18 15 35 33 Net income (R$ million) Ebitda (R$ million) 1,706 4,588 4,543 4,060 1,719 1,743 1,887 2,134 2,258 3,222 4,062 4,099 2006 2007 2008 2009* 2010* 9M11 2006 2007 2008 2009* 2010* 9M11* Dividend pay-out (% of Net

Slide 50: Strategic Plan Results: Dividends
Strategic Plan Results: Dividends Dividends paid in 2010 reach R$ 1.8 billion • Ordinary dividends R$ 931mn, paid in equal parts in June and December 2010 • Extraordinary dividends: R$ 900 million, paid in December 2010 Dividends paid in 2011 reach R$ 2,046 billion • 52.97% of the net profit - R$ 1,

Slide 51: Results reflect long-term vision
Results reflect long-term vision Company's structure oriented towards electricity sector consolidation Operational excellence aligned with costs reduction Investment criteria defined by Strategic Plan to add value Risk management ensures reliable processes Corporate governance as a corporate value c

Slide 52: Continuous improvement of our KPI
Continuous improvement of our KPI Leverage (%) Key debt indicators (%) Debt / (Debt + Equity) 5.0 48 44 53 50 44 4.0 4.2 4.2 4.2 2007 2008 2009 2010 9M11 2.2 2.2 2.0 1.7 1.2 2007 2010 2009 2010 9M11 Debt/Ebitda Ebitda/Interes t Key performance indicators in line with Long Term Strategic Plan Earning

Slide 53: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 53

Slide 54: Basics of our business portfolio
Basics of our business portfolio Power generation More competitive environment Regulated market : long term contracts with distributors sales through public auctions. Un-regulated market : medium term contract with large clients. Contract terms bilaterally negotiated. Power transmission Most success

Slide 55: Power Generation: Cemig
Power Generation: Cemig Installed Capacity (September/2011) Installed capacity Efective Power Plant (MW) (MW Average) São Simão 1,710 1,281 Emborcação 1,192 497 Nova Ponte 510 276 Jaguara 424 336 Miranda 408 202 Três Marias 396 239 Volta Grande 380 229 Irapé 360 206 Aimorés 330 172 Others hydro 744

Slide 56: Power Generation: Expansion
Power Generation: Expansion Acquisitions: 3 wind farms – from Energimp S.A.: R$ 223 million (49%). New projects Plant Installed Cemig stake Start up date capacity (MW) (%) Santo Antônio 3,150 10% Dec/2011 Itaocara Hydro Plant* 195 49% Feb/2014 Belo Monte 11,233 7,28% Feb/2015 Installed capacity (MW)

Slide 57: Conventional energy: CEMIG GT supply-demand balance
GROWTH DRIVR #1 CEMIG GT – Supply-demand balance Estimate of secondary Detail of requirements energy overages accounted in short-term market Probable renewals Negotiations in progress Conventional energy 5.500 62 5.000 168 274 380 775 380 380 4.500 330 600 163 113 1.228 1.242 1.310 230 197 4.000 327

Slide 58: CEMIG GT: Power generation prices estimates
CEMIG GT: Power generation prices estimates Effect of renewal of existing contracts (R$/MWh) 130 In 2011 there has been a significant reduction in the projected short-term 121 (spot) price at the secondary energy 113 113 market If isolated, this effect on the average price of energy would be 110.5 R

Slide 59: Power Generation Sales Volume Estimates: CEMIG GT
Power Generation Sales Volume Estimates:CEMIG GT MARKET – TWh* In 2011 Cemig GT participated in the Secondary Energy market (additional generation above the assured physical levels, due to favorable hydrology and sold on the Short-term (Spot) Market) Energy purchases (Petrobrás, Copel, Incentive-bea

Slide 60: Brazilian National Grid
Brazilian National Grid Structural Energy Balance (Average MW) Sources: PMO, May 2011; PDE, 2019; Cemig research and an estimated GDP of 5% for the 2011-2014 period 60

Slide 61: Level of reservoirs (%)
Level of reservoirs (%)* Level of reservoirs by region (%) 100 90 83,36 80 70 60 58,74 50 48,06 47,90 40 30 20 Mar-10 Apr-10 Oct-10 Mar-11 Apr-11 Oct-11 Jan-10 Feb-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Nov-10 Dec-10 Jan-11 Feb-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Nov-11 Northeast North South Southe

Slide 62: Spot Market: 2010/2011
Spot Market: 2010/2011 Brazil: electricity spot price - monthly average (R$/MWh) 160 140 120 100 80 70.23 60 45,55 40 28,20 20 0 Monthly average spot price, R$/MWh 2009 average 2010 average, up to end-November *Source: CCEE 62

Slide 63: Power Generation Auctions: 2010/2011
Power Generation Auctions:2010/2011 Capacity Efective Power Name Date Power Plant Price/MWh Installed(MW) (MW Average) Special Power Auctions 2010 Belo Monte (30 years long contracts) 11.233 4.571 R$ 77,97 Garibaldi 178 83 R$ 108,00 Colider 300 180 R$ 103,00 A-5 2010 th Ferreira Gomes 252 150 R$ 70,

Slide 64: Business Opportunities: Small Hydros Program
Current status Business Opportunities: Small Hydros Program Short-term supply alternative Successful funding format: – 30% Equity • Cemig 49% Àrea reservada para o mapa • Private Investor 51% – 70% Debt • BNDES Current status: • Cachoeirão Small Hydro Power Plant (27 MW) in commercial operation; • P

Slide 65: Business Opportunities: biomass cogeneration
Business Opportunities: biomass cogeneration Sugar and ethanol potencial in Minas gerais Plants Quantity* Generatn. (MWa**) Surplus (MWa**) Existing 12 750 300 Expected 22 2,416 1,631 Total 34 3,166 1,931 * Just includes plants available to generate and sell power ** Average generation in 6 months o

Slide 66: Brazilian hydroelectric power generation potential
Brazilian hydroelectric power generation potential Situation as of December 2010, MW Region State Operation Estimated Overall RR AC - 1,121 1,121 AP AM 250 19,648 19,898 AP 68 1,938 2,006 North RO 3,549 9,342 12,891 RR 5 5,257 5,262 AM PA MA PA 8,500 40,900 49,400 CE RN TO 2,324 4,351 6,674 PB PI AL

Slide 67: Tapajós Complex
Tapajós Complex Location: Tapajós Basin, PARA State 5 Hydro Power Plants Installed Capacity: 10,682 MW Assured energy: 4,581 average MW (expected) Power Plant River Installed Assured Start-up Capacity Energy -MW Avg MW São Luiz do Tapajós Tapajós 6,133 3,369 2016 Cachoeira do Caí Tapajós 802 418 201

Slide 68: Teles Pires Complex
Teles Pires Complex Location: Teles Pires Basin, Mato Grosso State 3 Hydro Power Plants Installed Capacity: 3,027 MW Power Plant River Installed Assured Start-up Capacity -MW Energy Date Avg MW Teles Pires Teles Pires 1,820 915 2015 São Manuel Teles Pires 746 400 2015 Sinop Teles Pires 461 227 2015

Slide 69: Santo Antônio hydro plant – basic information
Santo Antônio hydro plant – basic information • 3,150 MW of installed capacity • 2,218 MWAverage of energy > Capacity Factor (CF) of 69%; • Price: R$78.87/MWh (equivalent to R$99/MWh for a traditional 55% CF Hydro Power in Brazil) • Winner consortium: – 10% Cemig – 39% Furnas – 20% FIP (Investment F

Slide 70: Santo Antônio hydro plant – basic information
Santo Antônio hydro plant – basic information • Low-fall plant (13.9 m), average estimated flow 568 m3/s, lake 271 km2, resulting in lower ratio between reservoir area and total energy generated than in other Amazon region plants: index of 0.09 – Balbina ( 250 MW, 2,360 km2 reservoir): index 9.44 –

Slide 71: Belo Monte hydro plant – basic information
Belo Monte hydro plant – basic information • Concession period: 35 years • 11,233 MW of installed capacity • Assured energy: 4,571MW average • 516 km2 reservoir • Ratio between reservoir area and total energy generated: 0.04 km2 /MW • Estimated cost of the project: R$ 25.8 billion 71

Slide 72: Wind power potential in Minas Gerais
Wind power potential in Minas Gerais Cemig is one of the pioneer companies in terms of wind generation in Brazil through the Morro do Camelinho plant, which was connected to the grid in 1992. Wind power map of Brazil: Brazil has a theoretical wind power generation potential of 143.5 GW, estimated at

Slide 73: Power Transmission Capacity (Km)
Power Transmission Capacity (Km) 2005 2006 2007 2008 2009 2010 In 2011* >525-Kv lines 0 0 0 51 77 101 228 500-kV lines 2,165 2,592 2,488 2,788 3,594 4,421 5,190 345-kV lines 1,976 1,969 2,001 2,001 2,167 2,358 2,251 230-kV lines 751 803 824 915 1,668 1,888 2,016 Total 4,892 5,364 5,313 5,755 7,506 8

Slide 74: Transmission: Present all over Brazil
Transmission: Present all over Brazil ETEP and ERTE NOVATRANS Cemig is now Brazil’s third EATE and ENTE GTESA largest transmission group: Total lines: 9,871Km PATESA RN Consolidated Permitted MA PA PE Annual Revenue (RAP-2010): PI PB R$1.4 billion, including TO AL SE Transchile MT BA MT MUNIRAH EBTE

Slide 75: Power Transmission: Expansion
Power Transmission: Expansion Acquisitions in 2009: Taesa (formerly Terna): R$ 1.90 billion for a 56.7% stake Increased interest in TBE: R$ 505 million Acquisitions in 2010 Increased interest in TBE: R$ 100 million. Current stake of 40% approximately. ASSETS RAP (Permitted Annual Cemig stake (%) Sta

Slide 76: Start up in Chile: First international step
Start up in Chile: First international step Charrúa–Nueva Temuco Transmission Line Chile •Voltage: 2x 220kV •Length: 205 km •Concession period: 20 years •Stake: 49% •Total investment: US$88 million •Annual Revenue: US$65 million Transchile •Financing: 63% of the investment •Capital from Cemig : U$20

Slide 77: 2010 Auctions
Power Transmission auctions 2010 Auctions June, 11th December, 09th 9 lots totaling 700 Km of lines 8 lots totaling 555 Km of lines These assets will be built in 7 states These assets will be built in 6 states 30 years contracts and estimated total capex of R$700 million 30 years contracts and estim

Slide 78: The 1st Transmission Tariff Review
The 1st Transmission Tariff Review This cyclical review is related just with old assets hold by Cemig GT • Taesa and TBE are not entitled to this type of review The criteria of this Tariff Review were set by Aneel Normative Resolution 257/07, the principal ones being: a. WACC: 9.18% p.a. b. Operatio

Slide 79: Electricity Distribution Capacity
Electricity Distribution Capacity Network in km 2007 2008 2009 2010 1Q11 SUB-TRANSMISSION 16.676 16.810 16.959 17.096 17.367 161-kV lines 55 55 55 55 55 138-kV lines 11.145 11.254 11.442 11.491 11.749 69-kV lines 4.510 4.535 4.508 4.595 4.608 Lines below 69 kV 966 966 954 955 955 DISTRIBUTION 429.56

Slide 80: Cemig D: sales by category
Cemig D: sales by category in 2Q11 Sales by category - GWh Electricity sold – GWh: Changes, 2Q11 TYPE 3Q11 3Q10 Change % -1% Residential 2,144 2,021 6% 6.301 6.231 Industrial 1,143 1,209 -6% Commercial 1,253 1,117 12% Rural 813 746 9% Other 805 740 9% Clients 6,158 5,833 6% CCEE 64 460 -86% 3Q10 3Q1

Slide 81: Electricity Distribution tariff review
Electricity Distribution tariff review Allowed return on asset approach: Benchmark WACC: was 11.26% in 1st cycle (2003• Tariff review: WACC of 9.95% in 2nd cycle (2008• New Tariff Review methodology: Reference company model disclosed: Black box opened. Asset base review every 10 years (proposal•: CE

Slide 82: Cemig D 2009 readjustment and Impact on Tariff
Cemig D 2009 readjustment and Impact on Tariff 2009 IMPACT to CONSUMERS Financial Components 2008 + CVA R$ 442.300.746 Financial Components + CVA ANEX II (IRT) R$ 682.427.357 REQUIRED Appendix Appendix Appendix REVENUE I I VERIFIED II REVENUE Appendix R$ 7.622.802.110 II R$ 6.124.630.949 Appendix I:

Slide 83: Cemig D 2010 readjustment and Impact on Tariff
Cemig D 2010 readjustment and Impact on Tariff 2010 IMPACT to CONSUMERS Financial Components 2009 + CVA R$ 332,792,812 Financial Components + CVA ANEX II (IRT) R$ 442,300,746 REQUIRED Appendix Appendix Appendix REVENUE I I VERIFIED II REVENUE Appendix R$ 7,974,659,463 II R$ 7,622,802,110 Appendix I:

Slide 84: 1st Tariff Review 2003 vs 2nd Tariff Review 2008/2009
1st Tariff Review 2003 vs 2nd Tariff Review 2008/2009 2nd Tariff Review 2009 1st Tariff Review 2003 2nd Tariff Review 2008 Final • Regulatory Ebitda • Regulatory Ebitda • Regulatory Ebitda Margin: 21.2% Margin: 21% Margin: 21% • Losses coverage: • Losses coverage: • Losses coverage: inadequate suffi

Slide 85: Aneel's Proposal for the 3rd Cycle: WACC
Aneel’s Proposal for the 3rd Cycle: WACC Regulatory Proposal WACC 2nd Cycle ( Final) 3rd Cycle (Aneel’s Proposal) Debt Cost of Debt (Rd) 14.97% 11.50% Taxes (t) 34.00% 34.00% Debt-to-Capital (D/D+E) 57.16% 60.00% WAC of debt 5.65% 4.55% Equity Risk free Rate (Rf) 5.32% 4.96% Market Premium (Rm – Rf)

Slide 86: Aneel's Proposal for the 3rd Cycle: Main Changes
Aneel’s Proposal for the 3rd Cycle: Main Changes Opex: • Two stages: o Reference Company model of the 2nd Cycle (2008) adjusted to inflation and productivity gains and sales volume increase – First Stage o Benchmarking with peers in order to verify Stage 1 and produce component (T) – Second Stage; C

Slide 87: Aneel's Proposal for the 3rd Cycle: Main Changes
Aneel’s Proposal for the 3rd Cycle: Main Changes Energy Losses: Regulatory energy losses will be defined according to the complexity of each concession area • Companies ranked and then grouped. In a ranking from more to less complexity, to deal with electricity losses, Cemig was considered 24th and

Slide 88: Natural Gas Distribution - Gasmig
Natural Gas Distribution - Gasmig 287 Clients (conventional), 2 Thermal power plants 28 municipalities served 222 employees 794 km of networks Concession area: 586,523 km² Major works: Sul de Minas Project – Completed Vale do Aço project Market*: –completed Sales volume: 668,441,993 m³ Average: 2,44

Slide 89: Natural Gas Expansion: consortium wins oil and gas bids
Natural Gas Expantion: Cemig´s consortium wins Brazilian Oil and Gas Bids in December 2008 Strategic initiative seeks means to ensure supply of natural gas for distribution, through Gasmig, and for thermal power generation Consortium Structure Winning Bid Cemig´s stake in the consortium of 24.5% Sig

Slide 90: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 90

Slide 91: Acquisitions leverage results
Aquisitions leverage results Assets 2004 2005 2006 2007 2008 2009 2010 Total Value invested in acquisitions R$ Million Total Rosal 137 - - - - - - 137 TBE(1) - - 349 4 15 575 139 1,081 Light - - 175 - - - 786 961 Total 137 - 524 4 15 575 925 2,178 Contribution to net income Rosal (6) 19 19 19 21 23

Slide 92: Holdings acquired add net income to Cemig's results
Holdings acquired add net income to Cemig’s results TBE +R$130 MM TAESA +R$239 MM LIGHT +R$ 55 MM + R$524 million/year of Net Income in 1H2011 92

Slide 93: Cemig Group grows through management of assets
Cemig Group grows through management of assets As well as operators, we have become managers of assets, in all segments of electricity: 8,677 Power Generation 6.925 1.752 Installed capacity (MW) 64,144 Cemig Electricity Distributed consolidated 48,765 15,379 Annual Sales(GWh)* 13,820 Management for

Slide 94: Acquisition of Brookfield's shares in TBE (Transmission)
Acquisition of Brookfield’s shares in TBE (Transmission) In 2006 Cemig acquired a Stake in TBE Cemig increased its stake in TBE: R$505M paid in 2009 Stakes before the acquisition EATE ECTE ENTE ERTE ETEP CEMIG 17.68% 7.50% 18.35% 18.35% 19.67% Eletrobrás 29.30% 0% 0% 0% 21.33% Other partners 53.02%

Slide 95: Acquisition of MDU's Shares in TBE (Transmission)
Acquisition of MDU’s Shares in TBE (Transmission) The acquisition of equity interests held by MDU in the companies of the TBE group was completed on November 12, 2010. Cemig’s stakes were increased to the following: COMPANY % OF TOTAL CAPITAL Empresa Norte de Transmissão de Energia S.A. (ENTE) 13.30

Slide 96: Description of TBE – Power transmission group
Description of TBE – Power transmission group Length Company Line/Substation Capacity(kV) Start-up (Km) EATE Tucuruí (PA) a Presidente Dutra (MA) 927 500 mar/03 ECTE Blumenau (SC) a Campos Novos (SC) 253 525 mar/02 ENTE Tucuruí (PA) a Açailândia (MA) 458 500 fev/05 ERTE Vila do Conde (PA) a Santa Ma

Slide 97: Acquisition of holdings in wind farms: The Transaction
Acquisition of holdings in wind farms: The Transaction Resulting stockholding structure The Transaction • Acquisition of 49% stockholdings in three wind farms (99.6MW) in the Brazilian State of Ceará, currently owned by Energimp S.A. (IMPSA). • Price paid for the shares: R$ 223 million, to be paid (

Slide 98: Acquisition of holdings in wind farms: The Assets
Acquisition of holdings in wind farms: The Assets Locations Volta do Rio Wind Power Plant Volta do Rio Morgado • Location: Acaraú (240km from Fortaleza), Ceará Fortaleza • Equipment: 28 rotors of 1,500KW each Parajurú • Installed capacity: 42.0MW • Load factor : >45% • Energy contracted: 161.2GWh /

Slide 99: Terna (now TAESA) acquisition - Transaction Summary
Terna (now named TAESA) acquisition - Transaction Summary Power Transmission Company with 3,753 km of lines in 11 Brazilian States Acquisition in partnership with Equity Investment Fund - FIP Coliseu Largest FIP created to invest in the Brazilian electricity sector: R$ 1.33 billion o Attractive to i

Slide 100: FIP Coliseu: Efficient vehicle for growth in Transmission
FIP Coliseu: Efficient vehicle for growth in Transmission On November 4th, 2009, Cemig GT, jointly with FIP Coliseu, acquired 65.85% of Terna Participações S.A., through Transmissora do Atlântico de Energia Elétrica S.A. Atlântico was split, creating Transmissora Alterosa, which will be responsible

Slide 101: TAESA - Overview
TAESA - Transmissora Aliança de Energia Elétrica S.A - Overview Geographic Footprint Overview of Concessions Start-up Concession Line Date Term TSN abr-03 dez-30 GTESA jul-03 jan-32 PATESA mar-04 dez-32 Munirah nov-05 fev-34 Novatrans abr-04 dez-30 ETAU mai-05 dez-32 ETEO out-01 mai-30 under Brasnor

Slide 102: Distribution: Increasing stake in Light in 2010
Distribution: Increasing stake in Light in 2010 creates new opportunities A 13.03% stake was bought for R$172M in 2006 (with full payback in 2 years) Cemig D and Light represent almost 16% of electricity distributed in Brazil in 2008 • Tradition and experience in Light and Cemig brought closer • Opp

Slide 103: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 103

Slide 104: CAPEX - Investment program
CAPEX(R$ Million) Investment program 104

Slide 105: Planned expansion
Planned expansion Power Generation Expansion Capacity, MW CEMIG % 2009 2010 2011 2012 2013 Santo Antônio Hydro Plant 10 3,150 Pipoca PCH 49 20 Senhora do Porto PCH 49 12 Dores de Guanhães PCH 49 14 Jacaré JCH 49 9 Fortuna II PCH 49 9 Itaocara 49 194 Paracambi 49 25 Lajes 49 18 Capacity under constru

Slide 106: Large Growth in Cash Flow
Large Growth in Cash Flow Cash position provides flexibility to financial management 106

Slide 107: Consolidated net revenue
Consolidated net revenue Growth in net revenue reflects business diversification, and positive effects of acquisitions (RME/Light S.A., TAESA and TBE companies) Operating Revenues 3Q11 2Q10 Ch% 2Q11 2Q10 Ch% 1Q11 1Q10 Ch% 9M11 9M10 Ch% Sales to end consumers 3,821 3,360 14 3,659 3,387 8 3,534 3,086

Slide 108: Operating Expenses
Operating Expenses Operating Expenses 3Q11 2Q10 Ch% 2Q11 2Q10 Ch% 1Q11 1Q10 Ch% 9M11 9M10 Ch% Personnel/Administrators/Councillors 293 265 11 297 299 (1) 307 294 28 897 858 5 Forluz – Post-Retirement Employee Benefits 47 53 (11) 31 7 343 31 28 11 109 88 24 Materials 31 16 94 29 30 (3) 18 29 (38) 78

Slide 109: Consolidated operational expenses
Consolidated operational expenses Expenses - R$ million 5% 2,781 2,597 3Q10 3Q11 Operational Efficiency Program continues to generate excellent results. • Greater control of costs and management of PMSO expenses achieves real-terms reduction from 3Q10. • Quest for greater efficiency in reduction of

Slide 110: Expansion of consolidated net income in the year
Expansion of consolidated net income in the year Result shows growth consistent with solid fundamentals • Growing productivity in all areas • Continuous improvement in operational margins • Diversification of the risk inherent to each business through integrated structure Statement of Results 3Q11 2

Slide 111: Cemig Distribuição
Cemig Distribuição Operating Revenues 3Q11 3Q10 Ch% 2Q11 2Q10 Ch% 1Q11 1Q10 Ch% 9M11 9M10 Ch% Sales to end consumers 2,563 2,332 10 2,446 2,331 5 2,307 2,295 1 7,316 6,958 5 TUSD 458 439 4 446 431 3 447 330 35 1,351 1,200 13 Revenues from construction 167 267 353 257 213 3 739 737 Others 35 67 (48)

Slide 112: Cemig Geração e Transmissão
Cemig Geração e Transmissão Statement of Results 3Q11 3Q10 Ch% 2Q11 2Q10 Ch% 1Q11 1Q10 Ch% 9M11 9M10 Ch% Net Revenue 1,303 1,072 22 1,053 945 11 2,317 1,958 14 4,673 3,975 16 Operating Expenses 517 480 8 491 467 5 980 917 6 1,988 1,864 6 EBIT 786 592 33 562 478 18 1,337 1,041 28 2,685 2,111 27 EBITD

Slide 113: Agenda
Agenda •Background •Strategy Overview •Business Outlook •Acquisitions •Results •Market Recognition •Regulatory Framework •Others 113

Slide 114: Market Recognition
Market Recognition Included in the DJSI for the 11th year running. Included in Bovespa Corporate Sustainability Index. Included in The Global Dow Index as the only Latin American electricity company in this 150-company index, and one of the 10 selected to represent emerging markets. Prêmio Anefac Tr

Slide 115: Appendix: Regulatory Framework, Others
Appendix •Regulatory Framework •Others 115

Slide 116: Power Generators are the most exposed to risks
Power Generators are the most exposed to risks Regulated market Concessions granted based on the least price approach. Power purchase contract: Auctions organized by a Federal agency: Final buyer : Electricity Distributors. New capacity : longer term, no market risk, inflation adjusted; Existing cap

Slide 117: Power Generation Price Trend
Power Generation Price Trend Price will behave differently according to the nature of the contract to be auctioned by ANEEL: Existing capacity (so called old energy • contracts: power to be supplied in a year from now; Term of 8 years; (can be from 3 to 15 years• Imply distributor s forecasted deman

Slide 118: Brazil's electricity markets
Brazil’s electricity markets Generation Wholesale prices resulting Freely negotiated wholesale from auctions prices Regulated Market Free Consumers Distribution Companies Free Market (“ACR”) Special Consumers (“ACL”) Traders Generators Co-existence of two markets: competitive, and regulated 118

Slide 119: Types of contracting in the Regulated Market
Types of contracting in the Regulated Market A–5 A–3 A–1 Adjustment Local Generation New New Energy Existing Auctions Auctions (Distribution Energy Auctions Generation Company Option) Auctions Auctions Objective Expansion Expansion Existing load Adjustment of Existing load current situation Duration

Slide 120: Reserve Auctions
Reserve Auctions Objective: To further increase the security of the System by diversifying supply sources Energy sources: So far specific auctions for Small Hydro Plants (“PCHs”) and plants generating from wind energy and biomass. Contract periods: • Hydro: 30 years • Biomass:15 years • Wind: 20 yea

Slide 121: Brazilian generation market – 2010
Brazilian generation market – 2010 (% of total installed capacity) Source: ANEEL, Cemig 121

Slide 122: Brazilian transmission market – 2010
Brazilian transmission market – 2010 (% of Permitted Annual Revenue (RAP)) Others Source: ANEEL, Cemig 122

Slide 123: Transmission regulation is the most successful one
Transmission regulation is the most successful one Competition for concession contract: Cap price approach: annual permitted revenue; Allowed revenue: the winner bid is the lowest revenue earned from users; 30-year long concession. Stable Cash flow Guaranteed contracts signed with users: Receivables

Slide 124: Transmission network expansion
Transmission network expansion • Facilities built before 1995: – Concession will expire on July 8, 2015; – 20-year extension may be granted at ANEEL discretion; – Allowed return to be reviewed every four years Expansion projects can be carried out in three ways: New concessions to be granted through

Slide 125: Electricity Distribution: Brazil
Electricity Distribution: Brazil AES RR AP Ashmore Energy Main controlling MA Energisa (Cat-Leo) groups in Brazil CE RN Endesa AM PA PI PB EDP PE State-owned, Federal AC TO AL RO State-owned, Indiv. BA SE MT State Grupo Rede GO Equatorial Energia Brazil Numbers (2009) MG MS NeoEnergia ES Concessions

Slide 126: Brazilian distribution market – 2010
Brazilian distribution market – 2010 % of all electricity distributed to free and captive clients in Brazil) Source: EPE, Cemig 126

Slide 127: Electricity Distribution business is the most regulated one
Electricity Distribution business is the most regulated one Allowed return on asset approach: Benchmark WACC: 9.95 (real• Operating expenses: Full passed through mechanism: Energy purchase expenses under certain circumstances. Yearly inflation adjusted; Tracking account for offsetting estimated expe

Slide 128: Electricity Distribution Tariff Review Process
Electricity Distribution Tariff Review Process PARAMETERS REVENUE FROM BILLING Special EXPENDITURES TO CONSUMERS Obligations + Reinstatement Depreciated Revenue Captive Consumers Depreciation Installment Residential Assets Rate Remuneration of 4.65% Accumulated Capital Total Assets Base Depreciation

Slide 129: Appendix: Regulatory Framework, Others
Appendix •Regulatory Framework •Others 129

Slide 130: Glossary
Glossary • Average outage frequency (FEC): Average number of outages suffered in a given period per consumer, in a given group of consumers. • Debt coverage index: Ebitda divided by total financial expenses in the year. This gives a figure for the company’s capacity to pay debt servicing. • Deferred

Slide 131: Glossary
Glossary • The CDE (Energy Development) Account: This is a source of subsidies to make alternative energy sources such as wind and biomass more competitive, and promote universalization of electricity services. It is funded by annual payments made by the concession holders for the use of public asse

Slide 132: Investor Relations
Investor Relations Telefone: (55-31) 3506-5024 Fax: (55-31) 3506-5025 Email: ri@cemig.com.br Website: http://ri.cemig.com.br 132 132

Slide 133: Notes
C-MIG Notes 133

Slide 134: Notes
C-MIG Notes 134
Source: Internet Archive copy of ri.cemig.com.br
More decks from Companhia Energetica de Minas Gerais SA
Cemig — Q3 2026 Earnings Presentation18 slides · Nov 13, 2026
Q3 2026 Earnings Presentation18 slides · Sep 30, 2026
Cemig — Q2 2026 Earnings Presentation17 slides · Aug 14, 2026
Q2 2026 Earnings Presentation17 slides · Aug 14, 2026
Energy Co of Minas Gerais — Q1 2026 Earnings Presentation25 slides · Jun 9, 2026
Cemig — Q1 2026 Earnings Presentation20 slides · May 8, 2026