Eldorado Gold Corporation · TSX:ELD
Eldorado Gold — Investor Presentation (February 2013)
48 slides from Eldorado Gold's investor presentation, February 2013
Slide 1: Focusing on Delivery
Focusing on Delivery Investor Presentation February 2013
Slide 2: Forward-looking statements
Certain of the statements made in this Presentation may contain forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of applicable Canadian securities law. These forward-looking statemen
Slide 3: Gold producer with 20 years of international operating experience
> 650,000 oz gold producer with 20 years of international operating experience Leading low cost operator with solid margins and a strong balance sheet Experienced management team with a proven ability to build and operate Open Pit, Kişladağ, Turkey mines www.eldoradogold.com 3
Slide 4: Track record of value creation
Track record of value creation through exploration, development, production and acquisitions Solid reserve and resource base (P&P gold reserves: 25.7 Moz) Competitive and transparent dividend Processing Plant, Efemcukuru, Turkey policy www.eldoradogold.com 4
Slide 5: 2013 guidance and priorities
Gold production of 705,000–760,000 oz Cash operating costs of $515–$530/oz; estimated total cash costs of ~$585/oz Capital expenditure of $648m ($410 operations; $238 projects) Exploration budget increased by 22% to $98.5m Cash and cash equivalents of $817m at year end 2012 Dividend of C
Slide 6: Operations in highly prospective areas
Operations in highly prospective areas with well-established mining cultures Asset base is diversified across the mining lifecycle Pipeline of assets drives organic growth www.eldoradogold.com 6
Slide 7: By 2016, we aim to
By 2016, we aim to: Produce over 1.5m ounces of gold (2012: ~660,000oz) Have cash operating costs of $300-350/oz net of by-product (2012: $489/oz) Maintain balance sheet strength Continue to distribute an industry leading dividend Gold Bars, White Mountain, Chine www.eldoradogold.com 7
Slide 8: Estimated Gold Production 2012-2016
Estimated Gold Production 2012-2016 1,650,000 1,800 We’re seeing: 1,500,000 1,600 Strong production 1,350,000 1,400 growth (Average 1,200,000 1,200 Annual Growth Rate: 1,050,000 Gold Production (oz) 1,000 27%) with decreasing 900,000 cash costs 750,000 800 US$/oz 600,000 600 Over 1.5 million o
Slide 9: Increasing Gold Production and Reserves & Resources
Increasing Gold Production and Reserves & Resources Over the past 5 years we have: Reserves & Resources (Moz) 40 700 Gold Production (Koz) 35 600 30 500 Doubled production 25 400 20 300 15 200 Materially increased reserves 10 5 100 & resources per share 0 0 2008 2009 2010 2011 2012 P+P M+I Pro
Slide 10: Four projects account for 75% of future production growth
These four projects account for 75% of Eldorado’s future production growth Kişladağ Olympias Skouries Perama Hill (Expansion) (Expansion) (Construction) (Development) www.eldoradogold.com 10
Slide 11: Kişladağ Expansion Highlights
EXPANSION Highlights Current production rate 12.5 million tonnes / year (crushing, screening, stacking) Expanded production rate 25.0 million tonnes / year (crushing, screening, stacking) Expanded production rate, average 475,000 ounces / year LOM strip ratio 1.4:1 ROM ore treatment , average 8MT /
Slide 12: Kişladağ Expansion Engineering and Construction
EXPANSION Engineering Detailed engineering design initiated Procurement Phase IV Leach Pad Expansion Continue procurement of major mining and process equipment Phase IV Plant Expansion Major fabrication initiated Construction Construction of Phase IV leach pad extension Installation of Nor
Slide 13: Development Potential
Development Potential Projects within a 10km radius Projects EIA approved Excellent infrastructure (roads, power, port access) Experienced & growing local teams Phased construction approach Strong government support Reserves as at December 31, 2012 www.eldoradogold.com 13
Slide 14: Olympias Project Highlights
EXPANSION Deposit Type Replacement mixed sulphide Mine Life 25 years Initial Capex ~US $165 million to Phase II UG Production Mining Rate Phase I (2012 - 2015) –Tailings 2013: 900 ktpa Phase II (2016 - 2017) – Underground: 450 ktpa Phase III (2018 - On) – Underground Expansion: 850 ktpa Grade 7.9 g/
Slide 15: Olympias Work in 2012 and 2013
EXPANSION Work in 2012 Plant refurbishment a. complete Schist Production from tailings Amphibolite Gneiss commenced in Q4 Marble Refurbishment of existing Intrusive mine ramp complete Underground tunnels refurbished using rock- bolting and shotcreting c. d. Work in 2013 Achieve com
Slide 16: Skouries Project Highlights
CONSTRUCTION Deposit Type Gold-Copper Porphyry Mine Life 27 years Initial Capex ~US $340 million to plant production from Open Pit Schist Mining Rate 8 Mtpa Open Pit Amphibolite Gneiss 4.4 Mtpa Underground Marble Grade (OP & UG) 0.76 g/t Au and 0.57% Cu Intrusive Strip Ratio 0.7 : 1 Gold Production
Slide 17: Skouries Work in 2012 and 2013
CONSTRUCTION Work in 2012 Site preparation – surface clearing Schist activities and earth moving Amphibolite Gneiss Marble Road access Intrusive Portal excavation Work in 2013 Continue construction of Processing Plant Advance underground development Test geological potential of near
Slide 18: Perama Hill Project Highlights
DEVELOPMENT Disseminated epithermal Deposit Type gold-silver deposit Mine Life 8 years Initial Capex ~US $220 million Mining Rate 1.25 Mtpa Open Pit 3.13 g/t Au Grade 4 g/t Ag Strip Ratio 0.35 : 1 Gold Production 110,000 oz/year Silver 85,000 oz/year Production Cash Costs $288/oz (by-product) Proces
Slide 19: Perama Hill Work in 2012 and 2013
DEVELOPMENT Work in 2012 PEIA approved in February 2012 EIA submitted to Ministry of Environment (MoE) in March 2012 under Fast Track Legislation Basic engineering package for process plant completed in Q4 Work in 2013 EIA approval anticipated in Q1 Commence construction activities i
Slide 20: Efemcukuru Piavitsa Certej Tanjianshan
Efemcukuru Piavitsa Certej Tanjianshan www.eldoradogold.com 20
Slide 21: Efemcukuru exploration: Kestane Beleni and Kokarpinar veins
EXPLORATION Kestane Beleni Vein At KBNW: Drilling defined a new shallowly-plunging ore shoot with high gold grades. Remains open to the northwest. At SOS and MOS/NOS: Drilling extended the known mineralization downdip. Ore shoots remain open at depth. Kokarpinar Vein Drilling identified two ne
Slide 22: Exploration
EXPLORATION www.eldoradogold.com 22
Slide 23: Exploration Potential
Exploration Potential Strategic land position Mining district with multiple deposit styles within 10km radius Defined gold resources of: M+I: 9.7 Moz Au Inferred: 3.9 Moz Au Untested targets provide excellent upside potential Reserves as at December 31, 2012 www.eldoradogold.com 23
Slide 24: Initial inferred resource of 1.7 Moz Au
EXPLORATION Initial inferred resource of 1.7 Moz Au Excellent upside potential 2012 program tested target horizon on 100m x 200m spaced grid www.eldoradogold.com 24
Slide 25: Over 1.5 million oz added to M&I resource base in 2012
EXPLORATION Over 1.5 million oz added to M&I resource base in 2012 2012 drill holes in Link Zone target cut high- grade gold mineralization West Pit target has high-grade epithermal veins Limited modern exploration in Romania but extensive historical exploration and mining data www.eldoradog
Slide 26: Qinglongtan North and Xijingou drilling
EXPLORATION Qinglongtan North (QN) Several holes at QN intersected a new high-grade gold zone beneath previously mined deposit Further drill testing planned for 2013 Drillhole From To Interval Au (g/t) QD-278 233.0 243.0 10.0 2.87 QD-279 247.0 273.0 26.0 9.24 Including 251.0 257.0 6.0 36.72 Xiji
Slide 27: Investment highlights summary
Low cost operator with strong balance sheet Portfolio of high-quality, long-life mines and development projects Management team that has built 4 mines in 3 countries since 2005 Track record of growing reserves and resources, expanding production and increasing margins Competitive and trans
Slide 28: Thank You
Thank You TSX: ELD NYSE: EGO Total shares outstanding (as at Dec 31, 2012): 714.3 M Investor Relations: Nancy Woo (604) 601-6650 ⋅ nancyw@eldoradogold.com www.eldoradogold.com 28
Slide 29: Background Information
Background Information www.eldoradogold.com 29
Slide 30: Five cornerstone gold mines
Five cornerstone gold mines: Kişladağ Efemçukuru Jinfeng Tanjianshan White Mountain www.eldoradogold.com 30
Slide 31: Kişladağ production overview
PRODUCTION OVERVIEW Location Uşak Province, Western Turkey Deposit Gold porphyry Ownership 100% Eldorado Open pit Type Heap leach gold mine Expected Life of Mine 15-20 years Recovery 65% Strip Ratio 2013 1.75:1 RESERVES AND RESOURCES (at Dec 31, 2012) Proven + Probable Reserves 10.0 Moz Au @ 0.70 g/
Slide 32: Efemçukuru production overview
PRODUCTION OVERVIEW Location Izmir Province, Western Turkey Deposit High grade epithermal gold vein Ownership 100% Eldorado Underground gold mine Type Flotation and Carbon in Leach Expected Life of Mine 12 years Recovery 87% RESERVES AND RESOURCES (at Dec 31, 2012) Proven + Probable Reserves 1.3 Moz
Slide 33: Jinfeng production overview
PRODUCTION OVERVIEW Location Guizhou Province, China Deposit Carlin type 82% Eldorado Ownership 18% Guizhou Lannigou Gold Mine Ltd Open pit and underground gold mine Type Biox and Carbon in Leach Expected Life of Mine 13 years Recovery 85% RESERVES AND RESOURCES (at Dec 31, 2012) Overview Acquired
Slide 34: Tanjianshan production overview
PRODUCTION OVERVIEW Location Qinghai Province, China Deposit Orogenic 90% Eldorado 5% First Institute of Geology and Ownership Mineral Exploration of Qinghai Province 5% Dachaidan Gold Mine Open pit gold mine Type Float roast Carbon in Leach Expected Life of Mine 5 years Recovery 81% Overview Strip
Slide 35: White Mountain production overview
PRODUCTION OVERVIEW Location Jilin Province, China Deposit Orogenic 95% Eldorado Ownership 5% Jilin Tonghua Institute of Geology and Minerals Exploration and Development Underground gold mine Type Carbon in Leach plant Expected Life of Mine 9 years Recovery 80% Overview Acquired by Eldorado from S
Slide 36: Olympias production overview
PRODUCTION OVERVIEW Location Chalkidiki Peninsula, Northern Greece Deposit Polymetallic gold, silver, lead and zinc 95% Eldorado Ownership 5% Aktor SA Underground mine Type (previously mined using underground drift and fill) Estimated Development Capital US$165 million Production (from tailings) Q4
Slide 37: Vila Nova iron ore production overview
PRODUCTION OVERVIEW Location Amapa State, Brazil Ownership 100% Eldorado Type Open pit iron ore mine Expected Life of Mine 9 years RESERVES AND RESOURCES (at Dec 31, 2012) Overview Commercial production began in 2011 Proven + Probable Reserves 9.7 Mt @ 58.8% Fe 2013 Guidance Measured + Indicated R
Slide 38: Stratoni production overview
PRODUCTION OVERVIEW Location Chalkidiki Peninsula, Northern Greece Deposit Replacement mixed sulphide 95% Eldorado Ownership 5% Aktor SA Underground drift and fill Type Multi-stage flotation Expected Life of Mine 5 years RESERVES AND RESOURCES (at Dec 31, 2012) 5.3 Moz Ag @ 184 g/t Proven + Probable
Slide 39: Five key development projects
Five key development projects: Skouries Perama Hill Certej Tocantinzinho Eastern Dragon www.eldoradogold.com 39
Slide 40: Skouries construction overview
CONSTRUCTION OVERVIEW Chalkidiki Peninsula, Location Northern Greece Deposit Gold-copper porphyry 95% Eldorado Ownership 5% Aktor SA Type Open pit and underground Strip Ratio (open pit) 0.7:1 Estimated Development Capital US$340 million Overview Production Expected 2015 Acquired from European Gold
Slide 41: Perama Hill development overview
DEVELOPMENT OVERVIEW Eastern Thrace, northern Location Greece Epithermal gold-silver vein Deposit deposit Ownership 100% Eldorado Type Open pit gold mine Expected Life of Mine 8 years 90% (Gold) Expected Recovery 60% (Silver) Estimated Development Capital US$220 million Production Expected Q1 2015 S
Slide 42: Certej development overview
DEVELOPMENT OVERVIEW “Golden Quadrilateral” area Location of the Apuseni Mountains, Western Romania Epithermal gold-silver Deposit deposit Ownership 80% Eldorado Open pit Type (Previously mined via shallow open pit) Expected Life of Mine 12 years Estimated Development Capital US$270 million Overview
Slide 43: Tocantinzinho development overview
DEVELOPMENT OVERVIEW Tapajos district, Para State, Location central Brazil Shallow, intrusion-hosted, Deposit non-refractory gold deposit Ownership 100% Eldorado Type Open pit gold mine Expected Life of Mine 11 years RESERVES AND RESOURCES (at Dec 31, 2012) Proven + Probable Reserves 1.9 Moz Au @ 1.
Slide 44: Eastern Dragon development overview
DEVELOPMENT OVERVIEW Location Heilongjiang Province, China Deposit High-grade, epithermal, gold-silver vein 95% Eldorado Ownership 5% County (Daxinglanling Yihua Development Company Ltd) Open pit and underground gold mine, Type CIL plant under construction Expected Life of Mine 7 years Expected Reco
Slide 45: 2013 Exploration budget: US$98.5 million
2013 Exploration budget: US$98.5 million Romania ($12m) 5 projects 34,000 meters Vancouver (Head Office) ($3.5m) Greece ($23m) 6 projects 47,000 meters Turkey ($12m) China ($22m) 4 projects 9 projects 25,000 meters 59,000 meters Brazil ($16m) 4 projects 16,000 meters Other Proj
Slide 46: Summarized Financial Results
Summarized Financial Results 2012 2011 Revenues (millions) $1,147.5 $1,103.7 Gold sold (ounces) 625,394 658,919 Average realized gold price ($/ounce) $1,674 $1,581 Cash operating costs ($/ounce sold) (1) $483 $405 Total cash cost ($/ounce sold) (1) $554 $472 Gross profit from gold mining operations(
Slide 47: Reserves and resources by project
Total Proven and Probable Total Meaured and Indicated Inferred Resources Tonnes Grade Ounces Tonnes Grade Ounces Tonnes Grade Ounces (x1000) (Au g/t) (x1000) (x1000) (Au g/t) (x1000) (x1000) (Au g/t) (x1000) Certej (See Note 5) 106,700 1.27 4,380 24,400 1.01 800 Eastern Dragon 3,090 7.71 764 3,500 7
Slide 48: TSX: ELD NYSE: EGO
TSX: ELD NYSE: EGO Total shares outstanding (as at Dec 31, 2012): 714.3 M Investor Relations: Nancy Woo (604) 601-6650 ⋅ nancyw@eldoradogold.com www.eldoradogold.com 48