Slide 1: Advancing the Filo del Sol Copper-Gold-Silver Project in South America
ADVANCING THE FILO DEL SOL COPPER-GOLD-SILVER PROJECT IN SOUTH AMERICA Corporate Presentation – October 2020 A Lundin Group Company www.filo-mining.com TSXV: FIL | Nasdaq First North Growth Market: FIL
Slide 2: Cautionary Statement
CAUTIONARY STATEMENT Certain statements made and information contained in this presentation constitutes “forward-looking information” and “forward- Estimates of Mineral Reserves and Mineral Resources looking statements” within the meaning of applicable securities legislation (collectively, “forward-
Slide 3: Filo Mining Corp. Company Profile
FILO MINING CORP. COMPANY PROFILE South American Project – Filo de Sol (100% interest) Current Indicated Resource of: Advanced Exploration » 4.4m Ounces of Gold » 147m Ounces of Silver Company » 3.1b Pounds of Copper 7% CAPITAL STRUCTURE SHARE OWNERSHIP FIL TSXV, Nasdaq First North Growth Market Top
Slide 4: Filo del Sol Project
FILO DEL SOL PROJECT Filo del Sol hosts a high-sulphidation epithermal copper-gold-silver deposit associated with a large porphyry copper-gold system. Located in San Juan, Argentina & Chile » Pro-mining jurisdictions » Mining Integration and Complementation Treaty for cross-border projects » 12 km a
Slide 5: Investment Highlights
INVESTMENT HIGHLIGHTS UNPARALLELED GROWTH POTENTIAL Lukas Lundin commented, Existing Cu-Au-Ag resource, backstopped by a robust oxide “…the potential size and scale project. of the Filo del Sol deposit is unparalleled to any project I have been involved with … Our drill results this season are Outst
Slide 6: Exploration
EXPLORATION Filo Mining | Corporate Presentation
Slide 7: 2019 / 2020 Field Program Summary
2019 / 2020 FIELD PROGRAM SUMMARY 2019 / 2020 Program » Approximately 8,000m of drilling completed prior to curtailment of the drilling program » Drone magnetometer & 3D induced polarization ("IP") geophysical surveys Targets Filo Deep Area Tamberias West Filo North Testing porphyry Recently permitt
Slide 8: 2019 / 2020 Select Drill Results
2019 / 2020 SELECT DRILL RESULTS HIGHLIGHT HOLES: FSDH032: total FSDH034: total FSDH038: » All holes ended in strong copper-gold intercept of intercept of highlight mineralization 1,009m @ 1,034m @ intercept of 73m » Three holes are now in excess of 1 0.95% CuEq 0.68% CuEq @ 2.04% CuEq kilometres de
Slide 9: Sections on Holes 25, 34, and 32
SECTIONS ON HOLES 25, 34, AND 32 Moving South to North (1km total span) FSDH25 FSDH34 FSDH32 +500m N of Hole 25 +500m N of Hole 34 Slide 9 Filo Mining | Corporate Presentation
Slide 10: Comparison with Global Copper Intercepts
COMPARISON WITH GLOBAL COPPER INTERCEPTS Best holes over the past 12 months with Copper as the primary commodity CuEq Grade x Date Hole Number Project Country Company From (metres) To (metres) Interval (metres) CuEq (%) Source Document Interval¹ (%-m) 2020-02-24 VHD037 Onto Indonesia PT Sumbawa Timu
Slide 11: 2019 / 2020 Results: Intersections Outside Resource Pit Shell
2019 / 2020 RESULTS SIGNIFICANT INTERSECTIONS OUTSIDE OF THE RESOURCE PIT SHELL Intersections by hole OUTSIDE of resource pit shell Hole ID From (m) To (m) Length (m) Cu % Au g/t Ag g/t CuEq % FSDH029 180.0 800.1 620.1 0.22 0.27 1.8 0.43 FSDH027 70.0 545.4 475.4 0.23 0.29 2.0 0.46 FSDH026 240.0 613.
Slide 12: Development of an Exploration Target
DEVELOPMENT OF AN “EXPLORATION TARGET” BASED ON PREDICTED VOLUMES AND AVERAGED GRADES FROM SAMPLING THE DEEP DRILLING » This target is in addition to the current resource and does not include prospective areas to the north & south » Surface data suggests centre of the system lies between holes FSDH0
Slide 13: Positive PFS (Jan 2019)
POSITIVE PFS (JAN 2019) Filo Mining | Corporate Presentation
Slide 14: Filo del Sol – PFS Results Summary
FILO DEL SOL – PFS RESULTS SUMMARY Cu Copper After-Tax NPV (8%) $1.28b Avg. Annual Cu Production 67 kt Au Gold After-Tax IRR 23% Payback 3.4 Yrs Avg. Annual Au Production 159 koz Ag Silver C1 Cash Cost $1.23/lb CuEq Avg. Annual Ag Production 8,653 koz Slide 14 Filo Mining | Corporate Presentation
Slide 15: Next Steps
NEXT STEPS Filo Mining | Corporate Presentation
Slide 16: 2020 / 2021 Program Highlights
2020 / 2021 PROGRAM HIGHLIGHTS Drilling to the north to test the ~2km gap between FSDH032 and VRC093 to further define the sulphide resource. Target additional high-grade zones as defined by our recent geophysical interpretation. Complete preliminary metallurgical testwork on the sulphide material.
Slide 17: 2020 / 2021 Program Plans
2020 / 2021 PROGRAM PLANS HIGH-GRADE TARGETS » Test several geophysical anomalies which look similar to the high-grade, breccia- hosted mineralization intersected by FSDH038 last season (73m @ 2.04% CuEq.) » Holes will also tighten drill spacing – data gathering for potential mineral resource estima
Slide 18: Experienced Management Team
EXPERIENCED MANAGEMENT TEAM EXPERTISE IN EXPLORATION, PROJECT STUDIES, FINANCING JAMIE BECK BOB CARMICHAEL JEFF YIP President & CEO Vice President Exploration Chief Financial Officer » More than 15 years of international » Also Vice President Exploration of » Also CFO of NGEx Minerals Ltd. project m
Slide 19: Strong & Reputable Board
STRONG & REPUTABLE BOARD EXPERTISE IN EXPLORATION, PROJECT STUDIES, FINANCING, M&A TRANSACTIONS ADAM LUNDIN ALESSANDRO BITELLI ERIN JOHNSTON Chairman » Over 30 years of experience in the resource » Current Managing Director of the industry and in public accounting, both in North Lundin Foundation, a
Slide 20: A Lundin Group Company
A LUNDIN GROUP COMPANY Creating Value for Shareholders The Lundin Group of Companies has a record of creating substantial value for shareholders. Past projects have generated some $15.8 billion. Shareholder Return on Investment* 1757% 1041% 1091% 961% 850% 558% 609% 352% 139% Lundin Mining Red Back
Slide 21: Environmental, Social and Governance (ESG)
ENVIRONMENTAL, SOCIAL AND GOVERNANCE (ESG) LAYING THE STRATEGIC GROUNDWORK FOR RESPONSIBLE MINERAL DEVELOPMENT » Lundin Group’s commitments, culture and track record set expectations for ESG » Filo’s Responsible Mineral Development Policy frames corporate approach » Alignment with International Stan
Slide 22: Lundin Foundation: ESG Differentiator
LUNDIN FOUNDATION: ESG DIFFERENTIATOR A Canadian corporate foundation whose purpose is to position Lundin Group companies as the resource developers of choice, resulting in stronger communities. SINCE OUR 2007 INCEPTION, WE HAVE DISBURSED MORE THAN $72.6M USD INTO INITIATIVES THAT ENABLE LOCAL EMPLO
Slide 23: Contact Us
Filo Mining | Corporate Presentation CONTACT US filo-mining.com Filo Mining Corp. Suite 2000 - 885 West Georgia Street Vancouver, BC, V6C 3E8 Canada FOR MORE INFORMATION CONTACT Amanda Strong Robert Eriksson Investor Relations Canada Investor Relations and Media Sweden info@filo-mining.com reriksson
Slide 24: Appendix
APPENDIX Filo Mining | Corporate Presentation
Slide 25: Indicated and Inferred Resource
INDICATED AND INFERRED RESOURCE Cu 3.1 Billion lbs Cu Copper INDICATED Cu INFERRED 1.0 Billion lbs Au 4.4 Million oz Au Gold INDICATED Au INFERRED 1.8 Million oz Ag 146.9 Million oz Ag Silver INDICATED Ag 34.8 Million oz INFERRED Refer to slide 23 for additional details regarding the reporting of th
Slide 26: Mineral Resource
MINERAL RESOURCE Tonnes Cu Au Ag Lbs Cu Ounces Au Ounces Au Zone Cutoff Category (millions) (%) (g/t) (g/t) (millions) (thousands) (thousands) Indicated 349.6 0.34 0.32 12.6 2,656 3,623 141,364 Oxide * See notes Inferred 103.9 0.26 0.32 8.7 585 1,083 29,067 Indicated 75.5 0.27 0.34 2.2 451 813 5,374
Slide 27: Pre-Feasibility Results
PRE-FEASIBILITY RESULTS FILO DEL SOL – PFS RESULTS – January 2019 Pre-Tax NPV (8%) ($B) $1.86 ANNUAL METAL Pre-Tax IRR (%) 27% PFS METALS PRODUCTION PROFILES After-Tax NPV (8%) ($B) $1.28 PRICES Payable Copper After-Tax IRR (%) 23% ASSUMED 90 80 70 Undiscounted After-Tax Cash Flow ($B) $3.23 60 Tonn
Slide 28: Probable Mineral Reserves
PROBABLE MINERAL RESERVES FILO DEL SOL MINERAL RESERVE STATEMENT (@ 0.01 $/T NVPT CUT-OFF) Tonnage Grade Contained Metal Category (all domains) (Mt) Cu (%) Au (g/t) Ag (g/t) NVPT ($/t) Cu (M lbs) Au (K oz) Ag (K oz) Proven _ _ _ _ _ _ _ _ Probable 259.1 0.39 0.33 15.1 25.30 2,226 2,764 126,028 Total