Slide 1: Florida Canyon LOM After-tax Free Cash Flow
(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure. Figure 2: Florida Canyon LOM After-tax Free Cash Flow 1
Slide 2: Florida Canyon After-Tax NPV and Cash Flow Sensitivity to Gold Price
(1) Please refer to "Cautionary Note Regarding Non-GAAP Measures" for a description of non-GAAP financial measures included in this figure. Table 2: Florida Canyon After-Tax NPV and LOM After-tax Net Cash Flow ("CF") Sensitivity to Gold Price 1 Gold Price Estimate ($/oz) Change in Gold Price After-T
Slide 3: Updated Mineral Resource Estimate
Updated Mineral Resource Estimate Mineral resources were re-estimated from the resource model released in 2024 and include historic waste rock stockpiles whose grade exceeds current cut-off grades for the Project. The updated Mineral Resource Estimate ("MRE") incorporates a revised geological interp
Slide 4: Notes for Florida Canyon Mineral Resource Estimate
Notes for Florida Canyon Mineral Resource Estimate (1) Mineral resources are reported, using the 2014 CIM Definition Standards, with an effective date of May 31, 2026. The qualified person as defined under NI 43-101 for the estimate is Ms. Terre Lane, MMSA QP, a Global Resource Engineering, Ltd. emp
Slide 5: Notes to Mineral Reserves
Notes to Mineral Reserves (1) Mineral reserves are reported at the point of delivery to the process plant, using the 2014 CIM Definition Standards, with an effective date of May 31, 2026. The qualified person as defined under NI 43-101 for the estimate is Ms. Terre Lane, MMSA QP, a Global Resource E
Slide 6: Processing and Recovery
Processing and Recovery Crushed ore at Florida Canyon passes through two stages of open circuit crushing to a final crush size of 80% minus 2.5 inches with processing capabilities of 21,000 tonnes per day ("tpd"). Crushed ore is then agglomerated with a polymer binding agent to improve solution perc
Slide 7: Florida Canyon Project Mining & Processing Summary
Table 5: Florida Canyon Project Mining & Processing Summary ROM Crushing Total Mining Total Ore Mined (Kt) Total Waste (Kt) Total Mined (Kt) Strip Ratio (Waste: Ore) Grade & Contained Metals Average Gold Grade (g/t Au) Contained Gold (Koz Au) Production LOM Average Gold Recovery (%) LOM Gold Recover
Slide 8: Florida Canyon LOM Cash Costs and Site-Level AISC
Table 7: Florida Canyon LOM Cash Costs and Site-Level AISC 1 $/oz Au Site-Level Cash Costs, AISC Breakdown By-Product Site-Level All-in Sustaining Costs - Excluding Closure Costs $2,331 Site-Level All-in Sustaining Costs - Including Closure Costs $2,373 (1) Please refer to "Cautionary Note Regarding