Slide 1: Willcox Wharf to Windmill Point Transmission Rebuild Project
Willcox Wharf to Windmill Point Transmission Rebuild Project © 2003 Dominion
Slide 2: Project Overview
Project Overview Dominion plans to replace four deteriorating transmission structures on an existing 500kV line between Willcox Wharf and Windmill Point The transmission line was placed into service in the 1960s, and the structures have reached the end of their functional life Two structures a
Slide 3: Project Need
Project Need Significant steel deterioration
Slide 4: Project Need
08/13/26 mo) oD) co) 2 ~ UO oD) — Oo San a.
Slide 5: Project Area Map
Project Area Map Legend Existing transmission line Structures to be replaced
Slide 6: Structure Drawings – On the James
Structure Drawings – On the James (Not to Scale) Existing (Cor-ten) Proposed (Galvanized Steel) Subject to Final Engineering Structure height and style will remain the same.
Slide 7: Structure Drawing – Anchor
Structure Drawing – Anchor (Not to Scale) Existing Proposed* Subject to Final Engineering *Proposed structures will be galvanized steel and approximately 15 feet taller than existing structures.
Slide 8: Other Project Characteristics
Other Project Characteristics Tentative Construction Dates: September 15 – December 15, 2017 Construction: An extended construction schedule may be necessary at times to minimize impacts Construction may occur seven days a week from 7 a.m. to 7 p.m. Some helicopter work may occur
Slide 9: Community Benefits
Community Benefits Project will: Replace aging infrastructure Maintain continued reliable service to local customers Help strengthen the electrical grid Require no new right of way Require no new foundations in the river Have minimized underwater disturbance
Slide 10: Community Outreach
Community Outreach State and Local Officials: Meetings with public officials and other community stakeholders (October 2016) Planned Public Outreach: Letters and fact sheets mailed to nearby landowners (October 2016) Website available at www.dom.com, keyword: “Willcox” (October 2016) Open Ho
Slide 11: Target Schedule
Target Schedule (Subject to change) Public outreach: meetings with elected officials, letters to Fall 2016 residents, website, open house Winter 2016 Application submitted to the SCC for approval Concurrent with Secure necessary permits for construction SCC review Spring 2017 Community outreach and
Slide 12: The Transmission Line Approval Process
The Transmission Line Approval Process Virginia's State Corporation Commission (SCC) has regulatory authority over all electric utilities and requires that all transmission facilities at or above 138 kV be certified by the SCC. The SCC determines the need for a proposed line and the route. Among oth