Green Technology Metals Limited · ASX:GT1

Green Technology Metals — Investor Presentation (October 2023)

36 slides from Green Technology Metals's investor presentation, Oct 9, 2023

  1. Slide 1: Investor Presentation October 2023

    For personal use only INVESTOR PRESENTATION OCTOBER 2023 Building the pre-eminent vertically integrated Lithium business in Ontario, Canada ASX | GT1

  2. Slide 2: Indigenous Partners Acknowledgement

    INDIGENOUS PARTNERS ACKNOWLEDGEMENT For personal use only We would like to say Gchi Miigwech to our Indigenous partners. GT1 appreciates the opportunity to work in the Traditional Territory and remains committed to the recognition and respect of those who have lived, travelled, and gathered on the l

  3. Slide 3: Corporate Snapshot

    CORPORATE SNAPSHOT 276.1M SHARES ON ISSUE GT1 $0.42 $115.96M $90.36 $25.6M $0 5.8M OPTIONS For personal use only ASX CODE SHARE PRICE MARKET CAP EV CASH DEBT 18.5M PERFORMANCE RIGHTS SHARE REGISTER SHARE PRICE PERFORMANCE 0.8 0.7 LGES 7.87% AMCI 0.6 9.07% WARATAH 0.5 4.97% 0.4 LAC 4.82% OTHERS 0.3 6

  4. Slide 4: Company Overview

    COMPANY OVERVIEW Extensive Portfolio of Company Highlights projects in Tier-1 jurisdiction For personal use only Tier-1, low risk mining jurisdiction 22.5Mt1 1.14% ▪ Prime position to support the North American EV market TOTAL JORC MINERAL AVERAGE LI2O GRADE PENNOCK ▪ Supportive and proactive Govern

  5. Slide 5: Board and Management

    BOARD AND MANAGEMENT Extensive experience and proven track record of rapidly advancing and delivering lithium projects globally For personal use only JOHN YOUNG CAMERON HENRY Non-Executive Chairman Executive Director Highly experienced geologist 20 years' experience managing and operating public com

  6. Slide 6: Executive Team

    EXECUTIVE TEAM For personal use only LUKE COX MATT HERBERT Chief Executive Officer Chief Operation Officer SCOTT GILBERT NATHAN SIMS Chief Financial Officer VP Operations - Exploration JOHN WINTERBOTTOM ROGER SOUCKEY GM Technical Services VP HR and Communities METALS GREEN TECHNOLOGY METALS 66

  7. Slide 7: Why Ontario?

    GT1 is strategically WHY ONTARIO? positioned at the heart of the Ontario battery TIER-1 MINING JURISTDICTION ecosystem, making it the ideal choice as the $1.5b >$25b Western Hub Eastern preferred local lithium For personal use only Hub In Strategic Innovation Fund Committed in battery minerals suppl

  8. Slide 8: Supply Chain Rock to EV-Battery

    SUPPLY CHAIN ROCK TO EV-BATTERY For personal use only MINE MADE IN ONTARIO CONCENTRATE GT1 Organic Growth Spodumene Process Plant CONVERT CAM BATTERY CAR Exploration LITHIUM CONVERSION CATHODE ACTIVITY BATTERY MANUFACTORING CAR MANUFACTORING GT1 Resources FACILITY MATERIAL FACILITY FACILITY FACILITY

  9. Slide 9: Pioneering Ontario's Lithium Future

    PIONEERING ONTARIO'S LITHIUM FUTURE 3 stage integrated strategy to become the first Concentrates and Chemicals producer in the region For personal use only GREEN TECHNOLOGY Metals 1. Seymour has an existing Mineral Resource estimate of 9.9 Mt @ 1.04% Li2O (comprised of 5.2 Mt at 1.29% Li2O Indicated

  10. Slide 10: Integrated Project - Flowsheet

    INTEGRATED PROJECT - FLOWSHEET Conventional mining and For personal use only conversion processes Concentrators  Seymour: Crushing and Dense Media Separation (DMS)  Root: Crushing, DMS, milling, magnetic removal, mica and spodumene flotation Conversion Facility  Thunder Bay: Analcime by-product t

  11. Slide 11: World Class Infrastructure

    WORLD CLASS INFRASTRUCTURE The Integrated Project located in Northern Ontario, one of the premier regions in the world for lithium exploration, with proximity to infrastructure, car manufacturers, battery storage and major high-tech population centres compared to other provinces in Canada For person

  12. Slide 12: Indicative Timeline to Production

    INDICATIVE TIMELINE TO PRODUCTION For personal use only 1. All proposed production dates quoted are indicative GREEN TECHNOLOGY METALS 12

  13. Slide 13: Strategic Highlights

    STRATEGIC HIGHLIGHTS LOI signed for conversion facility For personal use only First ever Offtake agreement Transformational 22.5 million in Thunder Bay with due diligence executed and A$20m strategic tonne resource base across underway Investment from LG Energy Ontario Projects Solution SIF Funding

  14. Slide 14: Preliminary Economic Assessment

    PRELIMINARY ECONOMIC ASSESSMENT The full potential of our mineral endowment will be unlocked through Pit to Product Lithium Business Development Integrating mine, concentrator and conversion plant Study to Include For personal use only  A sustainable, valuable vertically integrated lithium operatio

  15. Slide 15: Stage 1: Eastern Hub

    Stage 1: For personal use only EASTERN HUB FALCON JUNIOR OWNERSHIP 100% Owned AREA 32,720 Hectares RESOURCE (Current) 9.9Mt @ 1.04% Li2O (with 5.2Mt @ 1.29% Indicated) EXPLORATION TARGET 22 to 26 Mt @ 0.8 to 1.5% Li2O DRILLING 74,667m STAGE Pre-Development EXPECTED FIRST 2025 PRODUCTION The potentia

  16. Slide 16: Seymour

    SEYMOUR Central processing facility located at Seymour Potential to add satellite pits from the Junior and Falcon projects For personal use only Mineral Resource  Increased geological confidence with +50% in the Indicated category  7736m infill drilling program underway to increase mineral resourc

  17. Slide 17: Green Lithium Production in Canada

    GREEN LITHIUM PRODUCTION IN CANADA Minimal environmental impact – small operation For personal use only Designed with minimal ground impact  Minimised footprint - only~500ha  2 open pits – staged North and South Aubry  Dry stacked tailings No chemicals in processing DMS only concentrator – NO CHE

  18. Slide 18: Seymour Project - Progress

    SEYMOUR PROJECT - Progress Plant layout and sections For personal use only GREEN TECHNOLOGY METALS 18

  19. Slide 19: Permitting Schedule

    PERMITTING SCHEDULE 2021 - 2022 Baseline data collection Technical studies & engineering For personal use only    Indigenous consultation  Pre-submission consultation with government agencies 2023  3 years of baseline data completed  Indigenous consultation – In progress  Project design compl

  20. Slide 20: Testwork - Concentrator

    TESTWORK - Concentrator Conventional mining processes utilising industry expertise Seymour – Very coarse, clean in nature – Spodumene For personal use only HLS  Completed – Achieved a 72% recovery.  Demonstrating Seymour’s coarse grain spodumene is amenable to DMS.  Opportunity for further optimi

  21. Slide 21: Junior Lithium Project

    JUNIOR LITHIUM PROJECT Potential to significantly add to Eastern-hub Sample Name E N Type Li2O % resource base F713162 Despard 422507 5586337 Float 3.23 For personal use only LCT spodumene-bearing pegmatites F713124 Despard 422504 5586341 Outcrop 2.56 Tape measuring up to 40 meters in length and app

  22. Slide 22: Stage 2: Conversion Facility

    Stage 2: For personal use only CONVERSION FACILITY OWNERSHIP Under option AREA 25 Hectares STAGE Preliminary Economic Assessment PRODUCTION 2028 22

  23. Slide 23: Conversion Facility

    CONVERSION FACILITY Stage 1 – proposed circa 20-25 kt capacity For personal use only Stage 2 – plant/site layout confirmed for additional train Proposed Alkali leach flow sheet - analcime by-product that can be treated and potentially used for civil/fill applications. Flow sheet currently being impl

  24. Slide 24: Conversion Facility

    CONVERSION FACILITY  Initial emissions studies underway – complete Oct 23  Geotechnical investigation - work commenced Serviced site – power, natural gas, water and municipal sewer. For personal use only   Grid power – Hydropower connection 115kV line adjacent to the property  Port and rail acc

  25. Slide 25: Stage 3: Western Hub

    Stage 3: For personal use only WESTERN HUB OWNERSHIP 100% Owned AREA 23,095 Hectares RESOURCE (Current) 12.6Mt @ 1.21% Li2O EXPLORATION TARGET 20-24Mt @ 0.8 to 1.5% Li2O DRILLING 42,000m STAGE Preliminary Economic Assessment EXPECTED FIRST 2028/9 PRODUCTION The potential quantity and grade of Explor

  26. Slide 26: Western Hub - Root Bay

    WESTERN HUB Root Bay Excavation For personal use only The original Root Bay outcrop was only exposed when the local forestry came through and cleared roads and trees. GT1 teams have been successfully trenching the ridge and exposing LCT pegmatites East and West of the original find. Exploration Geol

  27. Slide 27: Root Bay - Deep Potential

    ROOT BAY – Deep Potential Root Bay Thickness For personal use only The stacked pegmatites within the Root Bay area progressively get thicker from East to West with Pegmatite #6 on the west averaging 18m thickness. Depth All of the pegmatites are open at depth with the capability to extend further. P

  28. Slide 28: Root Project - Plant Layout & Sections

    ROOT PROJECT – Plant layout & sections  High grade - finer grained spodumene however still coarse against benchmarks For personal use only  Hybrid DMS/Flotation concentrator envisaged – better recoveries  Proposed standard Tailings Storage Facility (TSF)  Standard permitting timelines – federal

  29. Slide 29: Stage 3: Additional Projects

    Stage 3: For personal use only ADDITIONAL PROJECTS 29

  30. Slide 30: Allison

    ALLISON AREA 9,444 Hectares For personal use only STAGE Exploration  Located 42km from the Root Lithium Project and easily accessible by road  Believed to be the source of LCT pegmatite occurrences in the region  3 claim blocks; North, Central and South lie on the edge of a fertile granite believ

  31. Slide 31: Pennock

    PENNOCK AREA 1389 Hectares For personal use only STAGE Exploration An extensive reconnaissance program is underway over the entire Pennock project. Pennock is located adjacent to Frontier Lithium’s Pennock Pegmatite, that has a 30x16m spodumene-bearing outcrop with results from Frontiers channel sam

  32. Slide 32: What is Next?

    WHAT IS NEXT?  Root Bay MRE update & further drilling For personal use only  Seymour DMS Test work results – October  Conversion Test work – Q4 2023 & ongoing  Integrated PEA – Q4 2023  Junior maiden drilling program – Q1 2024  Seymour MRE update  Finalisation of partnering process for downst

  33. Slide 33: Contacts

    For personal use only Contacts Chief Executive Officer Luke Cox L1, 338 Barker Rd, Subiaco Perth, Western Australia 6008 Email: info@greentm.com.au Investor Relations and Media Jacinta Martino Email: ir@greentm.com.au Share registry Automic Group Email: hello@automic.com.au ASX GT1

  34. Slide 34: Appendix | Mineral Resource Estimate

    APPENDIX | MINERAL RESOURCE ESTIMATE Tonnes Li2O Ta2O5 Project (Mt) (%) (ppm) Root Project For personal use only Root Bay Inferred 8.1 1.32 35 McCombe Inferred 4.5 1.01 110 Total 12.6 1.21 62 Seymour Project1 North Aubry Indicated 5.2 1.29 161 Inferred 2.6 0.90 120 South Aubry Inferred 2.1 0.50 90 T

  35. Slide 35: Appendix | Disclaimer

    APPENDIX | DISCLAIMER Important information: Green Technology Metals Limited (ASX GT1) ACN 648 657 649 (the "Company") is the issuer of this presentation. Not a disclosure document: This presentation is not a disclosure document for the purposes of Chapter 6D of the Corporations Act 2001 (Cth) ("Cor

  36. Slide 36: Appendix | Competent Persons Statement

    APPENDIX | COMPETENT PERSONS STATEMENT The information in this Presentation that relates to the Exploration Results is based on activities carried out by Mr Luke Cox. Mr Cox has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and the act

Green Technology Metals — Investor Presentation (October 2023) on 6ix