Cochin Shipyard Limited · NSE:COCHINSHIP
Cochin Shipyard — Q1 FY2019 Earnings Presentation
21 slides from Cochin Shipyard's earnings presentation, August 2018
Slide 1: Cochin Shipyard Limited Investor Presentation (Q1 FY19)
Cochin Shipyard Limited Investor Presentation (Q1 FY19) – Aug 18
Slide 2: Revenue Mix: Quarterly Performance
REVENUE MIX (Rs Cr.) Quarterly Performance Particulars (Rs. Cr) FY 19 Q1 FY 18 Q1 YoY % FY 18 Q4 Shipbuilding 454.39 398.25 14% 503.53 Ship Repair 204.34 158.00 29% 97.07 Turnover 658.73 556.25 18% 600.60 Other Income 57.58 38.81 48% 38.09 Total Income 716.31 595.06 20% 638.69
Slide 3: Highlights: FY19 – Q1 Ship Building
HIGHLIGHTS: FY19 – Q1 SHIP BUILDING Commenced Block erection of 500 Pax cum 150 T Cargo vessels (2 nos) for A&N Administration on 28 April 2018. Project at advanced stages. Scheduled for launching by end Sep 2018. Block fabrication of 1200 Pax cum 1000 Tonne Cargo vessels (2 nos) in advanced sta
Slide 4: Highlights: FY19 – Q1 Ship Building
HIGHLIGHTS: FY19 – Q1 SHIP BUILDING Secured order for construction of 10 nos. Ro-Ro and Ro Pax vessels for Inland Waterways Authority of India (IWAI) @ Rs. 102 Crores. Steel cutting ceremony for the vessels held on 10 Aug 18. Other vessels Outfitting of equipments, pipes and electrical systems
Slide 5: Highlights: FY19 – Q1 Ship Repair
HIGHLIGHTS: FY19 – Q1 SHIP REPAIR 53 vessels handled since April 2019. 20 vessels are undergoing repairs presently at CSL. INS Vikramaditya docked for refit. Project cost-Rs. 500 Cr. approx. Vessel repairs progressing on schedule. Other Defence vessel of order value of Rs. 100 Cr. Approx. Un
Slide 6: Orderbook – Update (as on 13 Aug 18)
ORDERBOOK – UPDATE (as on 13 Aug 18) Balance orders Sl. Total No. Total Value Project in hand No. of Vessels (INR Cr.) (INR Cr.) 1 Indigenous Aircraft Carrier for Indian Navy 1 2848.00 616.00 2 Technology Demonstration Vessel for DRDO 1 365.00 142.00 500 Pax cum 150 Ton Cargo Vessels for A&N 3 2 474
Slide 7: Annual Performance
ANNUAL PERFORMANCE
Slide 8: Revenue Mix: Annual Performance
REVENUE MIX (Rs Cr.) Annual Performance Particulars (Rs cr) FY18 FY17 YoY % Shipbuilding 1731.86 1515.82 14% Ship Repair 623.27 543.05 15% Turnover 2355.12 2058.87 14% Other Income 189.16 158.63 19% Total Income 2544.28 2217.50 15%
Slide 9: Key Financial Parameters
KEY FINANCIAL PARAMETERS Particulars (INR cr) FY18 FY17 Networth 3256 2029 Book value / share (Rs) 240 179 Net Debt 123 123 EBITDA (%)* 28 26 EPS (Rs) 31.03 28.39 * Includes other income but excludes one off items
Slide 10: Turnover (Rs Cr) & EBITDA Margins
TURNOVER (RS CR) & EBITDA MARGINS 2500 35.00% 2355 1996 30.00% 29.21% 1996 27.76% 2000 26.69% 1860 26.35% 25.00% 1637 1554 22.00% 1462 1405 20.61% 23.71% 1500 20.45% 22.81% 20.23% 20.00% 1256 1249 15.00% 1000 10.00% 500 5.00% 0 0.00% FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 Turnover EBITDA
Slide 11: Profit After Tax (Rs Cr.) & PAT Margins (%)
PROFIT AFTER TAX (Rs Cr.) & PAT MARGINS (%) 450 20.00% 397 18.00% 400 17.86% 16.85% 16.00% 350 15.57% 322 15.62% 13.78% 14.00% 300 12.74% 275 12.27% 11.86% 11.92% 12.64% 12.00% 250 228 235 223 10.00% 194 200 185 172 8.00% 160 150 6.00% 100 4.00% 50 2.00% 0 0.00% FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY
Slide 12: Return Efficiencies
RETURN EFFICIENCIES Networth (INR cr), Return on Networth (%) FY13 FY14 FY15 FY16 FY17 FY18 16% 16% 16% 15% 14% 12% 3256 2029 1732 1561 1353 1176 Networth Return on Networth Debt Equity Ratio 0.04
Slide 13: Shareholding Pattern
SHAREHOLDING PATTERN
Slide 14: Shareholding Pattern as on August 07, 2018
SHAREHOLDING PATTERN as on August 07, 2018 Percentage Holding Top 5 Public FY18 Shareholders 3.45 11.26 Reliance MF 5.94% 10.29 HDFC MF 2.30% Pinebridge Global 2.00% Fund 75 ICICI Lombard 0.81% Aditya Birla Sunlife 0.62% Promoters Mutual Funds FPIs Others
Slide 15: Expansion Projects Overview
EXPANSION PROJECTS OVERVIEW
Slide 16: Major Expansions: New Large Drydock
MAJOR EXPANSIONS NEW LARGE DRYDOCK Facility : Dock : 310m x 75/60m x 13m and other allied facilities Estimate : Rs. 1799 Crores Target Completion : June 2021 Present Status: Construction works of Plant and Machinery awarded to M/s. Larsen & Toubro Ltd on 27 April 18. Construction works com
Slide 17: Major Expansions: International Ship Repair Facility (ISRF)
MAJOR EXPANSIONS INTERNATIONAL SHIP REPAIR FACILITY (ISRF) Facility : Shiplift: 130m x 25m x 6000T with 6 workstations Estimate : Rs 970 Crores Target Completion : Nov 2019 Present Status: Major equipment – Shiplift & transfer system ordered on consortium of M/s. Broehl & M/s. IMG, Germany i
Slide 18: Geographical Expansions: Hooghly Cochin Shipyard Limited, Kolkata
GEOGRAPHICAL EXPANSIONS HOOGHLY COCHIN SHIPYARD LIMITED, KOLKATA (JVC : CSL - 74% equity) Modern Small Ship building facility being set up at Nazirgunje in Kolkata Investment of Rs. 160 Cr. envisaged Contractors shortlisted Pre-bid meeting conducted. Tendering process progressing Construct
Slide 19: Geographical Expansions: Ship Repair at Ports
GEOGRAPHICAL EXPANSIONS SHIP REPAIR AT PORTS Mumbai Port Trust MoU signed with Mumbai Port Trust in Jan 2018 for ‘Development, Management and Operations’ of Ship Repair Facility at Indira Dock. Formal Agreement to be signed shortly. Operations to commence in Oct 18. Kolkata Port Trust MoU inke
Slide 20: Disclaimer
Disclaimer This presentation and the following discussion may contain “forward looking statements” by Cochin Shipyard Limited (“Cochin” or “CSL” or the “Company”) that are not historical in nature. These forward looking statements, which may include statements relating to future results of operation
Slide 21: Thank You