Sandfire Resources Ltd · ASX:SFR

Sandfire Resources — Sandfire Resources NL — Diggers & Dealers Mining Forum 2011

26 slides from Sandfire Resources's conference presentation, Aug 1, 2011

  1. Slide 1: Diggers & Dealers Mining Forum

    For personal use only Diggers & Dealers Mining Forum 1 August 2011 1

  2. Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer Competent Person’s Statement For personal use only • The information in this public presentation that relates to Exploration Results and Mineral Resources is based on information compiled by Mr John Evans who is a Fellow of the Australasian Institute of Mining an

  3. Slide 3: Our Mission

    For personal use only Our Mission • To develop and operate the 100%-owned premier high-grade DeGrussa copper gold mine • To deliver superior returns to our owners • To make new discoveries within our existing portfolio of copper-gold, lead- zinc, uranium, iron ore and manganese projects in Australia

  4. Slide 4: Company Snapshot

    Company Snapshot • DeGrussa Copper-Gold Project moving into production For personal use only • Discovery to development in two years (2009 to 2011) • DFS project operating cash flow of $2.4 billion (pre-tax) on $4.2 billion revenue • DFS does not include oxide copper or further discoveries • Sandfir

  5. Slide 5: Recent Achievements

    For personal use only Recent Achievements • DeGrussa Definitive Feasibility Study completed and approved • Development activities well advanced with +250 personnel on site • Mining and process plant works have commenced • First copper production on track for Q1 2012 (DSO) • Key project development a

  6. Slide 6: Corporate Summary

    Corporate Summary Issued Capital: 149.4M ordinary shares Board For personal use only 10.9M options DEREK LA FERLA – Non-executive Chairman Cash (30 June 2011): A$74.0M KARL SIMICH – Managing Director/CEO Major Shareholders W. JOHN EVANS – Executive Technical Director Oz Minerals 18.8% Posco 15.9% JO

  7. Slide 7: Asset Overview

    Asset Overview Western Australia Northern Territory – For personal use only Borroloola Project COPPER-GOLD LEAD-ZINC • Warramana • DeGrussa – production and exploration COPPER • Greater Doolgunna – exploration • Tawallah 1/2 GOLD IRON ORE • Greater Doolgunna – exploration • Roper Bar LEAD-ZINC URANI

  8. Slide 8: From Concept to Cash

    For personal use only From Concept to Cash Discovery to DFS in Discovered April 2009 2 years Maiden Mineral Resource February 2010 Pre-Feasibility Study, Ore Reserve March 2011 Mine development commenced April 2011 Definitive Feasibility Study June 2011 Today Plant construction commencing shortly Pr

  9. Slide 9: From Concept to Cash: DFS Outcomes

    For personal use only From Concept to Cash DFS Outcomes First Production Q1 2012 (DSO), Q3 2012 (Conc.) 10.72Mt @ 5.1% Cu, 1.7g/t Au Life-of-mine extraction from Ore (541,000t contained copper, Reserves and Mineral Resources 599,000oz contained gold) discovered to date 93% Mineral Resource to Ore Re

  10. Slide 10: Years, +200,000m of Drilling, Four Deposits

    For personal use only 2 Years, +200,000m of Drilling, Four Deposits 10

  11. Slide 11: DeGrussa Project – Open Pit Operations

    For personal use only DeGrussa Project – Open Pit Operations • Early extraction of DSO Ore Reserves: • 0.14Mt @ 25.6% Cu, 2.5g/t Au • 37,000t copper, 12,000oz gold (Contained) • Early sulphide copper ore for plant commissioning • Oxide copper resources to be stockpiled for proposed processing 11

  12. Slide 12: DeGrussa – Key Parameters

    DeGrussa – Key Parameters • Life-of-mine extraction of 10.72Mt @ 5% Cu, 1.7g/t Au (541,000t For personal use only copper, 599,000oz gold – contained) • Conventional open pit mining operation (~2 years) and long-term underground mine (initial 7+ year mine life) • Conventional 1.5Mtpa on-site concentr

  13. Slide 13: DeGrussa – Financial Evaluation and Price Assumptions

    DeGrussa – Financial Evaluation and Price Assumptions Life-of-mine (LOM) For personal use only $ Billion Project revenue 4.2 Royalties (5% weighted average) (0.2) Operating costs and sustaining capital (1.6) Project operating cash flow (pre-tax) 2.4 Pre-production capital expenditure (0.4) Project c

  14. Slide 14: DeGrussa – Capital and Operating Costs

    For personal use only DeGrussa – Capital and Operating Costs Capital Cost Breakdown A$M Construction (plant, equipment and infrastructure) 267 Open pit mining to access DSO 44 Underground mine development 56 Other pre-production 17 Total pre-production capital 384 Life-of-Mine Operating Cost Estimat

  15. Slide 15: DeGrussa – Annual Grade and C1 Cost Profile

    For personal use only DeGrussa – Annual Grade and C1 Cost Profile 15

  16. Slide 16: DeGrussa – Annual Grade and C1 Cost Profile

    For personal use only DeGrussa – Annual Grade and C1 Cost Profile • Definitive Feasibility Study optimises project cash flows • Higher grades + lower C1 costs in first three years = increased cash flow 16

  17. Slide 17: DeGrussa Project – Development Underway

    DeGrussa Project – Development Underway • Box-cut excavation completed – For personal use only development of Evans Decline has commenced – 150m advanced • Pre-strip of open pit commenced April 2011 – two years from discovery • Bulk earthworks underway for plant construction • +250 people on site •

  18. Slide 18: DeGrussa Project – Development

    For personal use only DeGrussa Project – Development Pre-Feasibility Definitive Feasibility Study Project Financing Infrastructure Construction Major Equipment Concentrator Construction Open Pit Direct Shipping Ore Underground Massive Sulphide Concentrator Ramp-up Shipment 18

  19. Slide 19: DeGrussa – Unlocking the “Corridor of Riches”

    For personal use only DeGrussa – Unlocking the “Corridor of Riches” • Only a small portion of the +15km long prospective stratigraphic sequence has been tested to ~600m • Minimal drilling has been conducted below 50m depth outside of the central mine corridor campaign – A$20-30M budget 19

  20. Slide 20: Major Exploration Push

    For personal use only Major Exploration Push • Developing regional geology model from: • Deep drilling • Sterilisation & pre-development drilling • Mapping & geophysical interpretation • Priority VMS corridor extended from 6km to 10km with transported copper mineralisation • Lithogeochemistry progra

  21. Slide 21: DeGrussa Mineral Field – Regional Exploration

    For personal use only DeGrussa Mineral Field – Regional Exploration 21

  22. Slide 22: Summary

    Summary • Development of DeGrussa Project underway For personal use only • On track to produce first copper next year: • First DSO ore from open pit due Q1 2012 • First underground ore expected Q3 2012 • High-margin production profile – positioned to take advantage of strong copper, gold and other c

  23. Slide 23: Diggers & Dealers Mining Forum

    For personal use only Diggers & Dealers Mining Forum 1 August 2011 23

  24. Slide 24: Appendix – DeGrussa: Mineral Resources

    Appendix – DeGrussa: Mineral Resources Table 1: DeGrussa Copper-Gold Project – March 2011 JORC Resource Statement For personal use only Resource Contained Contained Competent Zone Location Tonnes (Mt) Copper (%) Gold (g/t) Category Copper (t) Gold (oz) Person Gold Measured Open Pit 0.14 - 1.5 - 7,00

  25. Slide 25: Appendix – DeGrussa: Ore Reserves

    Appendix – DeGrussa: Ore Reserves Table 2: DeGrussa Copper-Gold Project – March 2011 Ore Reserve Statement Reserve Mining Contained Copper Contained Gold For personal use only Deposit Tonnes (Mt) Copper (%) Gold (g/t) Category Method (t) (oz) Open Pit - DeGrussa Probable 0.14 25.6 2.5 37,000 12,000

  26. Slide 26: Appendix: Competent Person’s Statements

    Appendix: Competent Person’s Statements Competent Person’s Statement – Mineral Resources For personal use only • The information in this report that relates to Mineral Resources (except the Indicated Resource of Supergene Chalcocite) is based on information compiled by Diederik Speijers who is a Fel