  1. Slide 1: PNC Infratech Limited Investor Presentation Q1 FY27

    PNC Infratech Limited Investor Presentation Q1 FY27

  2. Slide 2: Safe Harbor

    Safe Harbor This presentation and the accompanying slides (the “Presentation”), which have been prepared by PNC Infratech Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any securit

  3. Slide 3: Table of Contents

    Table of Contents 01 Quarterly Highlights 02 Orderbook Details 03 Portfolio of Development Projects on PPP Mode 04 Company Overview 3

  4. Slide 4: Quarterly Highlights

    PNG Quarterly Highlights

  5. Slide 5: Key Updates for Q1FY27

    Key Updates for Q1FY27 ➢ Received Letter of Award from NHAI for Barabanki to Mustafabad HAM project in the state of Uttar Pradesh o The Quoted Bid Project Cost is Rs. 1,728 Crores ➢ Received Letter of Award from NHAI for Mustafabad to Biswariya HAM project in the state of Uttar Pradesh o The Quoted

  6. Slide 6: Key Updates for Q1FY27

    Key Updates for Q1FY27 ➢ Received Completion Certificate for Singraur Uphar - Baranpur Kadipur Ichauli (Package-III) HAM Project o The Company received Completion Certificate for a HAM Project executed by Prayagraj Kaushambi Highway Package 3 Private Limited, a Subsidiary of the Company o The projec

  7. Slide 7: Quarterly Highlights

    Quarterly Highlights Total Revenue (Rs. Crs) EBITDA (Rs. Crs) EBITDA Margin % Profit After Tax (Rs. Crs) +34% +167% +1,230 bps +235% 1,518 375 24.7% 271 1,136 12.4% 141 81 Q1 FY26 Q1 FY27 Q1 FY26 Q1 FY27 Q1 FY26 Q1 FY27 Q1 FY26 Q1 FY27 Debt Position Strong Credit Rating Net Working Capital Days • As

  8. Slide 8: Profitability Statement – Q1 FY27

    Profitability Statement – Q1 FY27 Standalone Consolidated Particulars (Rs. Crs) Q1FY27 Q1FY26 YoY Q1FY27 Q1FY26 YoY REVENUE 1,518 1,136 34% 1,688 1,423 19% EBITDA 375 141 167% 524 367 42% EBITDA margin 24.7% 12.4% 1,230 bps 31.0% 25.8% 520 bps Other Income 42 10 71 31 Depreciation 33 19 39 31 Financ

  9. Slide 9: Segmental Revenue Breakup

    Segmental Revenue Breakup Q1FY26 (Rs. Crs) Q1FY27 (Rs. Crs) 170 (10%) 237 137 (17%) (8%) 103 (7%) 1,083 1,382 (76%) (82%) Roads Water Toll/Annuity 9

  10. Slide 10: Debt Position

    Debt Position Standalone Debt Position (Rs. Crs) Gross Debt to Equity (x) 913 1.5 1.6 741 0.8 0.8 382 399 0.1 0.1 0.1 0.2 FY24 FY25 FY26 Q1FY27 Standalone Debt to Equity Consolidated Debt to Equity Mar-24 Mar-25 Mar-26 Jun-26 Consolidated Debt Position (Rs. Crs) Standalone – Working Capital Days 9,1

  11. Slide 11: Orderbook Details

    Orderbook Details 11

  12. Slide 12: Orderbook Summary

    Orderbook Summary Balance Orderbook Sectors No. of Projects as on 30th Jun. ‘26 (Rs. Crs) Roads - EPC 7 5,148 Roads - HAM 8 3,684 Mining 1 2,847 Water – JJM 7 2,310 Canal 1 732 Airport 2 551 Railways 1 397 Total 27 15,670 * Includes Projects worth Rs. 1,393 Crs where appointed date is awaited 12

  13. Slide 13: Orderbook Mix

    Orderbook Mix By Sector By Geography 2% 3% 18% 5% 23% 2% 1% 10% 4% 56% 19% 20% 17% 3% 18% Maharashtra Madhya Pradesh Karnataka Roads Airport Runway Bihar Andhra Pradesh Rajasthan Railway Mining Chhattisgarh Haryana Water/Canal Uttar Pradesh Uttarakhand Disclaimer: This map is a generalized illustrat

  14. Slide 14: Orderbook Details – Road EPC

    Orderbook Details Road EPC Balance Orderbook as Contract Value incl. Project Name Authority State % Completion on 30th Jun. '26 (Rs. Escalation, if any (Rs. Crs) Crs) Pune Ring Road Project MSRDC Maharashtra 2,272 20% 1,810 Jalna To Nanded Road MSRDC Maharashtra 2,368 27% 1,735 Elevated Flyover - Gw

  15. Slide 15: Orderbook Details – Road HAM

    Orderbook Details Road - HAM Balance Orderbook as Contract Value incl. Project Name Authority State % Completion on 30th Jun. '26 (Rs. Escalation, if any (Rs. Crs) Crs) Bhopal Bypass* NHAI MP 1,091 0% 1,091 Varanasi Kolkata Pkg-6 NHAI Bihar 1,162 25% 871 Varanasi Kolkata Pkg-3 NHAI Bihar 1,028 24% 7

  16. Slide 16: Orderbook Details – Mining and Water JJM

    Orderbook Details Mining Balance Orderbook as Contract Value incl. Project Name Authority State % Completion on 30th Jun. '26 (Rs. Escalation, if any (Rs. Crs) Crs) OB Removal and Coal Extraction by Surface Miner and South Eastern Loading and Transportation of Extracted Coal to Chhattisgarh 2,957 4%

  17. Slide 17: Orderbook Details – Canal, Airports, Railways

    Orderbook Details Canal Balance Orderbook Contract Value incl. Project Name Authority State % Completion as on 30th Jun. '26 Escalation, if any (Rs. Crs) (Rs. Crs) DWRO Water Resources Canal Project -Ap Kurnool AP 1,148 36% 732 Department, Govt. of AP Orderbook – Canal 732 Airports Balance Orderbook

  18. Slide 18: Orderbook Highlights

    Orderbook Highlights Included In Orderbook Won Post 30th June 2026 – Not in Orderbook Western Bhopal Bypass, Madhya Pradesh AAI, Pantnagar Airport, Uttarkhand NH-927: Barabanki to Mustafabad, UP 4 Laning on Hybrid Annuity Mode | Financial Air and Land Side Works| EPC Basis | Letter 4 Lane Highway |

  19. Slide 19: Diversification in Other Segments

    Diversification in Other Segments Solar Project Mining Project Awarding Entity Awarding Entity NHPC Limited – Intermediary Procurer / Renewable Energy Implementing Agency South Eastern Coalfields Limited (SECL), Bilaspur, Chhattisgarh (REIA) Nature of Order Nature of Order Handling, Transport and Ot

  20. Slide 20: Portfolio of Development Projects on PPP Mode

    Portfolio of Development Projects on PPP Mode

  21. Slide 21: Equity Requirement

    Equity Requirement Total Equity Equity Invested Balance to Invested Balance to Invested in 9m Balance to Invested in Projects Requirement Upto 30th Jun. ‘26 (Rs. Crs) FY27 (Rs. Crs) FY28 (Rs. Crs) (Rs. Crs) (Rs. Crs) 12 HAM Projects 1,623 1,187 436 226 210 Total 1,623 1,187 436 226 210 21

  22. Slide 22: Toll/Annuity Projects

    Toll/Annuity Projects PNC Share of Invested Total Debt as on % State / JV Kms / TPC Invested Grant Project Authority Type Equity Debt 30th Jun. '26 Stake Stretch Partners Lanes (Rs. Crs) Amount (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) 107.68 / Gwalior Bhind ** 100% MPRDC MP / NH-92 Toll - 3

  23. Slide 23: HAM Projects

    HAM Projects Invested Debt / Bond as % TPC Total Debt Project Authority State / Stretch Kms / Lanes Status Equity on 30th Jun’26 Stake (Rs. Crs) (Rs. Crs) (Rs. Crs) (Rs. Crs) Gaju Village- Devinagar (Pkg-1C) 100% NHAI UP/ NH-530B 33.0 / 4 COD 819 85 386 359 Kanpur-Lucknow (Pkg II) 100% NHAI UP / NH-

  24. Slide 24: Landmark Projects

    Landmark Projects Prayagraj-Kaushambi Project Hardoi Project Mathura Gaju Village Project Canal Project – AP Kurnool Pune Ring Road Project Haryana Rail Project 24

  25. Slide 25: Company Overview

    Company Overview BE 25

  26. Slide 26: PNC Infratech – At a Glance

    PNC Infratech – At a Glance 25+ Years of Experience, Innovation Geographical Footprint Proven Execution Capabilities and Excellence Executed projects across 16 states with Executed over 98 major infrastructure projects Promoter-Led Vision Backed by a Professional across segments and currently execut

  27. Slide 27: Journey

    Journey • Secured 3 EPC rural water supply projects for • Received PCOD for 3 HAM Projects • Executed its 1st independent highway • Got listing on the Stock 2,337 villages in UP project with NHAI, the four-laning of Exchanges • Received Completion Certificate for the Agra-Gwalior section of NH3 in U

  28. Slide 28: Business Overview

    Business Overview Roads & Highways EPC Coal Mining Completed 74 infrastructure road projects on EPC basis OB Removal and Coal Extraction Project Roads & Highways BOT / OMT/ HAM The Company has completed 74 Projects and has 3 operating BOT projects, comprising both toll & annuity assets; and a total

  29. Slide 29: Corporate Structure

    Corporate Structure PNC Infra Holdings Limited (“PNCIHL”) (PNC Infratech owning 100% Stake) PNC Renewable Energy Private Joint Ventures Limited (“PNCREPL”) (PNC Infratech owning 100% Stake) MP Highways Private Limited (“MPHPL”) 100% PNC-SPSCPL (Koilwar to Bhojpur) 55% PNC Delhi Industrial Infra Priv

  30. Slide 30: Board of Directors

    Board of Directors Mr. Pradeep Kumar Jain : Chairman & Managing Director With over 47 years of experience, Mr. Pradeep is a veteran in infrastructure construction, operations, and management. He provides strategic leadership in administration, stakeholder relationships, and corporate governance, gui

  31. Slide 31: Board of Directors

    Board of Directors Mr. Krishan Kumar Jalan (IAS): Independent Director Mr. Jalan, a former Secretary to the Government of India, brings over 35 years of experience in the Indian Administrative Service (IAS). His expertise in governance and administration strengthens the Company’s decision-making and

  32. Slide 32: Clientele

    Clientele > WRITES THE INFRASTRUCTURE PEOPLE om é 1B/S/R/ Dic] Uttar Pradesh DS I I DC @® State Water & Sanitation Mission 2 s < NAMAMI GANGE AND RURAL WATER SUPPLY DEPARTMENT Power Corporation Limited Delhi State Industrial and Infrastructure Development ‘Government of Uttar Pradesh Corporation Lid

  33. Slide 33: Geographical Presence

    Geographical Presence 16 States Execution and Operational Presence 95+ Major Infrastructure Projects Delivered 3 Operational BOT Projects Comprising Toll and Annuity Assets 14 HAM Projects across Nation in Different States under Operation / Implementation Disclaimer: This map is a generalized illust

  34. Slide 34: Execution Capabilities

    Execution Capabilities Man & Machine added to execute more projects • Strengthening of In-house execution team with induction of engineers with strong technical knowledge • Investments in Machinery over the years to augment and upgrade the execution capabilities Strong Credit Rating • Long term bank

  35. Slide 35: Strong Credit Rating

    Strong Credit Rating Upgraded Reaffirmed Assigned ◼ PNC Infratech Ltd. Varanasi Kolkata Highway Package 6 Private Limited ◼ Prayagraj Kaushambi Highway Package 3 Pvt. ◼ Ltd. ✓ Long term bank facilities at CARE AA+; Stable ✓ Long term bank facilities at CARE A; Stable (Single (Double A plus; Outlook:

  36. Slide 36: Enhanced to Augment and upgrade the execution

    Enhanced to Augment and upgrade the execution Rs. Crs 1,698 1,609 1,317 1,341 1,330 FY23 FY24 FY25 FY26 Jun-26 Present Capex will enable us to achieve a Turnover of Rs. 8,000-10,000 Crs 36

  37. Slide 37: Integrated Business Model

    Integrated Business Model In-house Design & Engineering In-house Construction ◼ Controls the entire process from conceptualization to ◼ Ensuring timely completion of projects, reducing reliance on commissioning of a given project which helps in providing third parties and lowering costs. customized

  38. Slide 38: Growth Strategies

    Growth Strategies Diversification Strong Relationship Focused Approach Competitiveness • Leveraging Strong Project • Improve performance and • Maintaining Strategic • Continue to focus on our Execution track record to competitiveness of existing Alliances with companies Core EPC Strength & diversify

  39. Slide 39: THANK YOU

    PNC Infratech Limited THANK YOU Company: PNC Infratech Ltd Investor Relations: Strategic Growth Advisors (SGA) CIN: L45201DL1999PLC195937 CIN: U74140MH2010PTC204285 Mr. Pankaj Agarwal - Vice President (F&A) Mr. Jigar Kavaiya - COO – IR Practice jigar.kavaiya@sgapl.net pankajca@pncinfratech.com +91 9