DOST STEELS LIMITED Corporate Briefing Session For Financial year Ended on 30 June 2022 1
Slide 2: Table of Contents
Table of Contents 1.Company Overview 2.Vision 3.Mission 4.Values 5.Market overview 6.Who we are 7.Brief Operational History 8.Financial Performance 2022 9.Current Situation 10.Future Hope 2
Slide 3: Company Overview
Company Overview Company Name -Dost Steels Limited CEO – Jamal Iftakhar Head Office - 4th Floor, Ibrahim Trade Centre, 1-Aibak Block, Barkat Market, New Garden Town, Lahore,54700, Pakistan Contact - +9242 35941375-77 Date of Incorporation – March 19, 2004 Lines of Business - Steel Rebars Manufacturi
Slide 4: Vision
Vision To become the leading quality steel products supplier for Pakistan. 4
Slide 5: Mission
Mission To be an agent of change by providing innovative solutions. DSL will lead the market and raise the bar for quality standards prevailing in the country. It will offer re-bar which gives true and lasting value to our customers. 5
Slide 6: Values
Values Integrity Excellence Respect Togetherness Responsibility 6
Slide 7: Pakistan Steel Market
Pakistan Steel Market • As of today due to current economic situations the steel sector is under slump and there is no significant demand in the market. As a result, steel sector sees 40% decline. The weaker demand also put pressure on the pricing power of steel market. • Major causes for this decli
Slide 8: Who we are
Who we are “Dost Steels has a competitive advantage in terms of quality and marketing strategy” First Automatic Greenfield Project Only single location over 350,000 tons production capacity per year DSL will be a trusted supplier of rebar aiming for highest levels of certifications 8
Slide 9: Re-Bar Process
a-leosr Ine & Te =) Re-Bar Process
Slide 10: Dost Steels – Setting a milestone
Dost Steels – Setting a milestone • Dost Steels is proud of being Pakistan’s first global standard compliant steel rebar manufacturing plant with an annual capacity of 350,000 Metric Tons. • Dost Steels Ltd is the first fully automatic, green field steel rolling bar mill in Pakistan capable of makin
Slide 11: Geographical existence
Geographical existence • Dost Steels mid-Country location is geographically enabled to supply all types of customers on competitive advantages. The project is located at 52-KM Multan Road (Phoolnagar Bypass) District Kasur which is 40-KM away from Lahore, which itself is an epicenter of Punjab’s ind
Slide 12: Our Products
Our Products The plant processes 130 mm2 and 150 mm2 steel billets in 6 m and 12 m sizes as raw material. The finished product is quenched steel deformed bars (rebar) ranging from 8mm to 40mm in finished bundles of 2-3 tons in 6 meters to 16 meters in length. DSL will manufacture the following w
Slide 13: Industrial Competitive Edge
Industrial Competitive Edge Straight line bar mill comprising of 18 horizontal and vertical rolling stands Automated production line with magnetic crane logistics handling 60 tons per hour pusher type furnace Completely automated bundling and binding station Interconnection of all equipment and
Slide 14: Health & Safety Environment
Health & Safety Environment • Dost Steels Ltd houses its own water treatment plant which recycles the entire water being used for all stages of manufacturing. This plays a big role in saving our environment and ensures waste particles such as iron oxide and oil sludge do not mix into our precious su
Slide 15: Socially Responsible and Healthy Working Environment
Socially Responsible and Healthy Working Environment DSL will contribute towards society by coming up with projects which will help the community to embrace their deserved living standards. Our Health, Safety and Environment (HSE) policy ensures that DSL remains one step ahead of meeting the needs o
Slide 16: Brief Operational History
Brief Operational History • Company has started its commercial production in February 2018 but unfortunately stopped its production unit in December 2018, due to lack of sufficient working capital funds. Thereafter management is in continuing effort for arrangement of suitable new investor to restar
Slide 17: Financial Results 30 June 2022
Financial Results 30 June 2022 Financial performance of the Company for the year ended June 30th, 2022, along-with comparative figures was as under: Description 30 June 2022 30 June 2021 (PKR) (PKR) Sale Nill 7,053,960 Cost of Sales (38,478,275) (61,375,236) Gross (Loss) / Profit (38,478,275) (54,32
Slide 18: Current situation
Current situation • After lot of efforts over many years and dialogues with different Investors, management has finally found a serious investor group for investment of PKR 524 million against issuance of 29% fresh share (Other than right). In this regard company has sought approval of shareholders
Slide 19: Disconnection of 132KV LESCO grid connection due to financial problems
Disconnection of 132KV LESCO grid connection due to financial problems: • As faced by the entire country, due to the current economic situation, the sponsors of the company also faced financial constraints and have already exhausted their means to finance the losses of the company and it is not prac
Slide 20: Future Hope
Future Hope • The current depressed economic situation, in the backdrop of no foreign exchange being made available by the State Bank of Pakistan has made it very difficult for import based Pakistan Steel sector to come out of its impasse. • The current management is making all out efforts to come o