Slide 1: Agency Consultation Meeting
Agency Consultation Meeting Oakdale West Estate May 2022 1
Slide 2: Overview
Overview Welcome and Introductions Upcoming Developments Project Update – OWE Project Update – Buildings Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Kiera Plumridge Carl Vincent Caitlin D’Arcy Kate McKinnon Alasdair Cameron Lachlan O’Reilly Luke Ridley 3
Slide 4: Oakdale West Estate site plan and area schedule
+ REFER TO DRAWING OAK MPO3 FOR CONTINUATION oodmar ‘OAKDALE SOUTH Emme neasentn Lot 12 0P1178389 Katie Oo ‘rage Re 5600 Enpraus Cate Keay RE 8400 Oakdale West Estate - MOD 9 PASSES E thc [ ptt To P.0003 ) Site Area Schedule Total She Area 154.12 ha Les ‘Non Devote Land 2108 he Ensemerss| 2238 he Fe
Slide 5: Progress to Date & Upcoming Works – Building 1A
Progress to Date & Upcoming Works – Building 1A • Site commencement 8th of July 2020 • Concrete pours to internal warehouse complete • Concrete pours to external hardstands progressing • Ancillary buildings nearing completion • First handover to the customer occurring this period. 5
Slide 6: Progress to Date & Upcoming Works – Building 1B/1C
Progress to Date & Upcoming Works – Building 1B/1C • Site commencement 20th of August 2021 • Concrete pours to external hardstands and carparks progressing • Commencement of external landscaping • Ancillary office fit-out progressing. 6
Slide 7: Progress to Date & Upcoming Works – Building 2A
Progress to Date & Upcoming Works – Building 2A • Site commencement 5th of January 2022 • Warehouse structural steel installation complete • Roofing installation progressing • External warehouse cladding progressing • Internal concrete pours occurring. 7
Slide 8: Progress To Date & Upcoming Works – Building 3A
Progress To Date & Upcoming Works – Building 3A • Site commencement 23rd August 2021 • Installation of site sediment control measures • Warehouse fit out • External hardstand preparation and installation. • Main office construction & fit out • Commissioning of services • Landscaping • Carpark & fina
Slide 9: Progress To Date & Upcoming Works – Building 3B
Progress To Date & Upcoming Works – Building 3B • Site commencement 15th December 2021 • Warehouse roofing & cladding • External bulk earthworks & hardstand preparation • Internal warehouse slab preparation & pours • Office structural steel erection. 9
Slide 10: Progress to Date & Upcoming Works – Building 4E
Progress to Date & Upcoming Works – Building 4E • Site commencement 13th of November 2021 • Warehouse structural steel installation complete • Roofing installation progressing • Precast panel installation progressing. 10
Slide 11: Upcoming Works – Building 3C
Upcoming Works – Building 3C 11
Slide 12: Upcoming Works – Building 5A & 5B
Upcoming Works – Building 5A & 5B 12
Slide 13: Progress To Date & Upcoming Works - OWIE
Progress To Date & Upcoming Works - OWIE • Road 8 service installation and road construction works completed and dedication process to council is being finalised • Precinct 3 & 4 bulk earthworks and retaining walls are nearing completion • Lot 4A right of way construction has commenced and scheduled
Slide 14: ER Inspections and Audits: SSD7348 (Infrastructure, 1A & 1BC)
ER INSPECTIONS AND AUDITS: SSD7348 (INFRASTRUCTURE, 1A & 1BC ) ER INSPECTIONS 2019 TOTAL 3 2020 QTR1-4 TOTAL 42 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – JUN) 11 2021 QTR 7 (JULY – SEP) 12 2021 QTR 8 (OCT - DEC) 15 2022 QTR 9 (JAN-MAR Part) 13 2022 QTR 10 (APR-MAY Part) 5 TOTAL TO DATE 107 Copyright
Slide 15: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD NIL Copyright © ErSed 2011
Slide 16: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES OR INCIDENTS NIL Copyright © ErSed 2011
Slide 17: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 COMPLAINTS NIL Copyright © ErSed 2011
Slide 18: Environmental Performance - On Lots
ENVIRONMENTAL PERFORMANCE- ON LOTS INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTHLY REPORTS OTHER LOTS INSPECTIONS GENERALLY MONTHLY (2022- Current) 1A 4 LOT 1BC 4 LOT 2A 5 LOT 3AB 3 LOT 4E 4 INCIDENTS AND NON COMPLIANCES 18 MAY 2022 LOT 2A NEAR MISS SAFETY INCIDENT IMPACT OF SCISSOR LIFT WITH ME
Slide 19: Safety
Safety • There was one incident that occurred on the Lot 2A project that has been reported through the Incident Reporting Requirements in the Conditions of Consent. • The incident involved a formwork collapse. • No workers were injured due to exclusion zones that had been implemented. 21
Slide 20: Consultation and Community Interactions
Consultation and Community Interactions • There have been no consultation occurrences to report since the last meeting. 22
Slide 21: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: The Hayesbery 1-11 Hayes Road Rosebery, NSW, 2018 • Community Meetings: Subject to scheduling • E
Slide 22: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 24