  1. Slide 1: Essar Oil Limited Analyst Presentation

    Slide 1: Essar Oil Limited Analyst Presentation

    Essar Oil Limited Analyst Presentation May, 2012

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer This Document and any information made available orally or in writing at any presentation or delivery of this Document (together the “Materials”) do not constitute or form part of and should not be construed as, any offer or invitation to sell or issue, or any solicitation of any offer to

  3. Slide 3: Essar Oil

    Slide 3: Essar Oil

    Essar Oil Refining • World Scale, highly complex, 375000 bpd Refinery at Vadinar • Strategic Location with access to domestic & International markets Exploration & Production • High impact E&P platform • Leading Indian CBM Portfolio with 10 tcf + reserves & resources across 5 CBM blocks Retail Marke

  4. Slide 4: Agenda of Presentation

    Slide 4: Agenda of Presentation

    Agenda of Presentation Industry Overview Performance Highlights Refinery Business Exploration & Production Financials Key Issues 3

  5. Slide 5: Industry Overview & Market Outlook

    Slide 5: Industry Overview & Market Outlook

    Industry Overview & Market Outlook 4

  6. Slide 6: Crude Market Dynamics

    Slide 6: Crude Market Dynamics

    Crude Market Dynamics 125 USD/bbl WTI - Brent differential remained 123 WTI Brent Dubai 120 120 114 122 wide, however, it is expected to shrink after 115 116 114 117 113 111 110 111 116 109 reversal of cushing pipeline. 110 108 108 110 110 105 106 110 109 105 108 106 Difference between Dubai & Brent

  7. Slide 7: Product Cracks

    Slide 7: Product Cracks

    Product Cracks USD/bbl $25 Gasoil FO Jet Gasoline 20.33 20.36 20.02 20.92 20.89 21.28 18.75 18.64 18.62 $20 18.23 17.64 18.14 19.43 15.56 19.13 18.40 18.57 19.34 19.48 17.60 16.89 17.74 17.71 $15 17.81 17.34 16.26 14.64 $10 11.66 11.76 10.48 7.57 9.26 6.89 5.96 6.27 6.76 7.60 7.96 $5 6.86 $0 2.84 3.

  8. Slide 8: Performance Highlights

    Slide 8: Performance Highlights

    d ESSAR’ OIL & GAS Performance Highlights

  9. Slide 9: Performance Highlights

    Slide 9: Performance Highlights

    , Performance Highlights 1 Refinery capacity increased to 18 mmpta and complexity to 11.8 2 Operations of all new refinery expansion units stabilized 3 Optimization Project to increase capacity to 20 mmtpa on track, 90% completed Revenue & EBIDTA at Rs 63340 crore & 2106 crore respectively for FY12

  10. Slide 10: Refinery Business

    Slide 10: Refinery Business

    d ESSAR’ OIL & GAS Refinery Business

  11. Slide 11: Vadinar Refinery set to deliver significant value

    Slide 11: Vadinar Refinery set to deliver significant value

    Vadinar Refinery set to deliver significant value Vadinar Refinery becomes second largest single location 16 Indian Refineries refinery in India 14 11.8 One of the most complex refinery in Indian & global 12 market. Complexity 10 Refinery Capacity increased to 375,000 bpd & expanding to 405,000 bpd

  12. Slide 12: Refinery Expansion Project: Highlights

    Slide 12: Refinery Expansion Project: Highlights

    Refinery Expansion Project : Highlights Million Tones Vadinar Optimization Vadinar Phase - I Vadinar Refinery Rs in Crore Debottlenecking 405 400 375 30 350 27% 75 75 300 300 250 80 80 80 200 150 100 220 220 220 220 50 0 2010 2011 2012 Sept, 2012 Capacity & Complexity of Refinery almost doubled from

  13. Slide 13: Value driven by scale and complexity

    Slide 13: Value driven by scale and complexity

    Value driven by scale and complexity Higher complexity enables processing of ultra Crude Mix ~ 18 mmtpa heavy & toughest crudes (Average API ~ 24/25) 19% Continuous optimization of crude diet ; 70-80 60% 21% type of crudes processed in last 4 years. Substantial qty. of Ultra Heavy crudes tied up fro

  14. Slide 14: Significant Gross Refining Margin uplift

    Slide 14: Significant Gross Refining Margin uplift

    Significant Gross Refining Margin uplift US$/bbl Increased complexity to increase margins to Indian Complex Refinery IEA Singapore Margin 16.00 15.00 Average premium: US$ 8.76/bbl ~ US$ 7/ bbl above IEA Singapore benchmark 14.00 11.60 12.00 12.20 10.30 10.00 9.10 8.40 US$ 11.44/bbl FY12-13 throughpu

  15. Slide 15: Refinery Operations

    Slide 15: Refinery Operations

    Refinery Operations Throughput 13.49 million tonnes for year ended March – Million Tones 2012, impacted due to planned shutdown of 14 1.40 14.76 refinery for 35 days. 12 13.49 10 Processed 4.03 million tonnes of crude during 8 6 the quarter ended March-12, higher 4 throughput indicating enhancement

  16. Slide 16: Refinery Operations

    Slide 16: Refinery Operations

    Refinery Operations Product Mix Optimization production of middle & light Light Middle Heavy 100% distillates along with attractive margin Fuel Oil. 29% 29% 28% 27% 80% Heavy Distillates include positive margin 60% 43% 45% 42% superior performance VG grade bitumen (VG 40% 46% 30), produce by process

  17. Slide 17: Safe, Reliable & Sustainable operations

    Slide 17: Safe, Reliable & Sustainable operations

    Safe, Reliable & Sustainable operations LTI free Man - days 1460 LTI free Man-hours 11.30 million Major fire free days 1045 High focus on operational & process safety with regular audits & benchmarking exercises to ensure world class safety processes One of the Lowest Fuel & Loss in the Industry. In

  18. Slide 18: Exploration & Production

    Slide 18: Exploration & Production

    d ESSAR’ OIL & GAS Exploration & Production 17

  19. Slide 19: E&P Asset Portfolio

    Slide 19: E&P Asset Portfolio

    E&P Asset Portfolio Rajmahal Mehsana • 100% interest in CBM block • 70% interest (ESU) • Best estimate • 2P reserves: 2mmbbl prospective (oil) resources: 4.7tcf • Potentially significant CBM gas CBM play (787mmboe) • CPR by ARI (2010) Other Assets • Assam (100% interest): Unrisked/undiscovered in- p

  20. Slide 20: Exploration and Production

    Slide 20: Exploration and Production

    Exploration and Production Reserves and Resources (mmboe) Leading CBM gas player in India 2P/2C Prospective In place CBM Acreage Place Certified 2 resources Resources Unrisked 2,500 Blocks (km ) Gas (bcf) (bcf) Resource (bcf) 971 2109 40 NSAI, 2,000 176 Raniganj West Bengal 500 558 297 Jan12 1,500 9

  21. Slide 21: Raniganj Project Status

    Slide 21: Raniganj Project Status

    Project Progress at Raniganj Raniganj Project Status Reserve 1P Pilot well drilling completed & applied for moving Reserve 2P Reserve 3P Contingent Reserve 1P to Phase-III (Development Phase) Reserve 2P Drilled 73 wells, producing ~25,000 scmd from 15 Reserve 3P to 20 wells, supply of Gas to end cus

  22. Slide 22: Financials

    Slide 22: Financials

    d ESSAR’ OIL & GAS Financials 21

  23. Slide 23: Refinery & Marketing Financial Performance

    Slide 23: Refinery & Marketing Financial Performance

    Refinery & Marketing Financial Performance Rs in Crore 22

  24. Slide 24: Balance Sheet - Highlights

    Slide 24: Balance Sheet - Highlights

    Balance Sheet - Highlights Rs in Crore FCCBs of US$ 262 million (Rs 1340 crore for FY12 and Rs. 1171 crore for FY11) is forming part of Net worth for financial year ended march, 2012, being made compulsorily convertible. 23

  25. Slide 25: Thanks

    Slide 25: Thanks

    d ESSAR’ OIL & GAS Tanks

  26. Slide 26: CDR Exit

    Slide 26: CDR Exit

    CDR Exit Lenders Monitoring Committee “LMC” in its meeting held on 20/01/2012 recommended the Company’s CDR exit proposal to CDR – EG. The revised CDR Exit proposal, as recommended by LMC, discussed at CDR-EG in its meeting held on 3/02/2012 CDR Exit Proposal of Company has been approved by majority

  27. Slide 27: Sales Tax Matter

    Slide 27: Sales Tax Matter

    Sales Tax Matter Current Status The Company has reversed Rs 3962 crore in its Profit & Loss account pursuant to order of Hon’be Supreme Court on 17th January, 2012. As back up plan, Company has approached to lenders to provide bridge loan of Rs 5000 crore to settle Sales Tax Liability. The Company h

  28. Slide 28: Vadinar Funding & Liquidity

    Slide 28: Vadinar Funding & Liquidity

    Vadinar Funding & Liquidity Project risk & capex cycle for refinery business coming to an end. Net debt US$ 2. 6 bn at end March 2012 Options to refinance Rupee debt with US Dollar debt to reduce interest costs – natural hedge to US dollar. Free Cash Flow to be used to deleverage the balance sheet N