Slide 1: Boral Peppertree Quarry
Build something great™ BORAL PEPPERTREE QUARRY 17th June 2020 > Community Consultative Committee (CCC) Peppertree Quarry 1 meeting Marulan
Slide 2: Agenda
Agenda ˃ 1. Welcome and introductions ˃ 2. Confirmation of minutes and actions ˃ 3. Business arising ˃ 4. Correspondence ˃ 5. Operations over the last 3 months ˃ 6. Environmental performance ˃ a. Incidents ˃ b. Complaints ˃ c. Air ˃ d. Noise ˃ e. Blast ˃ f. Water – surface and ground ˃ g. Heritage ˃
Slide 3: Welcome, Minutes and Business Arising
Agenda item 1 – Welcome & Apologies Agenda item 2 – Confirmation of Minutes Agenda item 3 – Business Arising ˃ Update on real time noise monitoring system at the next meeting 3
Slide 4: Correspondence
Agenda item 4 - Correspondence ˃ Department of Planning and Environment ˃ Management plan updates and reviews ˃ Modification 6 approval April 3rd 2020 ˃ EPA ˃ Nil ˃ Resource Regulator ˃ Notice – intent to prosecute ˃ BCT ˃ Site visit to Coolumburra ˃ Aerial baiting approval for Coolumburra ˃ Souther
Slide 5: Operations
Build something great™ BORAL PEPPERTREE QUARRY 5 > Operations
Slide 6: Operations over the last 3 months
˃ Agenda item 5 - Operations over the last 3 months ˃ Safety ˃ Zero LTI’s since the last meeting ˃ Audit by Mines Regulator on COVID 19 Management ˃ Overburden ˃ Management plans being prepared for approval ˃ Design of emplacement and sediment controls progressed ˃ Discussion on road ownership and c
Slide 7: Environmental Performance
Build something great™ BORAL PEPPERTREE QUARRY 7 > Environmental Performance
Slide 8: Incidents March, April, May
Agenda item 6 Environmental Performance a. Incidents March, April, May Incidents 2017 - May 2020 8 7 6 5 4 3 2 1 0 ˃ March (nil) April (nil ) May (1 – fuel spill in bunded area) 8
Slide 9: Complaints March, April, May
Agenda item 6 Environmental Performance b. Complaints March, April, May Complaints 2017 to May 2020 2.5 2 1.5 1 0.5 0 Jan-2019 Jan-2017 Jul-2017 Sep-2017 Jan-2018 Jul-2018 Sep-2018 Jul-2019 Sep-2019 Jan-2020 Nov-2017 Nov-2018 Nov-2019 May-2017 May-2018 May-2019 May-2020 Mar-2017 Mar-2018 Mar-2019 Ma
Slide 10: Air: Deposited Dust (onsite NW boundary)
Agenda item 6 Environmental Performance c. Air Peppertree Quarry Deposited Dust 2017 - 2020 Onsite (NW boundary) 30 25 g/m2/month 20 15 10 5 0 rolling Annual… Nov-2017 Sep-2017 Sep-2018 Nov-2018 Sep-2019 Nov-2019 Jan-2020 Jan-2017 Jan-2018 Jan-2019 Mar-2017 May-2017 Jul-2017 Mar-2018 May-2018 Jul-20
Slide 11: Air: Deposited Dust (683 Marulan South Road)
In compliance g/m2/month 10.00 0.00 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 Jan-2017 Feb-2017 Mar-2017 Apr-2017 May-2017 Jun-2017 Jul-2017 c. Air Aug-2017 Sep-2017 Oct-2017 Annual Average goal of 4gm2/month Nov-2017 Dec-2017 Annual average below goal at the boundary Jan-2018 Feb-2018 Mar-2018 A
Slide 12: Air: Deposited Dust (432 Long Point Road, Tallong)
In compliance g/m2/month 10 12 14 16 18 20 0 2 4 6 8 Jan-2017 Feb-2017 Mar-2017 Apr-2017 May-2017 Jun-2017 Jul-2017 Aug-2017 c. Air Sep-2017 Ash Solids Oct-2017 Insoluble Annual Average goal of 4gm2/month Nov-2017 Dec-2017 Jan-2018 Annual average below goal at the boundary Feb-2018 Insoluble Solids
Slide 13: Air: PM10 Annual Average Trend
ug/m3 10.00 15.00 20.00 25.00 30.00 35.00 0.00 5.00 In compliance 6/01/2019 18/01/2019 5/02/2019 13/02/2019 1/03/2019 19/03/2019 6/04/2019 24/04/2019 c. Air 12/05/2019 Annual Average goal of 4gm2/month 30/05/2019 17/06/2019 Annual average below goal at the boundary 5/07/2019 23/07/2019 running annua
Slide 14: Air: PM10 24 Hour Performance
ug/m3 50 0 100 150 200 250 300 350 6/01/2019 15/01/2019 24/01/2019 5/02/2019 In compliance 11/02/2019 17/02/2019 1/03/2019 13/03/2019 25/03/2019 6/04/2019 18/04/2019 30/04/2019 12/05/2019 c. Air 24/05/2019 Annual Average goal of 4gm2/month 5/06/2019 17/06/2019 29/06/2019 Annual average below goal at
Slide 15: Air: TSP Annual Average Trend
In compliance 100.00 200.00 300.00 400.00 500.00 600.00 0.00 4/1/17 9/02/2017 17/03/2017 22/04/2017 28/05/2017 3/07/2017 8/08/2017 13/09/2017 c. Air 19/10/2017 24/11/2017 Annual Average goal of 4gm2/month 30/12/2017 4/02/2018 Annual average below goal at the boundary 12/03/2018 running annual averag
Slide 16: Noise: March (day)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring - March (day) Compliance Assessment (Leq, 15 minute in dBA) NPI, 2017 Comparison Annoying Comply Operational to Criteria (Quarry) Noise Receptor ID Description Date Quarry Noise with Noise Noise Impact (Δ Quarry Characteristic L
Slide 17: Noise: March (evening / night)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring March (evening / Night) Compliance Assessment (Leq, 15 minute in dBA) NPI, 2017 Annoying Comparison Comply (Quarry) Operational Quarry Noise to Criteria with Noise Noise Receptor ID Description Date Noise Impact Level (Δ Quarry
Slide 18: Noise: March (night 1 min)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring – March (night 1 min) Compliance Assessment (L1, 1 minute in dBA) NPI, 2017 Annoyin Comply Operational Comparison g Noise Quarry Noise with Noise Receptor ID Description Date Noise Impact to Criteria (Δ Quarry Criteria? Characte
Slide 19: Noise: April (day)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring – April (day) Compliance Assessment (Leq, 15 minute in dBA) NPI, 2017 Annoying Comparison Comply (Quarry) Operational Receptor ID Description Date Quarry Noise to Criteria with Noise Noise Noise Impact Level (Δ Quarry Criteria?
Slide 20: Noise: April (evening / night)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring April (evening / Night) Compliance Assessment (Leq, 15 minute in dBA) NPI, 2017 Annoying Comparison Comply (Quarry) Operational Receptor ID Description Date Quarry Noise to Criteria with Noise Noise Noise Impact Level (Δ Quarry
Slide 21: Noise: April (night 1 min)
Agenda item 6 Environmental Performance d. Noise – quarterly monitoring – April (night 1 min) Compliance Assessment (L1, 1 minute in dBA) NPI, 2017 Annoying Comply Noise Operational with Noise Receptor ID Description Date Quarry Noise Comparison Characteri Noise Impact Criteria? Level to Criteria (Δ
Slide 22: Blasts: Over Pressure Trend 2020
dB (lin peak) 20 40 60 80 0 100 120 140 14/01/2020 criteria 115 ˃ In compliance 20/01/2020 23/01/2020 30/01/2020 6/02/2020 11/02/2020 13/02/2020 north west boundary 20/02/2020 27/02/2020 e. Blasts 03/05/2020 03/12/2020 19/3/2020 26/3/2020 04/02/2020 north east boundary 04/06/2020 04/09/2020 17/4/202
Slide 23: Blasts: Ground Vibration Trend 2020
Agenda item 6 Environmental Performance e. Blast Blast Trend Ground vibration 2020 6 5 mm/sec 4 3 2 1 0 north west boundary north east boundary 683 Marulan sth rd residence criteria 5 ˃ In Compliance 23
Slide 24: Water - surface
Agenda item 6 Environmental Performance f. Water - surface Quarterly monitoring round undertaken in February 2020 (storm event) and May 2020. Next sample round quarter of July – August - September 2020 24
Slide 25: Water samples pH 2012 to 2020
pH 0 1 3 4 5 6 7 8 9 10 2 1.3.2012 6/06/2012 4/09/2012 11/12/2012 T1 5/04/2013 (March sample) 5/06/2013 25/09/2013 5/12/2013 dam 4/03/2014 26/06/2014 1/10/2014 18/12/2014 23/03/2015 24/06/2015 26/08/2015 (sept sample) 6/1/2016 (dec 2015 sample) 16/03/2016 lower criteria (6.5) 6/06/2016 5/09/2016 14/
Slide 26: Water samples turbidity
Agenda item 6 Environmental Performance f. Water - surface Peppertree water samples - Turbidity 2012 - 2020 300 250 200 150 NTU 100 50 0 T1 Main dam ANZECC guideline U1 MSth creek ˃ Below guideline for February and May samples 26
Slide 27: Water samples total dissolved solids
Agenda item 6 Environmental Performance f. Water - surface Peppertree water samples - Total Dissolved Solids 2012 - 2020 1400 1200 1000 800 mg/l 600 400 Aust Drinking water guidelines - 200 aesthetic value 500 mg/l 0 date T1 DAM ADWG aesthetic marulan sth creek U1 27
Slide 28: Water samples total phosphorus
Agenda item 6 Environmental Performance f. Water - surface Peppertree Quarry Total Phosphorus (mg/l) 2012 - 2020 0.6 0.5 0.4 mg/l 0.3 0.2 0.1 0 T1 dam marulan sth creek trigger U1 ˃ Below guideline for May samples at T1 and the dam. All above guideline for February28 sample
Slide 29: Water samples total nitrogen
Agenda item 6 Environmental Performance f. Water - surface Peppertree Quarry Total Nitrogen (mg/l) 2012 to 2020 12 10 8 mg/l 6 4 2 0 T1 dam marulan sth creek trigger U1 ˃ Below guideline for May samples at T1. All above guideline for February sample 29
Slide 30: Water - environmental flow
Agenda item 6 Environmental Performance f. Water – environmental flow year total in flow 10% total out flow in compliance Jan-2019 0 0 1.43 yes Feb-2019 0 0 1.89 yes Mar-2019 0 0 3.47 yes Apr-2019 0 0 2.51 yes May-2019 0 0 2.44 yes Jun-2019 0 0 2.17 yes Jul-2019 0 0 1.91 yes Aug-2019 0 0 1.75 yes Se
Slide 31: Groundwater
Agenda item 6 Environmental Performance f. Groundwater ˃ Monitoring conducted in March 2020 31
Slide 32: Groundwater
Agenda item 6 Environmental Performance f. Groundwater ˃ Monitoring conducted in March 2020 ˃ Analytical results are similar to previous monitoring rounds. ˃ Nitrogen species were generally increased across the dataset ˃ Regional Groundwater flow is largely around the granodiorite intrusion ˃ Within
Slide 33: Groundwater
Agenda item 6 Environmental Performance f. Groundwater 33
Slide 34: Heritage
Agenda item 6 Environmental Performance g. Heritage ˃ Collation of Artefacts has commenced 34
Slide 35: Ecology
Agenda item 6 Environmental Performance h. Ecology ˃ No new plantings being undertaken due to weather conditions ˃ Maintenance is being carried out and infill planting occurring where required. ˃ Feral animal management has continued ˃ Feral dog and pigs have been captured on camera. Plans being dev
Slide 36: Stakeholder Engagement
Build something great™ BORAL PEPPERTREE QUARRY 36 > Stakeholder Engagement
Slide 37: Stakeholder Engagement
Agenda item 6i – Stakeholder Engagement ˃ Tallong Community Park ˃ Donation of material ˃ Outward Bound ˃ Cancelled due to COVID ˃ CVA program ˃ Cancelled due to COVID ˃ Marulan Kite Festival ˃ Decision on the festival is pending due to COVID ˃ STEM ˃ 2 staff members are partners with the CSIRO STEM
Slide 38: Forward Plans
Build something great™ BORAL PEPPERTREE QUARRY 38 > Forward Plans
Slide 39: Operations next 3 months
Agenda item 7 – Operations next 3 months 39
Slide 40: General Business
Build something great™ BORAL PEPPERTREE QUARRY 40 > General Business
Slide 41: General Business
Agenda item 8 – General Business ˃ Marulan South State Significant Development ˃ Still with DPIE for assessment ˃ Real Time noise monitoring 41
Slide 42: General Business
Agenda item 8 – General Business 42
Slide 43: General Business
Agenda item 8 – General Business ˃ Other ˃ Next meeting September 2020 43
Slide 44: Thank you for your attendance
Build something great™ BORAL PEPPERTREE QUARRY 44 > Thank you for your attendance.