Mitsubishi Heavy Industries, Ltd. · TSE:7011

Mitsubishi Heavy Industries — International Workshop on Power Generation with Carbon Capture and Storage in India 2008

20 slides from Mitsubishi Heavy Industries's conference presentation, Jan 23, 2008

  1. Slide 1: MHI's Commercial Post Combustion CO2 Capture: Experiences in a Carbon Constrained World

    MHI's Commercial Post Combustion CO2 Capture Experiences in a Carbon Constrained World Ronald Mitchell Mitsubishi Heavy Industries, Ltd. International Workshop on Power Generation with Carbon Capture and Storage in India 22-23 January 2008, Ashok Hotel, Delhi, India 1

  2. Slide 2: Contents

    CONTENTS 1. Introduction & Concept of Post Combustion CO2 Capture 2. MHI’s CO2 Capture Experience 3. MHI’s Flue Gas CO2 Recovery Technology 4. CO2 Recovery from Coal-fired Boilers 5. MHI’s scope in a CCS Project 6. Path Forward - Government incentives for CCS 2

  3. Slide 3: 1. Introduction

    1. Introduction ‹ Coal will persist as a dominant fuel for power generation well into this century ‹ MHI has commercialized an advanced post combustion CO2 capture technology process ‹ MHI has an expanding list of commercial deliveries mainly in the fertilizer production industry ‹ MHI has conducted

  4. Slide 4: Concept of Flue Gas CO2 Recovery, Sequestration and EOR

    1. Concept of Post Combustion CO2 Capture Concept of Flue Gas CO2 Recovery, Sequestration and EOR Fertilizer Production in India Source: IPCC 4

  5. Slide 5: Advantages of Post Combustion CO2 Capture

    1. Concept of Post Combustion CO2 Capture Advantages of Post Combustion CO2 Capture ① Is applicable for the current, global PC fleet ② Offers high degree of flexibility – is adaptable and cost competitive with other technologies ③ Operation at atmospheric pressure – safe and does not require exotic

  6. Slide 6: MHI's Commercial CO2 Capture Plants

    2. MHI’s Experience MHI’s Commercial CO2 Capture Plants Malaysia Japan India Petoronas Chemical Co. IFFCO 1999~ 2005~ Dec 2006~ 200 t/d 330 t/d 2 x 450 t/d Urea General use Urea OTHER Abu China India Bahrain PROJECTS Dhabi Project FEED FEED Awarded Awarded Status Complete Complete Project Project Fl

  7. Slide 7: 1. Commercial Project in Malaysia

    2. MHI’s Experience 1. Commercial Project in Malaysia Plant Outline Client : Petoronas Fertilizer (Kedah) Sdn Bhd Solvent : KS-1 Capacity : 160T/D (200 T/D Max) Use of CO2 : Urea production Start up : October, 1999 Feed Gas : Stream reformer flue gas Process Description CO2 is recovered from flue ga

  8. Slide 8: 2. Commercial Project in Japan

    2. MHI’s Experience 2. Commercial Project in Japan Plant Outline Client : ‘A’ Chemical Company Solvent : KS-1 Capacity : 283T/D (330 T/D Max) Use of CO2 : General Use Feed Gas : Natural Gas and Heavy Oil Fired Boiler Start-up : 2005 Process Description CO2 is recovered from a natural gas fired boile

  9. Slide 9: 3. & 4. Commercial Projects in India

    2. MHI’s Experience 3. & 4. Commercial Projects in India Plant Outline Client : Indian Farmers Fertilizer Co. Solvent : KS-1 Solvent Capacity : 450 T/D x 2 units Feed Gas : Natural Gas and Naphtha Reformer Flue Gas Use of CO2 : Urea Production Start-up : 2006 Process Description CO2 is recovered fro

  10. Slide 10: 5. Commercial Project in Abu Dhabi

    2. MHI’s Experience 5. Commercial Project in Abu Dhabi Plant Outline Client : Ruwais Fertilizer Industries (FERTIL) Solvent : KS-1 Solvent Capacity : 400 T/D Feed Gas : Natural gas Boiler & Steam Reformer flue Gas Use of CO2 : Urea Production FEED Start-up : 2008 Completed Process Description CO2 is

  11. Slide 11: 6. Commercial Project in China

    2. MHI’s Experience 6. Commercial Project in China Plant Outline Client : ‘A’ Chemical Company Solvent : KS-1 Solvent Capacity : 800 T/D Feed Gas : Steam Reformer flue Gas Use of CO2 : Methanol Production FEED FEED Completed Completed Process Description CO2 is recovered from steam reformer flue gas

  12. Slide 12: 7. Commercial Project in India

    2. MHI’s Experience 7. Commercial Project in India Plant Outline Client : Indian Farmers Fertilizer Co. Solvent : KS-1 Solvent Capacity : 450 T/D Feed Gas : Natural gas Boiler & Steam Reformer flue Gas Use of CO2 : Urea Production Awarded Start-up : 2010 Project Process Description CO2 is recovered

  13. Slide 13: 8. Commercial Project in Bahrain

    2. MHI’s Experience 8. Commercial Project in Bahrain Plant Outline Client : Gulf Petrochemical Industries Company Solvent : KS-1 Solvent Capacity : 450 T/D Feed Gas : Natural gas Boiler & Steam Reformer flue Gas Use of CO2 : Urea Production Awarded Start-up : 2010 Project Process Description CO2 is

  14. Slide 14: Coal Fired Long Term Demonstration Plant

    2. MHI’s Experience Coal Fired Long Term Demonstration Plant Plant Outline Solvent : KS-1 Capacity : 10 T/D Feed Gas : Coal Fired Boiler (14.1 v% CO2) Start-up : July 2006 Location : Nagasaki, Japan Process Description ‡ Increased understanding of the effects of impurities on the system (dust, SOx,

  15. Slide 15: Large Scale CO2 Capture Plant (3000 T/D Plant)

    2. MHI’s Experience Large Scale CO2 Capture Plant (3000 T/D Plant) Basic design complete Absorber Stripper Cooling Tower Deep FGD Flue Gas Duct 15

  16. Slide 16: Process Flow for Amine Absorption

    3. MHI’s Flue Gas CO2 Recovery Technology Process Flow for Amine Absorption Feature of Process: Comparison with MEA solvent Flue Gas MEA KS-1 Outlet CO2 Circulation Rate 1 0.6 Purity : 99.9 % Regeneration Energy 1 0.68 Solvent Degradation 1 0.1 ABSORBER Solvent Loss STRIPPER 1 0.1 (Regenerator) Corr

  17. Slide 17: MHI's Proposed Phased Approach to Commercialization for Coal Fired Boilers

    4. CO2 Recovery from Coal-fired Boilers MHI’s Proposed Phased Approach to Commercialization of CO2 Capture Technology for Coal Fired Boilers MHI’s Operating Experience MHI’s operating experience includes an expanding number of commercial plants in a range of countries, combined with a strong foundat

  18. Slide 18: 5. MHI's Scope in a CCS Project: The CO2 Supply Chain

    5. MHI’s Scope in a CCS Project The CO2 Supply Chain ‹ The supply chain for a complete CCS project is complex ‹ Requires integration of a number of industry segments ‹ A carbon price creates incentives to drive CCS project execution ‹ Regulatory framework is in the pipeline Flue gas CO2 CO2 CO2 Long

  19. Slide 19: 6. Path Forward – Government Incentives for CCS

    6. Path Forward – Government Incentives for CCS Governments must create incentives which will encourage industry investment and widespread CCS – How? A) Funding for CCS demonstration projects – to reduce risk B) Establish regulatory certainty – do not delay further C) Create tax credits/subsidies fo

  20. Slide 20: Further Information

    Further Information Ronald Mitchell Manager Business Development Carbon Abatement Project Origination Environmental Plant Department Mitsubishi Heavy Industries, Ltd. 3-3-1 Nishi-ku, Yokohama, JAPAN, 220-8401 Office Ph: +81-45-224-9400 | Cell Ph: +81-90-4420-3941 E-mail: ronald_mitchell@mhi.co.jp MH

Mitsubishi Heavy Industries — International Workshop on Power Generation with Carbon Capture and Storage in India 2008 on 6ix