Slide 1: Ireland Inc - Chicago Resource Expo
IRELAND INC Chicago Resource Expo April 2010

Slide 2: Forward Looking Statements
Forward Looking Statements This Presentation may contain, in addition to historical information, forward -looking statements. Statements in this Presentation that are forward-looking statements are subject to various risks and uncertainties concerning the specific factors disclosed under the heading

Slide 3: Cautionary Note Regarding Estimates
Cautionary Note Regarding Estimates This presentation uses the terms “inferred”, “indicated”, and “measured resources”. The United States Securities and Exchange Commission (the “SEC”) does not normally permit issuers to disclose resource estimates in their filings with the SEC. SEC guidelines norma

Slide 4: Company Vision
Company Vision Build Ireland (OTCBB: IRLD) into a significant mid- tier mining company through the development to monetization of two precious metal projects. • Columbus Project – In active development Owns 100% of Gold / Silver mining rights Option to Expand • Red Mountain Project – Not in active d

Slide 5: Why Invest in Ireland?
Why Invest in Ireland? 1. Large Opportunity 2. Growing Opportunity 3. Lower Cost Process 4. Near Term Production Horizon 5

Slide 6: Why Invest in Ireland? Large Opportunity
Why Invest in Ireland? • Large Opportunity - ‘08 and ‘09 drill programs outlined seven mineralized zones within 5,000 acre “area of interest” - Inferred resource of 343 million tons with an average grade of 0.040 ounces per ton gold equivalent (AuE) - Two bulk leach tests extracted ~70%-83% of head

Slide 7: Why Invest in Ireland? Growing Opportunity
Why Invest in Ireland? • Growing Opportunity - Permitting process for 2010 drill program will be started this month - Aggressive 2010 drill program will be designed to expand and further delineate the resources by in-fill drilling • Goal is to upgrade the resource definition from inferred resources

Slide 8: Why Invest in Ireland? Lower Cost Process
Why Invest in Ireland? • Lower Cost Process - Cost Estimates = ~$10/ton of material - Goal: 75% extraction of 0.040 opt AuE - If achieved: operational costs $330/oz Au - Hard Rock Mining Comp.: ~$400 - $450/oz - Low Cost Operator: Strong positioning for production or acquisition 8

Slide 9: Why Invest in Ireland? Near Term Production Horizon
Why Invest in Ireland? • Near Term Production Horizon - Gold/Silver leach extraction circuit installed at onsite pilot plant in Q1 2010 - Currently testing and optimizing circuit - Expect to be producing gold on a continuous basis at the onsite pilot plant this summer 9

Slide 10: Management Team
Management Team Douglas Birnie – Chief Executive Officer, President and Director Mr. Birnie was a founder of Columbus Group Communications Inc., a privately -owned company that was acquired by TELUS Corp., one of Canada’s leading telecommunications companies Robert McDougal – Chief Financial Officer

Slide 11: Overview – Columbus Project
Overview– ColumbusProject • Gold and Silver Project • A “dry salt marsh” with drill indicated zones of surface mineable material • Located between Las Vegas and Reno in the Columbus Basin, in Esmeralda County, Nevada – a region with a proven history of major discoveries of gold and silver • Mine sit

Slide 12: Columbus Project Assets
Columbus Project Assets • 19,738 acres of mineral claims on federal land administered by the BLM (Bureau of Land Management), with an option for an additional 23,440 acres. • 378 acres permitted to 40 feet for extraction of gold and silver (Permitted Area) - 320 acre mine site, 58 acre mill site - 1

Slide 13: Drill Program 2008 and 2009
Drill Program 2008 and 2009 Identified seven mineralized zones with inferred resource of 343MM tons with 0.040 opt AuE. All reported results are by Caustic Fusion Protocol and analysis of extracted metal- in-hand for Gold and Silver. The caustic fusion protocol was selected because our research has

Slide 14: Project Prefeasibility
Project Prefeasibility Current Production Permits: mine up to 792,000 tpy in Permitted Mine Area, a 320- acre area, to a depth of 40 ft. (est. mine life 17+ years) 14

Slide 15: Independent Confirmation
Independent Confirmation All reported work to date has been completed and performed by third party engineers/geologists under Chain of Custody (COC) Technical Team– independent firms: Permitting Lumos & Associates – based in Reno, NV Project Resources McEwen Geological – Drill program management / M

Slide 16: Project Development 2010
Project Development 2010 Determine Project Resources/Reserves 2010 drill program to in-fill mineralized zones to better define continuity of grade and tonnage Update geologic technical report Complete Project Feasibility Optimize extraction process while operating on-site pilot plant Finalize mining

Slide 17: Financial Information
Financial Information 17

Slide 18: Capitalization and Finances
Capitalization and Finances Capitalization (3/31/2010) Issued and Outstanding 121,934,442 Free Float ~50,000,000 Total Fully Diluted 158,648,126 Market Capitalization (3/31/2010) ~$144 MM Finances Cash(12/31/09) + January Financing ~$8,615,000 Budget (Jan 1 ‘10 to Dec 31 ‘10) ~$7,325,000 Expected Ca

Slide 19: Expenses
Expenses Cash Expenses Budget (01/01/10 – 12/31/10) Columbus Project Property Payments $ 130,000 Drilling Program and Resource Estimates 2,155,000 Pilot Plant / Project Feasibility 2,935,000 Columbus Project Sub-Total 5,220,000 Red Mountain Project 240,000 General and Admin. 1,865,000 Cash Expenditu

Slide 20: Investment Summary
Investment Summary Exploration company with production expected this summer Identified inferred resource of 343MM tons with 0.040 opt AuE with 2008 and 2009 drill program results Simple, environmentally neutral leaching extraction process. Goal: 75% extraction Assembled talented technical team Opera

Slide 21: Ireland Inc.
Ireland Inc. Corporate Office: 2441 West Horizon Ridge Parkway, Suite 100 Henderson, NV, 89052 (702) 932-0353 info@irelandminerals. com http://www. irelandminerals. com Investor Relations: Terri MacInnis R. Jerry Falkner, CFA Bibicoff + MacInnis, Inc. RJ Falkner & Company, Inc. Tel: 818-379-8500 Tel
Source: SEC EDGAR · 8-K filed Apr 21, 2010
More decks from Ireland Inc
Corporate Update (November 2012)18 slides · Nov 29, 2012
LD Micro Conference (December 2011)10 slides · Dec 8, 2011
Rodman & Renshaw Conference September 201121 slides · Sep 9, 2011
Sidoti Micro Cap Conference June 201021 slides · Jun 30, 2010
Investor Presentation (April 2010)21 slides · Apr 15, 2010
Investor Presentation (February 2010)21 slides · Feb 3, 2010