Slide 1: YIT – Analyst lunch, December 2014
Novo Orlovsky St. Petersburg, Russia YIT – Analyst lunch, December 2014 Co-operation projects as part of YIT’s strategy Kari Kauniskangas, President and CEO
Slide 2: Contents
Contents 1 Co-operation projects, part of the strategy 2 Case example: Tripla project 3 Case example: Naantali CHP YIT | 2 | Analyst lunch, December 2014
Slide 3: Co-operation projects, part of strategy
Co-operation projects, part of strategy • Increasing role of co-operation projects: value added for customers and value creation for owners • Capital efficient business model • Higher profitability from higher value-added combined with less competition No sales risk Sales risk Self- Self- developed
Slide 4: Characteristics of different co-operation project types
Characteristics of different co-operation project types Alliance model Joint venture in development Plot co-operation Project Company Development and Development Construction Project Construction owned by YIT and construction by phase phase development and sales partner(s) YIT Development Progress R
Slide 5: Tripla
PRIPLA BY Yt
Slide 6: The project is advancing well and according to schedule
The project is advancing well and according to schedule • Zoning proceeding well and the project is Estimated timing of land acquisitions, construction and profit recognition on schedule • Helsinki city council to decide on the zoning in Q1/2015 • The zoning completed in Q2/2015 if no Land areas cla
Slide 7: Concept and brand ready, leasing started
Concept and brand ready, leasing started • Current focus on the shopping centre, ”Mall of Tripla” • Very good reception from potential tenants, more than 150 participants attended the launch event in November • Target to have anchor tenants in place by the end of H1/2015 • Formal negotiations with i
Slide 8: Project execution in a capital efficient way
Project execution in a capital efficient way • Plans for using a co-operation One potential structure for project financing in Tripla model for the project • Joint venture • Limited capital requirement, <50% equity stake • Project financing on project Debt financiers Equity investors company level •
Slide 9: Illustration of Naantali CHP power plant
Illustration of Naantali CHP power plant Naantali, Finland YIT | 9 | Analyst lunch, December 2014
Slide 10: Naantali CHP power plant, alliance model (1/2)
Naantali CHP power plant, alliance model (1/2) New multifuel power plant, 435 MW Customer: Turun Seudun Energiantuotanto Oy Total value: EUR 260 million, value for YIT EUR ~40 million Final selection criteria YIT’s project team and references appreciated Project won without the lowest target price
Slide 11: Naantali CHP power plant, alliance model (2/2)
Naantali CHP power plant, alliance model (2/2) Tendering, Tendering, 1st phase: 3rd phase: • Implementation • Capabilities model • Price Development • 6 bidders • 2 bidders phase April Sept Spring 2014 2014 2015 2017 Signing the Tendering, Implementation contract for 2nd phase: • Skills/capabilities
Slide 12: Together we can do it.
Together we can do it.