  1. Slide 1: Woodlawn Eco-Precinct Community Liaison Committee Meeting

    Woodlawn Eco-Precinct Community Liaison Committee Meeting May 2024 NSW Woodlawn Eco-Precinct 619 Collector Road / Tarago / NSW 2580 Australia off.: +61 2 8588 1360 www.veolia.com/anz

  2. Slide 2: Acknowledgement of Country

    Acknowledgement of Country Veolia acknowledges Ngunnawal people as the traditional custodians of the lands and waters in which we live and work and their continuing connection to land, water and community. We pay respects to their Elders past, present and emerging and any first nations people presen

  3. Slide 3: Introductions / Welcome

    @veoua Introductions / Welcome

  4. Slide 4: Meeting Agenda

    MEETING AGENDA Item Topic 1 Introductions / Welcome/Agenda 2 Present/Apologies Actions from last meeting 3 ARC Project Update 4 Woodlawn Eco-Precinct Operational Update 1. Woodlawn Bioreactor & Leachate Treatment Plant - tonnage 2. Water Management/Leachate Management 3. Bioenergy - gas capture & po

  5. Slide 5: Present / Apologies

    Present / Apologies

  6. Slide 6: Meeting Attendance

    MEETING ATTENDANCE Date Thursday 30th May 2024 Time 5:00pm to 7.30pm Location Tarago Hall - Wallace Street Tarago Name Present Name Present Justin Houghton (JH) (Veolia) Raymond Choy (RC) (Veolia) Cr Andy Wood (AW) (GMC Councillor) No representative (TSA Rep) Cr John Preston (JP) (QPRC Councillor) D

  7. Slide 7: Actions from Last Meeting

    Actions from Last Meeting

  8. Slide 8: Meeting Actions

    MEETING Actions Action Status Update community on H2S study in the Tarago Times - “not completed need more data” More information Veolia to investigate “snap send solve” app - IT looking at any cyber security risks IT investigating Veolia to continue to source a suitably qualified CLC meeting Facilit

  9. Slide 9: ARC Project Update

    ARC Project Update

  10. Slide 10: Veolia ARC Next Steps

    VEOLIA ARC Response to Submissions Report NEXT STEPS ● In late 2023 Veolia submitted our interim response to submissions report to DPHI and EPA ● We addressed the concerns and issues raised in the community and responding to government body submissions ● In April we received the results of the gap a

  11. Slide 11: Eco-Precinct Operational Update

    Eco-Precinct Operational Update

  12. Slide 12: Eco-Precinct Operational Update: Performance

    ECO-PRECINCT OPERATIONAL UPDATE Performance Bioreactor Landfill - Licence tonnage YTD Waste Processed (licence 7 Sep 2023 - Feb 2024) ➢ Regional Waste 96,285t - (licence 125,000t) ➢ Sydney Waste 481,369t - (licence 900,000t) ○ Both were within licence limits for Sep 2022- Sep 23 period Mechanical Bi

  13. Slide 13: Water Management: Storage status and location

    Water Management Storage status and location (End of Jan 2024) Coffer Dam #2 Below Freeboard ED1 Below Freeboard ED3N 1-4 Coffer Dam #1 Office area Leachate Above Freeboard Below Freeboard Treatment Plant Plant collection catchment ED3S Above Freeboard Western Ridge catchment Bioreactor Void catchme

  14. Slide 14: Water Management: Freeboard Management - compliance

    Water Management Freeboard Management - compliance ● ED1 - Below 0.5m freeboard ○ Current evaporation throughput 206 L/s, @20% efficiency = 3.6 ML /day volume loss ○ Extra 36L/sec evaporation system approved and being designed ● ED3N Over 0.5m freeboard and ED3SS - Below 0.5m freeboard - remaining c

  15. Slide 15: Water Management: Liquid Storage change - Trends

    Water Management Liquid Storage change - Trends ED1 ED3N and ED3SS ED3S Stormwater Coffer dam #1 Coffer dam #2 Nom de la présentation * Note: Storage volume in ML

  16. Slide 16: Eco-Precinct Operational Update: Bio-Energy

    ECO-PRECINCT OPERATIONAL UPDATE BIO-ENERGY Bioenergy 2023 Biogas Capture ➢ Gas collected in last 12 months (05/23-04/24) 46,063,481 m3 ○ Increased by 591,338 m3 compared to previous 12 months ➢ Energy Generation 57,523 MWh in last 12 months ○ Increased by 3,160 MWh compared to previous 12 months ➢ I

  17. Slide 17: Eco-Precinct Operational Update: Odour Management

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR MANAGEMENT ● Completed ○ ED3N Aeration - 5 aerator in operation, Additional surge aeration (IOA advised 14 February) installed early April 2024. ○ MBT Biofilters - Dec 2023 report recommendations,validated by TOU early May, Biofilter 2 receiving same changes tri

  18. Slide 18: Eco-Precinct Operational Update: Odour Management

    ECO-PRECINCT OPERATIONAL UPDATE ODOUR MANAGEMENT ● Odour complaints and events have been reducing since July ● Have finished one lift tipping and in the process of recovering LFG capture ● Installed extra drainage to ensure additional gas can be extracted from under the waste surface in the impacted

  19. Slide 19: Environment Update

    Environment Update

  20. Slide 20: Independent Odour Audit updates

    Independent Odour Audit updates Action Status Completion Date The ambient landfill gas The Odour Unit deployed the sampling equipment on 28 May 2024. This was a delayed 28 May 2024 composition laboratory analysis deployment as a result of unfavourable winds on previously planned dates. Improved mana

  21. Slide 21: Independent Odour Audit updates

    Independent Odour Audit updates Action Status Completion Date Leachate Management System Veolia investigated the cause of the elevated odour levels within the LMS, and implemented Completed - surge aeration improvement improvement actions. The Odour Unit have resampled the dams with elevated odour.

  22. Slide 22: Environmental Compliance Update: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS Approval Type Description Status MP 10_0012 Modifications Modify the existing project approval for the Bioreactor and MBT to: Transport to ARRF removed AWT 06_0239 ● Construct an approximately 15 megalitre (ML) dam at the

  23. Slide 23: Environmental Compliance Update: PA Modifications & Post Approval Applications

    ENVIRONMENTAL COMPLIANCE UPDATE PA MODIFICATIONS & POST APPROVAL APPLICATIONS

  24. Slide 24: Environmental Compliance Update: Regulatory Enforcements

    ENVIRONMENTAL COMPLIANCE UPDATE REGULATORY ENFORCEMENTS EPL/PA Date Facility Description Context Action EPL 11436 24/06/2022 Woodlawn Prevention Container transport to site - leaking Veolia engaged experts to assist in rectifying the Bioreactor Notice containers, requirement to leak test containers

  25. Slide 25: Community Q & A

    Community Q & A

  26. Slide 26: CLC Actions

    CLC Actions

  27. Slide 27: Next Meeting

    Next Meeting The next Community Liaison Meeting will be held at the Woodlawn Eco-Precinct TBC agreed.