Txnm Energy, Inc. · NYSE:TXNM

Txnm Energy — PNM Resources — Q1 2013 Earnings Presentation

29 slides from Txnm Energy's earnings presentation, May 6, 2013

  1. Slide 1: Q1 2013 Earnings Presentation

    Q1 2013 Earnings Presentation May 6, 2013

  2. Slide 2: Safe Harbor Statement

    Safe Harbor Statement Statements made in this presentation that relate to future events or PNM Resources’ (“PNMR”), Public Service Company of New Mexico’s (“PNM”), or Texas-New Mexico Power Company’s (“TNMP”) (collectively, the “Company”) expectations, projections, estimates, intentions, goals, targ

  3. Slide 3: Opening Remarks & Overview

    Opening Remarks & Overview Pat Vincent-Collawn Chairman, President and CEO

  4. Slide 4: Q1 2013 Financial Results and Company Updates

    Q1 2013 Financial Results and Company Updates Q1 2013 Q1 2012 Ongoing EPS(1) $0.18 $0.17 GAAP EPS(1) $0.13 $0.21  S&P credit ratings upgrade  PNM Resources has moved to investment grade  Affirmed 2013 ongoing earnings guidance at $1.32 - $1.42 (1) On a diluted basis 4

  5. Slide 5: Load and Economic Conditions

    Load and Economic Conditions Regulated Retail Energy Sales Growth Q1 2013 vs Q1 2012 (weather-normalized and leap-year adjusted) PNM(1) TNMP(2) Residential (0.8%) 4.0% Unemployment Rate Commercial (1.8%) 0.8% Industrial (6.2%) 0.3% 7.5% 6.9% 6.4% Total Retail (1.9%) 2.2% NM(3) TX(3) U.S.(4) YTD Aver

  6. Slide 6: Regulatory Update

    Regulatory Update Recent Approvals Action Approval Date Docket No. TNMP TCOS filing Approved with rates in place March 19, 2013 41176 FERC generation case Settlement approved April 5, 2013 ER11-4535-000 and (Navopache Electric Cooperative, Inc.) ER12-72-000 Expected Outstanding Items Action Docket N

  7. Slide 7: San Juan BART Timeline and Update

    San Juan BART Timeline and Update  Revised State Plan Expected Expected Action Item Start Completion PNM submits BART analysis to State Q2 2013 April 1, 2013 EIB approval of new SIP submitted by NMED Q2 2013 Q4 2013 EPA approval of SIP submitted by EIB Q4 2013 Q4 2014 NMPRC approval for retirement

  8. Slide 8: Financial Overview

    Financial Overview Chuck Eldred Executive Vice President and CFO

  9. Slide 9: Q1 2013 Financial Summary

    Q1 2013 Financial Summary Ongoing EPS $0.01 $0.01 $0.01 $0.18 $0.17 Corp/Other PNM TNMP Q1 2012 Q1 2013 9

  10. Slide 10: PNM and TNMP: Q1 2013 vs Q1 2012 EPS

    PNM and TNMP: Q1 2013 vs Q1 2012 EPS (Ongoing) PNM Q1 2013 Key Performance Drivers ∆ EPS Outage costs $0.02 Rate relief $0.02 $0.18 $0.17 Weather $0.02 PV3 market price $0.01 AFUDC ($0.01) Depreciation ($0.01) Load ($0.04) Other ($0.02) Q1 2012 Q1 2013 TNMP Q1 2013 Key Performance Drivers ∆ EPS Load

  11. Slide 11: Credit Ratings

    Credit Ratings S&P PNMR PNM TNMP Issuer debt rating BBB-(1) BBB(1) A-(2) Outlook Stable Stable Stable Moody’s PNMR PNM TNMP Debt rating Ba1(1) Baa3(1) A3(2) Outlook Stable Stable Stable (1) Senior unsecured debt (2) Senior secured debt 11

  12. Slide 12: 2013 Guidance

    2013 Guidance (Ongoing) $1.32 Consolidated EPS $1.42 PNM TNMP Corp/Other $1.16 - $1.23 $0.32 - $0.34 ($0.16) – ($0.15) 12

  13. Slide 13: 2013 Checklist

    2013 Checklist Continue progress toward: Implementing San Juan BART agreement Improving FERC earnings Optimizing the value of TX TCOS filings Maintain strong electric reliability and power plant availability Control O&M and capital costs Continue execution of plan to achieve top quartile tota

  14. Slide 14: Questions & Answers

    Questions & Answers

  15. Slide 15: Appendix

    Appendix

  16. Slide 16: PNM Plant EAF and Outages

    PNM Plant EAF and Outages 97.2% 2013 - 2014 Outage Schedule 89.6% 92.4% 85.5% 84.8% Duration Time 81.5% Unit in Days Period San Juan 4 54 Q1 – Q2 2013 1 12 Q1 2014 2 28 Q1 2014 Four Corners 4 21 Q2 2013 5 13 Q2 2014 4 13 Q4 2014 San Juan Four Corners Palo Verde Palo Verde 1 30 Q1 – Q2 2013 Q1 2012 Q

  17. Slide 17: Core Capital Spending

    Core Capital Spending 2013 – 2017 Core Capital Plan: $1.8B (In millions) PNM Rate Base CAGR: 2% - 3% 2013 Expected Depreciation: $153M TNMP Rate Base CAGR: 7% - 9% $429 $390 $14 $399 $14 $15 $128 $75 $84 $301 $13 $280 $13 $91 $92 $291 $310 $287 $197 $175 2013 2014 2015 2016 2017 PNM TNMP Other $1.3B

  18. Slide 18: Capital Spending Under Revised State Plan

    Capital Spending Under Revised State Plan Estimated incremental SIP(1) capital: $344M(2) PNM rate base CAGR with SIP(2): 3% - 5%  Revised State Plan (In millions) • Shut down units 2 and 3 $478  By year-end 2017 $462 • Install SNCRs on units 1 and 4 $33 $426 $400 $20  By early 2016 $10 $7 $377 $1

  19. Slide 19: Potential Earnings Power

    Potential Earnings Power Minimizing regulatory lag, improving market prices, and reducing Corporate debt could improve current EPS by $0.15 to $0.24 without rate base growth Mid Point Guidance Potential Earnings Power Growth 2013 % of Range Potential Rate Rate Potential Allowed Resulting Achievement

  20. Slide 20: Weather Impact

    Weather Impact PNM Q1 2013 Q1 2012 Normal Heating Degree Days 2,079 1,848 1,957 Cooling Degree Days 0 0 0 EPS Impact $0.01 ($0.01) $0.00 TNMP Q1 2013 Q1 2012 Normal Heating Degree Days 916 696 986 Cooling Degree Days 70 182 92 EPS Impact ($0.01) ($0.01) $0.00 A-6

  21. Slide 21: Liquidity as of May 1, 2013

    Liquidity as of May 1, 2013 PNM PNM Resources Resources PNM TNMP Consolidated Financing Capacity(1): (In millions) Revolving credit facility $300.0 $400.0 $75.0 $775.0 As of 5/1/13: Short-term debt and LOC balances $71.6 $19.7 $30.3 $121.6 Remaining availability 228.4 380.3 44.7 653.4 Invested cash

  22. Slide 22: Regulatory Information

    Regulatory Information

  23. Slide 23: NMPRC Commissioners and Districts

    NMPRC Commissioners and Districts NMPRC Districts and Term PNM Service Areas Name District Party Ends Karen Montoya District 1 2016 Democrat Patrick Lyons District 2 2014 Republican Valerie Espinoza District 3 2016 Democrat Vice Chair Theresa Becenti-Aguilar District 4 2014 Democrat Ben Hall Distric

  24. Slide 24: Public Utility Commission of Texas Commissioners

    Public Utility Commission of Texas Commissioners Term Term Name Party Began Ends Donna Nelson Aug. 2008 Aug. 2015 Republican Chairman Kenneth Anderson Sept. 2008 Aug. 2017 Republican Awaiting appointment(1) Commissioners are appointed by Governor of Texas. Length of term is determined by the Governo

  25. Slide 25: Balance Sheet and Credit Metrics

    Balance Sheet and Credit Metrics

  26. Slide 26: Selected Balance Sheet Information

    Selected Balance Sheet Information (In millions) Dec 31, 2012 Mar 31, 2013 Long-Term Debt (incl. current portion) PNM $1,215.6 $1,215.6 TNMP 311.6 311.7 PNMR 145.1 145.2 Consolidated $1,672.3 $1,672.5 Total Debt (incl. short-term) (1) PNM $1,236.7 $1,304.5 TNMP 311.6 336.7 PNMR 282.7 274.6 Consolida

  27. Slide 27: Environmental Compliance

    Environmental Compliance

  28. Slide 28: Environmental Control Equipment at Coal Units

    Environmental Control Equipment at Coal Units PNM Share Low NOx Activated Coal Unit Capacity Burners/ Carbon SNCR (2) SCR (2) Baghouse (3) Scrubbers (MW) Overfired Air Injection (1) San Juan Unit 1 170 X X X X San Juan Unit 2 170 X X X X San Juan Unit 3 249 X X X X San Juan Unit 4 195 X X X X Four C

  29. Slide 29: Impact of Proposed Environmental Regulation

    Impact of Proposed Environmental Regulation Estimated Compliance Costs Comments (PNM Share) San Juan Generating Station SNCR technology on 2 units; Retire 2 units Clean Air Act – Regional Haze(1) (State Alternative) – SNCR ~$62M - $64M See “Capital Spending Under Revised State Plan” slide Included i