Tlou Energy Ltd · ASX:TOU

Tlou Energy — Investor Presentation (May 2015)

29 slides from Tlou Energy's investor presentation, May 25, 2015

  1. Slide 1: Capital Raising Presentation

    For personal use only Capital Raising presentation Anthony (Tony) Gilby MD & CEO May 2015

  2. Slide 2: Disclaimer

    Disclaimer Important notice and disclaimer NO LIABILITY For personal use only This presentation (Presentation) has been prepared by Tlou Energy Limited (Tlou or the Company) and may contain forward- To the fullest extent permitted by law, Morgans Corporate (Morgans), disclaim any obligation or under

  3. Slide 3: Contents

    Contents For personal use only Offer Summary Company Overview Lesedi CBM Project Offer Details Investment Risks and Foreign Selling Restrictions 3

  4. Slide 4: Offer Summary

    Offer Summary For personal use only • A fully underwritten 4 for 15 Non-Renounceable Entitlement Offer to raise approximately A$5.5 million Offer Structure • Issue price of A$0.14 per share representing a discount of 30% to last close and 25% to the theoretical ex-rights price • Undertake the follow

  5. Slide 5: About Tlou Energy

    About Tlou Energy For personal use only Who we ASX listed coalbed methane (CBM) company are What CBM in Botswana we do Our Provide a clean and reliable energy Goal source to Botswana & southern Africa 5

  6. Slide 6: Company Overview

    Company Overview For personal use only Market Cap: Share Price: $0.20 ~$30m (21 May 2015) 148m shares Operations: Acreage: Botswana 10 Permits 100% owned 4 pilot locations HQ: Brisbane ASX: TOU 6

  7. Slide 7: Key Information

    Key Information For personal use only Botswana CBM Project • ~8,300km2, 100% owned • ~100 well database Certified Contingent Resources • 4.9 BCF (1C) • 239 BCF (2C) • 3,295 BCF (3C) Significant market opportunity • Botswana’s most advanced project • High energy demand Location • Low cost • Supportiv

  8. Slide 8: Experienced Team

    Experienced Team For personal use only 8 Field Personnel

  9. Slide 9: Botswana Field Operations

    Botswana Field Operations For personal use only Aerial view of Operations Selemo Pod Gas flare - Selemo Pod December 2014 9

  10. Slide 10: Botswana CBM Project

    Botswana CBM Project For personal use only 10

  11. Slide 11: Lesedi Project

    11 For personal use only Lesedi Project

  12. Slide 12: Gas flows

    Gas flows For personal use only Selemo Pilot - Short term test – December 2014* • Peak recorded gas flow of ~400,000 cfd • Average recorded gas flow of ~200,000 cfd • Results suggest a commercial development may be achievable. • First in Botswana to flow CBM gas at these rates *As detailed in Tlou’s

  13. Slide 13: Lesedi CBM Project Technical Fundamentals

    Lesedi CBM Project For personal use only Technical Fundamentals Coal depth ~300-700m Cumulative net coal thickness ~25m (Average) Gas contents 4-6 m3/t (DAF) (Average) Unstimulated reservoir ~2-5mD permeability per DST up to 90%+ Gas compositions methane 13

  14. Slide 14: Horizontal Pilot Design

    Horizontal Pilot Design For personal use only • Horizontal wells (~750m in-seam) with vertical pumping well • Lesedi pod completed as a dual lateral • Selemo pod completed as a single lateral • Target Reservoir: Basal Morupule coal seam (~6m) 14

  15. Slide 15: Operations

    Operations For personal use only Planned work program to end 2015 Up to 2 Single Horizontal Pilot Pods Commencing June 2015 Selemo area Dewatering and testing operations Results 2H 2015 Objective:  maximise reservoir drainage area  enhance dewatering  measure long-term gas flow potential  achiev

  16. Slide 16: Botswana Operations

    Botswana Operations For personal use only 16

  17. Slide 17: Commercialisation

    Commercialisation For personal use only Sequence • Pilot Project up to 10MW (scalable) • Existing Orapa Power Station 90MW • Proposed Power Station 300MW • Export Existing Power Grid • 33kV close to Lesedi Project • 220kV to the east • 400kV Interconnect to neighbouring countries 17

  18. Slide 18: Commercialisation: Initial Gas Delivery – Proof of Concept

    Commercialisation For personal use only Initial Gas Delivery – Proof of Concept • Uses otherwise flared gas • Transport CNG via truck • Connect to generator • Potential grid inter-connect Flared gas Transport CNG Generator Connect to grid 18

  19. Slide 19: Independently Certified Contingent Resource

    Independently Certified Contingent Resource For personal use only Certified Resource Statement Certified Contingent Resource OGIP(1) Unrisked Gross (100 Percent) Unrisked Net (100 Percent) Category (BCF) (BCF) (BCF) • 4.9 BCF (1C) Contingent Resources Low Estimate (1C) 7.6 4.9 4.9 • 239 BCF (2C) Bes

  20. Slide 20: Forward Plan

    Forward Plan For personal use only Gas Expanded Reserve Flow gas Marketing FID program certification Agreements • Achieved • Initial Gas to • Commencing • Target 2H15 • Target Power project June 2015 end 2015 • 90MW Orapa • Target first gas • 300MW IPP delivery 2016 20

  21. Slide 21: Offer Details

    Offer Details For personal use only • A fully underwritten 4 for 15 Non-renounceable Entitlement Offer of approximately 39.4 million new shares to raise approximately A$5.5 million • Record date of 7.00pm (AEST) on Friday, 29 May 2015 Entitlement Offer • New Shares rank pro-rata with existing TOU sh

  22. Slide 22: Use of Proceeds

    Use of Proceeds For personal use only Sources Uses Lesedi Project Pilot expansion • Up to 2 single horizontal pilot pods $2.6m (Selemo) Existing cash (31March 2015) $4.6m $0.3m • Potential single vertical well • Operations equipment $0.8m • Operating support & maintenance $3.6m Capital Raising (net

  23. Slide 23: Offer Timetable

    Offer Timetable For personal use only Activity Date Announcement of the Entitlement Offer Monday, 25 May 2015 Offer Booklet lodged with ASX Monday, 25 May 2015 Trading on an ex-entitlement basis Wednesday, 27 May 2015 Record date for determining entitlements for the Entitlement Offer (by 7pm) Friday

  24. Slide 24: Investment opportunity

    Investment opportunity For personal use only 24

  25. Slide 25: Foreign Selling Restrictions

    Foreign Selling Restrictions For personal use only New Zealand: This presentation does not constitute a prospectus or investment statement and has not been registered, filed with or approved by any New Zealand regulatory authority under or in connection with the Securities Act 1978 (New Zealand). Th

  26. Slide 26: Selling Restrictions

    Selling Restrictions For personal use only France: This document is not being distributed in the context of a public offering of financial securities (offre au public de titres financiers) in France within the meaning of Article L.411-1 of the French Monetary and Financial Code (Code monétaire et fi

  27. Slide 27: Selling Restrictions

    Selling Restrictions For personal use only Any financial information contained in this document has been prepared in accordance with Australian Accounting Standards and also comply with International Financial Reporting Standards and interpretations issued by the International Accounting Standards B

  28. Slide 28: Summary of Key Risks

    Summary of Key Risks For personal use only There are conditions that Tlou must satisfy to maintain its prospecting licences in Botswana and to facilitate their conversion to mining permits. Tenure risk There is a risk that Tlou may not be able to satisfy these requirements. Tlou has certain prospect

  29. Slide 29: Thank You

    Thank You For personal use only 210 Alice St Brisbane QLD 4000 Australia Tel: +61 7 3012 9793 Ground Floor, Victoria House 132 Independence Avenue Gaborone Botswana Tel: +267 316 0857 www.tlouenery.com info@tlouenergy.com ASX: TOU

Tlou Energy — Investor Presentation (May 2015) on 6ix