Slide 1: March 2022 CCC Presentation
March 2022 CCC Presentation 1 March 2022 July – December 2021 Hera Project CCC Presentation ASX Code: AMI
Slide 2: Acknowledgement of Country
2 Acknowledgement of Country March 2022 CCC Presentation • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure t
Slide 3: Work, Health & Safety – Jul 21 to Dec 21
3 Work, Health & Safety – Jul 21 to Dec 21
Slide 4: Q2 Highlights
4 Q2 HIGHLIGHTS March 2022 CCC Presentation Integrity I Certainty I Courage I Performance • Group TRIFR reduced from 8.6 to 7.6 across the quarter • Protocols adapted to manage risk of Omicron remain effective • Reduced workforce availability (approximately 20% across the Performance group) saw mode
Slide 5: Operating Snapshot
5 OPERATING SNAPSHOT March 2022 CCC External headwinds impacting throughput and production Presentation • Group gold production (26.9 koz) and AISC (A$1,395/oz) Group Gold Equivalent Production consistent with previous quarter • Lower quarterly lead and zinc metal production partly offset by higher
Slide 6: Continued Performance: Safety and Environment Outcomes
6 CONTINUED PERFORMANCE March 2022 CCC Safety and Environment Outcomes Presentation Group Total Recordable Injury Group Total Reportable Environmental Frequency Rate Incident Frequency Rate • 12-month moving average (12-month moving average) (12-month moving average) Group Total Recordable Injury Fr
Slide 7: Safety is at the core of our business
7 Safety is at the core of our business March 2022 CCC Presentation Hera Work, Health and Safety – Jul 21 to Dec 21 1 Positive activity • Lead indicator activity by departments for the period was at full practical compliance • By the end of the period, 70% of those involved in Lead indicator activit
Slide 8: Safety is at the core of our business
8 Safety is at the core of our business March 2022 CCC Presentation Work, Health and Safety – Jul 21 to Dec 21 3 Lag indicators • A reportable incident occurred in September when a fall of ground took place while a Jumbo was performing Re-Entry Rehabilitation works. • A recordable injury occurred in
Slide 9: Environment & Community – Jul 21 to Dec 21
9 Environment & Community – Jul 21 to Dec 21
Slide 10: Sustainability Pillars: Sustainable Foundation
10 SUSTAINABLE FOUNDATION March 2022 CCC Driven by our Vision and Values and underpinning durability Presentation 51% Leadership and SUSTAINABILITY GOVERNANCE accountability 75% D&I Response rate to Working Group Employees trained in Sustainability inaugural employee established ‘The Aurelia Way’ ap
Slide 11: Social licence to operate
11 Social licence to operate March 2022 CCC Presentation Seeking to deliver mutual benefit – Jul 21 to Dec 21 1 Community a critical stakeholder • Scholarship payments were provided for local students • Labour was provided for 3 clean-ups in the Nymagee township • Contributions were made towards the
Slide 12: Hera Mine Environmental Incidents, Complaints & Initiatives
12 Hera Mine March 2022 CCC Presentation Environmental Incidents, Complaints & Initiatives– Jul 21 to Dec 21 1 Environmental Incidents • On 3 December, the water level in a process water settling pond was found to be at a lower level than expected. Samples were taken of the water remaining inside th
Slide 13: Hera Mine Environmental Incidents, Complaints & Initiatives
13 Hera Mine March 2022 CCC Presentation Environmental Incidents, Complaints & Initiatives– Jul 21 to Dec 21 3 Environmental Initiatives • Real-time air quality monitoring stations were set up around the site. Calibration and validation was completed in October. • The Management Plan and MOP updates
Slide 14: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC 14 March 2022 CCC Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 15: Hera Mine Day time period
15 Hera Mine March 2022 CCC Presentation Environmental Monitoring – Jul 21 to Dec 21 July – December 2021 Hera Project CCC 1 March 2022 Presentation Day time period = 7am to 6pm Monday to Saturday
Slide 16: Hera Mine Evening time period
16 Hera Mine March 2022 CCC Presentation Environmental Monitoring – Jul 21 to Dec 21 July – December 2021 Hera Project CCC 1 March 2022 Presentation Evening time period = 6pm to 10pm Monday to Saturday
Slide 17: Hera Mine Night time period
17 Hera Mine March 2022 CCC Presentation Environmental Monitoring – Jul 21 to Dec 21 July – December 2021 Hera Project CCC 1 March 2022 Presentation Night time period = 10pm to 7am Monday to Saturday, all day Sunday and Public Holidays
Slide 18: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC 18 March 2022 CCC Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 19: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC 19 March 2022 CCC Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 20: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC March 2022 CCC 20 Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 21: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC 21 March 2022 CCC Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 22: Hera Mine Environmental Monitoring
July – December 2021 Hera Project CCC March 2022 CCC 22 Presentation Presentation 1 March 2022 Hera Mine Environmental Monitoring – Jul 21 to Dec 21
Slide 23: Projects Update Jul 21 to Dec 21
23 Projects Update Jul 21 to Dec 21
Slide 24: Federation Project – Jul to Dec
24 Federation Project March 2022 CCC Presentation – Jul 21 to Dec 21 1 Federation Exploration Decline Program • Exploration drilling continues. • All identified Aboriginal cultural heritage sites are marked with steel posts and signage • The disturbance boundary for the box cut, site facilities, mag
Slide 25: Contact
CONTACT T: +61 7 3180 5000 E: office@aureliametals.com.au Level 17, 144 Edward Street BRISBANE QLD 4000 GPO Box 7 BRISBANE QLD 4001 aureliametals.com.au