  1. Slide 1: Investor Presentation July 2025

    Investor Presentation July 2025 CAT 777 Fleet at Skouries

  2. Slide 2: Forward Looking Statement

    Forward Looking Statement Definitions and Photos: Capitalized terms used in this presentation but not otherwise defined herein have the meanings ascribed thereto in the Management’s Discussion and Analysis dated May 1, 2025 of Eldorado Gold Corporation for the three months ended March 31, 2025 (the

  3. Slide 3: Non-IFRS Measures

    Non-IFRS Measures Certain non-IFRS financial measures and ratios are included in this presentation, including total cash costs ($/oz sold), all-in sustaining costs ("AISC") ($/oz sold), adjusted net earnings, adjusted net earnings per share, adjusted EBITDA, cash flow from operating activities befor

  4. Slide 4: Diversified Portfolio of Long-Life, High-Quality Assets

    Diversified Portfolio of Long-Life, High-Quality Assets Kassandra Mines, GREECE Diverse Asset Portfolio ⚫ Olympias ⚫ Skouries ⚫ Stratoni • Operations in Türkiye, Greece and Canada ⚫ Olympias, GREECE (15-year mine life) 2024 Au Production 69,532 oz • 11.9 Moz of P&P gold reserves(2) 2024 AISC/oz sold

  5. Slide 5: Strong Investment Rationale

    Strong Investment Rationale Eldorado is driving investor returns by focusing on four key areas Pipeline of Strategic Focused Attractive Financial Growth Projects on Sustainability Valuation Position SKOURIES • Our Sustainability Integrated • Advancing high-quality Greek • Cash and cash equivalents o

  6. Slide 6: Upcoming Value Drivers

    Upcoming Value Drivers Focused on upcoming value drivers CORPORATE • Multi-year guidance demonstrates 33% growth on gold production over three- year period, based on 2024 production TÜRKIYE • Kışladağ Engineering and geometallurgical studies focused on the understanding of future mining phases and o

  7. Slide 7: 2025 Guidance and 3-Year Growth Profile

    2025 Guidance and 3-Year Growth Profile Growing production with significant upside from Skouries Au & Cu production 2025 3-YEAR PRODUCTION OUTLOOK(3): GOLD INCREASING 43% FROM 2023 TO 2027 GOLD PRODUCTION: 460,000 – 500,000 oz COPPER PRODUCTION STARTING IN 2026 800 ~43% Growth 80 TOTAL CASH COSTS(1)

  8. Slide 8: Attractive Valuation

    Attractive Valuation Advancing high-quality Greek assets creates re-rating potential Consensus P/NAV Consensus EV/2025E EBITDA(1) 12.00 1.40 10.00 1.20 EV / 2024 EBITDA 8.00 1.00 P/NAV 0.80 6.00 0.60 4.00 0.40 2.00 0.20 0.00 0.00 NGD AGI BTO SSR IMG ELD EQX CG AGI SSR NGD ELD IMG EQX BTO CG Source:

  9. Slide 9: Strong Financial Position

    Strong Financial Position Focus on maintaining solid financial position which provides flexibility to unlock value across our business Liquidity Position(1,2) (as of March 31, 2025) TOTAL LIQUIDITY: $1.2 billion Cash and cash equivalents + availability on senior secured credit facility 241 CASH & CA

  10. Slide 10: Skouries

    Skouries High-grade gold-copper porphyry deposit that is a key driver of Eldorado’s growth story OVERVIEW ADVANCING SKOURIES Location Halkidiki Peninsula, Greece • €680 M financing package (including additional cost overrun facility) secured for the development of Deposit type Gold-copper porphyry S

  11. Slide 11: Skouries Project Update: Capital Cost & Schedule

    Skouries Project Update: Capital Cost & Schedule Commercial production expected mid-2026; Initial 20-year mine life with robust economics Project Capital Variance Accelerated Operational Capital $86 $21 $1,063 CAPITAL COST ESTIMATE: $1.06 B $36 ACCELERATED MINING COST ESTIMATE: $154 M $920 $154 US$

  12. Slide 12: Skouries: Recent Achievements

    Skouries: Recent Achievements Skouries progressing to plan: First production expected in Q1 2026 and commercial production in mid-2026; Construction project capital invested since restart of construction to March 31, 2025: $588.7 M Q1 2025 HIGHLIGHTS • Q1 2025 project capital: $83.8 M plus $6.4 M of

  13. Slide 13: Skouries Progress: September 2025 thru June 2025

    Skouries Progress: September 2025 thru June 2025 12

  14. Slide 14: Process Plant

    Process Plant Work continues to expand to additional work fronts for cable tray, mechanical installations, piping installations have started and the pumphouse. Water testing of the rougher flotation circuit is also underway June 2025 September 2024 13

  15. Slide 15: Process Plant – west side infrastructure

    Process Plant – west side infrastructure Work on the support infrastructure including the sub-station, water pump station, lime plant, flotation blowers building, compressor building and flotation reagent areas. The substation structural concrete is complete and cable tray has also been completed. S

  16. Slide 16: Process Plant – east side infrastructure

    Process Plant – east side infrastructure Structural steel installation is complete for the lime plant building and flotation blowers building. Guar Lime and blowers September 2024 Pebble crusher June 2025 September 2024 15

  17. Slide 17: Thickeners

    Thickeners Concrete works for the first thickener is complete and mechanical installations have commenced. The second thickener is approximately 85% complete and the base for the third thickener has been completed. Water testing of the clarifier and water storage tank has commenced Thickener #2 Thic

  18. Slide 18: Filtered Tailings Building

    Filtered Tailings Building Filtered tailings building: Piling & concrete complete, transition to installation of structural steel and major mechanical equipment – advancing as planned June 2025 September 2024 17

  19. Slide 19: Primary Crusher

    Primary Crusher The concrete foundation has been completed and work is advancing; the primary crusher feed chute and spile bars have been installed. June 2025 September 2024 Primary crusher pre-assembly 18

  20. Slide 20: Coarse Ore Stockpile & Reclaim Feed Tunnel

    Coarse Ore Stockpile & Reclaim Feed Tunnel During Q1 2025, piling and drainage work for the primary crusher conveyor alignment to the coarse ore stockpile was completed and final excavations are commencing. June 2025 September 2024 19

  21. Slide 21: Skouries: Advancing Construction

    Skouries: Advancing Construction Advancing Construction May 2025 20

  22. Slide 22: Skouries: Fully Funded with Strategic Project Financing Partners

    Skouries: Fully Funded with Strategic Project Financing Partners Maximizing shareholder value with well-aligned strategic partnerships Key Features of Term Facility PROJECT IS • Non-recourse to Eldorado; secured by Hellas Gold FULLY FUNDED • Blended interest rate of approximately 6%(1) • 10-year ter

  23. Slide 23: Skouries: Land Reclamation in Parallel with Mining Activity

    Skouries: Land Reclamation in Parallel with Mining Activity Bringing the mine progressively back to as close to its original condition as early as possible TAILINGS MANAGEMENT SUPPORTS PROGRESSIVE RECLAMATION • Tailings are a by-product of the extraction process • At Skouries – we are utilizing filt

  24. Slide 24: Lamaque Complex

    Lamaque Complex Underground gold mine located in Val-d’Or, Québec. The high-grade orogenic Triangle deposit feeds the current mine life. OVERVIEW EXPLORATION UPSIDE Location Québec, Canada • Ormaque and Triangle deposits remain open at depth Ownership 100% • Large resource base and exploration upsid

  25. Slide 25: Lamaque Complex

    Lamaque Complex Celebrated the one millionth ounce produced during Q1 2025 Q1 2025 HIGHLIGHTS • Q1 gold production of 40,438 oz at total cash costs(1) of $836/oz sold • Production in Q1 2025 impacted by: Lower grades and recovery, partially offset by higher throughput • Costs impacted by higher labo

  26. Slide 26: Lamaque Complex: Advancing Ormaque

    Lamaque Complex: Advancing Ormaque Second bulk sample planned for 2025 First round drilling Maintenance bay 25

  27. Slide 27: Kışladağ

    Kışladağ Kışladağ is a low-grade, bulk-tonnage, open pit operation that uses heap leaching for gold recovery OVERVIEW ENHANCING EFFICIENCIES Location Uşak Province, Türkiye • Engineering study underway focused on the geometallurgical understanding of future mining Ownership 100% phases and optimizin

  28. Slide 28: Kışladağ

    Kışladağ Solid start to the year, aided by continued leaching of ounces stacked in 2024 Q1 2025 HIGHLIGHTS • Q1 gold production of 44,319 oz at total cash costs(1) of $1,039/oz sold • Production in Q1 2025 benefited from: Continued leaching of gold ounces stacked during 2024 21% increase in ounces p

  29. Slide 29: Kışladağ: Improving irrigation engineering

    Kışladağ: Improving irrigation engineering Sub-cell collection system Deep ripping system 28

  30. Slide 30: Kışladağ: Completed North-ADR Plant

    Kışladağ: Completed North-ADR Plant North-ADR plant First gold pour in late October 2024 Top: Aerial view of North-ADR plant and infrastructure; Bottom: Interior of North-ADR plant. 29

  31. Slide 31: Efemçukuru

    Efemçukuru High-grade underground operation located in Izmir Province in western Türkiye OVERVIEW MAINTAIN CONSISTENT PRODUCTION Location İzmir Province, Türkiye • Efemçukuru focused on continuous improvement Ownership 100% • Efemçukuru met annual production guidance for 10th consecutive year, since

  32. Slide 32: Efemçukuru

    Efemçukuru Inline quarter – production and cost Q1 2025 HIGHLIGHTS • Q1 gold production of 19,307 oz at total cash costs(1) of $1,357/oz sold • Gold grade, throughput, and production inline with expectations Q1 2025 2025 Guidance Gold Production 19,307 oz 70 – 80 K oz Total cash costs ($/oz sold)(1)

  33. Slide 33: Olympias

    Olympias Carbonate replacement style deposit with high gold grades and an orebody that will allow for mining rates up to 1 million tonnes per year OVERVIEW FOCUS ON GROWTH Location Halkidiki Peninsula, Greece • Continue to deliver Olympias productivity Ownership 100% improvements and expand processi

  34. Slide 34: Olympias

    Olympias Production during the quarter impacted by unplanned maintenance and lower throughput; back on track for Q2 Q1 2025 HIGHLIGHTS • Q1 gold production of 11,829 oz at total cash costs(1) of $2,398/oz sold • Production in Q1 2025 impacted by: Lower throughput due to plant equipment downtime duri

  35. Slide 35: Environmental Rehabilitation at Olympias

    Environmental Rehabilitation at Olympias Eldorado restored over 32 acres of an area that was used by a previous operator to improperly dispose of tailings containing arsenopyrite. Before restoration work (2012) After restoration work (2021) RESTORATION OF OLD OLYMPIAS ARSENOPYRITE CONCENTRATE STORAG

  36. Slide 36: Perama Hill

    Perama Hill Low-cost epithermal gold-silver project with transformative growth potential OVERVIEW SUPPORTS THE GROWTH PIPELINE Location Thrace, Greece • Next mine expected to be developed after Skouries Ownership 100% • Exploration potential in the Thrace region Mine type Open pit supports opportuni

  37. Slide 37: Perama Hill

    Perama Hill Upcoming catalysts • Social & Environmental Due Diligence – Ongoing (2025) • Project optimization and studies are ongoing to prepare permitting documentation Future developments • EIA submission • EIA Approval & Presidential Decree (PD) issued • Submission of full Social & Environmental

  38. Slide 38: 2025 Exploration: Focused in Eldorado's Operating Jurisdictions

    2025 Exploration: Focused in Eldorado’s Operating Jurisdictions Includes In-Mine Resource Conversion and Expansion Drilling, Drill Testing Multiple Near-Mine and Early-Stage Targets, as well as Generating Projects and New Targets through Generative Initiatives Generate & Grow Expand & Enhance Suppor

  39. Slide 39: Climate Change Strategy – Our GHG Emissions Mitigation Target

    Climate Change Strategy – Our GHG Emissions Mitigation Target Mitigate GHG emissions by an amount equal to 30% of our 2020 baseline by 2030, on a “business-as-usual” basis(1) Journey to Our GHG Emissions Mitigation Target Achievement Pathway Decarbonization • Leverages Eldorado’s low emissions on a

  40. Slide 40: ESG Recognized as a Key Priority

    ESG Recognized as a Key Priority Eldorado ESG performance as a mid-cap miner includes recognition of strong sustainability management practices ESG Rating Performance Recognition for Responsible Mining • MAC-TSM Level AAA on Tailings Management at all operating tailings facilities: Lamaque ELD Score

  41. Slide 41: Appendix

    >< Q Zz uu o. o. Sg

  42. Slide 42: Eldorado Gold Executive Management Team

    Eldorado Gold Executive Management Team Experienced Operators Supported by a Committed and Proven Leadership Team Executive Leadership George Burns Paul Ferneyhough Frank Herbert Simon Hille Louw Smith President & CEO EVP & CFO EVP, GC, and Chief EVP, Technical Services EVP, Development, Compliance

  43. Slide 43: Eldorado Share Price Performance

    Eldorado Share Price Performance Relative Share Price Performance Capital Structure Common Shares 205,469,879 outstanding(1) Share purchase options(1,2) 3,400,772 Performance share units(1) 1,044,489 Closing share price(3) $20.34 (NYSE: EGO) Market Capitalization(3,4) $4.2 B 52-week Share Price $13.

  44. Slide 44: Operations Update

    Operations Update Solid operational performance during Q1 2025: maintaining full year guidance Q1 2025 2025 Guidance Total Cash Total Cash Asset Production (oz) AISC(1) ($/oz) Production (K oz) AISC(1) ($/oz) Costs(1) ($/oz) Costs(1) ($/oz) Lamaque Complex 40,438 836 1,392 170 – 180 790 – 890 1,290

  45. Slide 45: 2025 Production & Cost Guidance

    2025 Production & Cost Guidance Kışladağ, Türkiye Lamaque Complex, Canada 2025 GOLD PRODUCTION BY MINE(3) Type Open pit Type Underground Gold Production 160 – 170 Koz Gold Production 170 – 180 Koz 14% Total Cash Costs(1,2) $1,020 – $1,120 Total Cash Costs(1,2) $790 – $890 AISC(1,2) $1,200 – $1,300 A

  46. Slide 46: 3-Year Operating Outlook

    3-Year Operating Outlook Gold production (midpoint) increasing 33% over 3 years driven by growth projects Gold Production (000’ oz) 2024A(1) 2025E 2026E(2) 2027E Lamaque Complex 197(1) 170 – 180 180 – 190 175 – 185 Kışladağ 174 160 – 170 135 – 145 165 – 175 Efemçukuru 80 70 – 80 75 – 85 70 – 80 Olym

  47. Slide 47: Hedge Portfolio

    Hedge Portfolio Managing gold and copper downside price exposure Skouries Project Finance Related Hedges Gold Hedges - Zero Cost Collar • Limited forward sales for delivery on June 30, 2026, as follows: • Mitigate volatility risk of the gold price during a period of elevated investment in the Skouri

  48. Slide 48: Sustainability Framework and SIMS

    Sustainability Framework and SIMS SIMS minimum performance standards operationalize our Framework’s four key commitments to ESG-related topics Healthy Environments Now Safe, Inclusive and Responsibly Produced & The Future Engaged & Prosperous Innovative Operations Products Communities • Implementing

  49. Slide 49: Inclusive Diversity

    Inclusive Diversity Committed to fostering safe and inclusive workplaces that value diversity, personal growth and innovation​ Global Initiatives Operating Sites • Updated Equity, Diversity & Inclusion Strategy created with input GREECE from the global employee workforce • 2024 Sustainability Bronze

  50. Slide 50: World Gold Council: Gold 247

    World Gold Council: Gold 247 What is Gold 247 Gold Why Now? The World Gold Council’s strategic vision for 247TM Gold has a systemic role in the world’s transforming the global gold market and economy – as an investment, a reserve elevating gold into the mainstream of asset, a source of employment an

  51. Slide 51: Why Gold & Where do we see Gold Price Moving

    Why Gold & Where do we see Gold Price Moving Now is the time for generalists. Long-Term Store of Value: ▪ Gold has been used as a store of value for thousands of years. ▪ During geopolitical turmoil or financial crises, investors often flock to gold as a Relative Performance over 20-years Relative P

  52. Slide 52: 2025 Full Year Gold Outlook

    2025 Full Year Gold Outlook: central banks and ETF investors likely to drive demand with economic uncertainty supporting gold’s role as a risk hedge Gold Demand Hit New Record in 2024 Central Banks – Buyers for 15 Consecutive Years Quarterly gold demand in volume, tonnes, and value, US$bn(1) Annual

  53. Slide 53: Financial Results

    Financial Results ($ millions unless otherwise noted) Q1 2025 2024 2023 2022 2021 Operating Metrics Realized Gold Price ($/oz) 2,933 2,405 1,944 1,787 1,781 Gold produced (oz) 115,893 520,293 485,139 453,916 475,850 Total cash costs(1) ($/oz sold) 1,153 940 850 878 715 All-in sustaining costs(1) ($/

  54. Slide 54: Historical Operating Results – Lamaque Complex

    Historical Operating Results – Lamaque Complex Q1 2025 FY 2024(2) Q4 2024(2) Q3 2024 Q2 2024 Q1 2024 Operating Data Tonnes milled 248,549 943,509 256,628 232,165 220,157 234,559 Head grade (g/t Au) 5.38 6.74 8.05 6.03 6.95 5.81 Average recovery rate 94.0% 96.1% 95.8% 95.8% 96.3% 96.5% Gold ounces pr

  55. Slide 55: Historical Operating Results – Kışladağ

    Historical Operating Results – Kışladağ Q1 2025 FY 2024 Q4 2024 Q3 2024 Q2 2024 Q1 2024 Operating Data Tonnes placed on pad 3,194,730 13,123,978 3,434,938 3,511,662 3,415,604 2,761,774 Head grade (g/t Au) 0.79 0.81 0.70 0.86 0.92 0.77 Gold ounces produced 44,319 174,080 56,483 41,084 38,990 37,523 G

  56. Slide 56: Historical Operating Results – Efemçukuru

    Historical Operating Results – Efemçukuru Q1 2025 FY 2024 Q4 2024 Q3 2024 Q2 2024 Q1 2024 Operating Data Tonnes milled 127,785 541,782 138,837 131,374 134,540 137,032 Head grade (g/t Au) 5.52 5.39 5.32 5.37 5.92 4.96 Average recovery rate (to concentrate) 91.8% 91.9% 91.4% 92.5% 92.1% 91.5% Gold oun

  57. Slide 57: Historical Operating Results – Olympias

    Historical Operating Results – Olympias Q1 2025 FY 2024 Q4 2024 Q3 2024 Q2 2024 Q1 2024 Operating Data Tonnes milled 98,602 446,732 109,186 124,374 94,575 118,597 Head grade (g/t Au) 7.65 8.54 8.05 9.16 8.11 8.67 Gold average recovery rate (to concentrate) 75.7% 82.3% 81.1% 82.9% 81.1% 83.6% Gold ou

  58. Slide 58: Mineral Reserves (Gold, Silver) as of September 30, 2024

    Mineral Reserves (Gold, Silver) as of September 30, 2024 Project Proven Mineral Reserves Probable Mineral Reserves Total Proven and Probable Tonnes Au Contained Au Tonnes Au Contained Au Tonnes Au Contained Au Gold (x1000) g/t ounces (x1000) (x1000) g/t ounces (x1000) (x1000) g/t ounces (x1000) Efem

  59. Slide 59: Mineral Reserves (Copper, Lead, Zinc) as of September 30, 2024

    Mineral Reserves (Copper, Lead, Zinc) as of September 30, 2024 Project Proven Mineral Reserves Probable Mineral Reserves Total Proven and Probable Tonnes Cu Contained Cu Tonnes Cu Contained Cu Tonnes Cu Contained Cu Copper (x1000) % tonnes (x1000) (x1000) % tonnes (x1000) (x1000) % tonnes (x1000) Sk

  60. Slide 60: Mineral Resources (Gold, Silver) as of September 30, 2024

    Mineral Resources (Gold, Silver) as of September 30, 2024(1) Project Measured Resources Indicated Resources Total Measured and Indicated Inferred Resources Tonnes Au Contained Au Tonnes Au Contained Au Tonnes Au Contained Au Tonnes Au Contained Au Gold (x1000) g/t ounces (x1000) (x1000) g/t ounces (

  61. Slide 61: Mineral Resources (Copper, Lead, Zinc) as of September 30, 2024

    Mineral Resources (Copper, Lead, Zinc) as of September 30, 2024 Project Measured Resources Indicated Resources Total Measured and Indicated Inferred Resources Contained Contained Contained Contained Tonnes Cu Cu tonnes Tonnes Cu Cu tonnes Tonnes Cu Cu tonnes Tonnes Cu Cu tonnes Copper (x1000) % (x10

  62. Slide 62: Notes on Mineral Resources and Reserves

    Notes on Mineral Resources and Reserves General Mineral Reserves and Mineral Resources are as of September 30, 2024 The Mineral Reserves and Mineral Resources were classified using logic consistent with the CIM Definition Standards for Mineral Resources & Mineral Reserves (2014) incorporated, by ref

  63. Slide 63: Notes on Mineral Reserves (cont'd)

    Notes on Mineral Reserves (cont’d) Mineral Reserve Notes Eldorado reports Mineral Reserves in accordance with CIM Definition Standards. Mineral Reserves for the operating sites (Efemcukuru, Kisladag, Olympias, and within the Lamaque Complex – Ormaque and Triangle) were determined using a long-term g

  64. Slide 64: Notes on Mineral Resources

    Notes on Mineral Resources Mineral Resource Notes: Eldorado reports Mineral Resources in accordance with CIM Definition Standards. All Mineral Resources are assessed for reasonable prospects for eventual economic extraction (RPEEE). The Resource cut-off grades or values (e.g. gold equivalent) are de

  65. Slide 65: Thank You

    Thank You TSX: ELD NYSE: EGO eldoradogold.com