Lithium Americas Corp. · NYSE:LAC

Lithium Americas — Technical Presentation (November 2017)

27 slides from Lithium Americas's technical presentation, November 2017

  1. Slide 1: Caucharí-Olaroz Site Visit

    CAUCHARI-OLAROZ SITE VISIT NOVEMBER 6-9 2017 Caucharí-Olaroz NO VEMBERLithium 2017 Project | Jujuy, Argentina

  2. Slide 2: Cautionary Statement

    CAUTIONARY STATEMENT Technical Information producers and potential producers; costs of development and production; anticipated results of Scientific and technical information in this presentation about the Caucharí-Olaroz Project has exploration and development activities; a cordial business relatio

  3. Slide 3: Overview

    OVERVIEW 1. Introduction 1. Project Overview 2. Financial Review | T SX : LAC NO VEMBER 2017 | 3

  4. Slide 4: Introduction

    INTRODUCTION NO VEMBER 2017 | 4

  5. Slide 5: Management Introduction

    MANAGEMENT INTRODUCTION | T SX : LAC NO VEMBER 2017 | 5

  6. Slide 6: Caucharí-Olaroz Lithium Project

    CAUCHARÍ-OLAROZ LITHIUM PROJECT Caucharí-Olaroz is located on an international highway with access to power, water, and a large local labour force Located in Jujuy, Argentina • Large property package ~ 70,000 ha. • Close proximity to current producers (ORE, FMC, SQM, ALB). Near excellent infrastruct

  7. Slide 7: Caucharí-Olaroz Lithium Project (cont.)

    CAUCHARÍ-OLAROZ LITHIUM PROJECT (CONT.) Working closely with local communities • Economic benefits agreements with 6 local communities. • Emphasis on local employment. • Minera Exar Jujuy and field office staff ramping up (over 125 currently). • Construction staff est. over 1,000 workers. • Operatio

  8. Slide 8: Minera Exar History

    MINERA EXAR HISTORY LAC enters a strategic 50/50 JV with SQM March 2016 | T SX : LAC NO VEMBER 2017 | 8

  9. Slide 9: Caucharí-Olaroz JV with SQM

    CAUCHARÍ-OLAROZ JV WITH SQM In March 2016, Lithium Americas entered a strategic 50/50 JV with SQM to develop and operate the Caucharí-Olaroz project Leverages SQM’s technical expertise. SQM is the largest producer of lithium brines with over 20 years experience operating and expanding its world-clas

  10. Slide 10: Project Overview

    PROJECT OVERVIEW NO VEMBER 2017 | 10

  11. Slide 11: Caucharí-Olaroz Development Schedule

    CAUCHARÍ-OLAROZ DEVELOPMENT SCHEDULE MARCH 2016 H1 2017 2018 50/50 JV with Started Stage 1 Plant, gas pipeline, and SQM development electricity transmission line Completed Stage 1 DFS construction 2016 2017 2018 2019 H2 2016 H2 2017 (currently) H2 2019 50,000 tpa development Execution of detailed en

  12. Slide 12: Caucharí-Olaroz Lithium Project Development

    CAUCHARÍ-OLAROZ LITHIUM PROJECT DEVELOPMENT Caucharí-Olaroz is located on an international highway with access to power, water, and a large local labour force • Similar technology as used in the Salar de Atacama operation, minimum mine life 40 years • Project capacity 50,000 MT of LCE in two stages

  13. Slide 13: SQM's Involvement

    SQM’S INVOLVEMENT • Key advantage - the “detail engineering” reflects the improvements SQM made during the construction of ponds and plants for the last 20 years and the expertise of the project team • Plant design - similar configuration of Salar del Carmen plant (mixture between lithium carbonate

  14. Slide 14: Cauchari vs. Atacama

    CAUCHARI VS. ATACAMA SQM has experience in similar Operations and is providing its expertise to have this project be a success- 60 SQM experienced professionals are contributing to the success of this initiative Atacama Cauchari • 4 Well Deposits • 2 Well Deposits • 379 Wells • 30 Wells • 7 PDA • 2

  15. Slide 15: Cauchari Project Layout

    CAUCHARI PROJECT LAYOUT | T SX : LAC NO VEMBER 2017 | 15

  16. Slide 16: Cauchari Project Layout (cont.)

    CAUCHARI PROJECT LAYOUT (CONT.) | T SX : LAC NO VEMBER 2017 | 16

  17. Slide 17: Caucharí-Olaroz Conventional Process

    CAUCHARÍ-OLAROZ CONVENTIONAL PROCESS Design by experience • SQM engineering staff developing design and execution planning. • Process is based on SQM’s +20 years experience operating in the Atacama. • Infrastructure and plant designed to be scaleable to a production capacity of 50,000 tpa of battery

  18. Slide 18: Cauchari Ponds Process: Design and Configuration

    CAUCHARI PONDS PROCESS: DESIGN AND CONFIGURATION | T SX : LAC NO VEMBER 2017 | 18

  19. Slide 19: Cauchari Plant Process: Design and Configuration

    CAUCHARI PLANT PROCESS: DESIGN AND CONFIGURATION | T SX : LAC NO VEMBER 2017 | 19

  20. Slide 20: Caucharí-Olaroz Exploration

    CAUCHARÍ-OLAROZ EXPLORATION Caucharí Salar Hydrostratigraphic Model Drilling program underway (deeper and stepping out): • Olaroz Salar (north) - 10 new holes (7 wells) • Caucharí (deep) - 4 new holes (2 wells) | T SX : LAC NO VEMBER 2017 | 20

  21. Slide 21: Lithium Resource and Reserve Summary

    LITHIUM RESOURCE AND RESERVE SUMMARY Average Li Concentration Brine Volume (m3) (mg/L) Lithium Metal (t) LCE (t) Caucharí-Olaroz (100% basis) Mineral Reserves – March 2017 Proven Reserves (Years 1-5)1,2,3,4 4.93 x 107 712 35,159 187,149 Probable Reserves (Years 6-40) 1,2,3,4 3.54 x 108 695 246,474 1

  22. Slide 22: Financial Review

    FINANCIAL REVIEW NO VEMBER 2017 | 22

  23. Slide 23: Caucharí-Olaroz Stage 1 Feasibility Study

    CAUCHARÍ-OLAROZ STAGE 1 FEASIBILITY STUDY Stage 1 DFS Results (100% basis) March 2017 Average annual production 25,000 tpa battery-grade Li2CO3 Project life 40 years * Proven & probable reserves 1.5 million tonnes LCE at 698 mg/L Li Construction capital costs US$425 million (before VAT) Operating co

  24. Slide 24: Caucharí-Olaroz Stage 1 Opex & Capex

    CAUCHARÍ-OLAROZ STAGE 1 OPEX & CAPEX Initial Capital Costs Operating Costs US$425 million capital costs before US$2,495/t of battery grade lithium VAT and working capital. carbonate produced All figures on a 100% project equity basis unless otherwise noted. Totals may not add due to rounding. | T SX

  25. Slide 25: Cauchari Development Spend to Date

    CAUCHARI DEVELOPMENT SPEND TO DATE | T SX : LAC NO VEMBER 2017 | 25

  26. Slide 26: Cauchari Development Budget

    CAUCHARI DEVELOPMENT BUDGET | T SX : LAC NO VEMBER 2017 | 26

  27. Slide 27: The Future Is Clear

    THE FUTURE IS CLEAR CONTACT INFORMATION info@lithiumamericas.com 1100 – 355 Burrard Street Vancouver, BC V6C 2G8 Canada NO VEMBER 2017 | Hong Kong