Voyager Metals — Investor Presentation (November 2022)
30 slides from Voyager Metals's investor presentation, November 2022

Slide 1: A Unique Iron and Vanadium Opportunity in Quebec
TSX.V: VONE FRANKFURT: 9VR1 AUnique Iron and Vanadium opportunity in Quebec November 2022 TSX.V:VONE

Slide 2: Disclaimer
Disclaimer This presentation contains "forward-looking statements" and "forward-looking information" (collectively, "forward-looking information") within the meaning of applicable Canadian securities legislation. All information contained in this presentation, other than statements of current and hi

Slide 3: Mont Sorcier Iron and Vanadium
Mont Soricer Iron and Vanadium Ideally located for Rapid Low-Cost Development • Located in an established mining district of Chibougamau, Quebec • Site located only 25km from public rail head • >300km of underutilized existing common carry rail space connected directly to ports • Existing low-cost H

Slide 4: Leadership History
Leadership History Team has Extensive Experience From Discovery Through to Production Maracás – Campbell Deposit ▪ Acquired 100% ownership of Maracas in 2006 Bahia State, Brazil Worlds highest grade pure vanadium producer ▪ Advanced project from resource estimate in 2008, through permitting, financi

Slide 5: Why Voyager Metals?
Why Voyager Metals? A Unique Investment Opportunity in Iron and Vanadium • July 2022 PEA Shows an After Tax NPV8 US$1.6 Billion and IRR of 43% RobustPEA Outliners Financials • 5mtpa for 21-year mine life at an all-in cost of US$66.2/dmt conc (CFR China) Robust Financials • Offtake agreement with Gle

Slide 6: Simple Logistics
Simple Logistics Major Infrastructure Already in Place 25 km all season dirt road to CN Railway on the Mont Sorcier outskirts of Chibougamau Town of Chibougamau Pop: 7,500 Mont Sorcier: 25km from Railroad Chibougamau ➢ Rail located 25km from site ➢ CN operated Port Of Saguenay Railroad ➢ All year-ro

Slide 7: Mont Sorcier Project - Preliminary Economic Assessment
Mont Sorcier Project Preliminary Economic Assessment PEA Summary $US Million Production Summary Unit LOM Total / Avg. LOM Magnetite Payable kt 104,303 PAYBACK UNDER 2 YEARS Annual Production Rate mtpa 5.0 Operating Costs Total On-site Operating Costs US$/t $21.9 Royalties US$/t $4.1 ✓ Annual average

Slide 8: Significant Indicated Resource In Place
Mont Sorcier Project Significant Indicated Resource In Place Mineral Resources at Mont Sorcier effective June 6, 2022 ➢ Significant Indicated Resource in place to Backstop Feasibility Study → Mine plan only utilizes Indicated North Zone ➢ Significant Additional Resources to support Future Expansion

Slide 9: Concentrate Quality
Concentrate Quality • Recent metallurgical test work supports the potential production of high-grade iron ore concentrate of at least 65% Fe and 0.6% V2O5 with low levels of TiO2 ready for direct blast furnace Average Davis tube % FeT Magnetite V2O5 SiO2 Al2O3 MgO TiO2 grinding Weig size (P95 Grade

Slide 10: High Quality Resource Base and Product
Mont Sorcier Project High Quality Resource Base and Product Resource and Grade(1) Concentrate Iron Grade (1) 35% Fe% V2O5% 62% Concentrate is the +65% Concentrate new benchmark for 67.5% 2.5% current benchmark for High Grade Green steel fines 68.0% 67.5% 67.0% 66.2% 66.1% Black Iron 65.0% Shymanivsk

Slide 11: Low-Capex and Opex and Robust Economics & Payback
Mont Sorcier Project Low-Capex and Opex and Robust Economics & Payback Capital Intensity ($US Initial Capex/LOM Production)1 NPV/Capital Expenditure($US)1 11.31 2.80 8.28 7.61 1.88 6.59 5.50 1.24 0.69 0.54 Voyager Black Iron Macarthur Magnetite Mines Zanaga Iron Magnetite Mines Zanaga Iron Macarthur

Slide 12: Premium Product Pricing
Premium Product Pricing Market Study Results Iron Ore Prices ▪ Third party market study supports premium product pricing expected. Revenue derived 86% by iron and 14% by V2O5 Iron Ore Concentrate Index Pricing by Grade 250 US$165/t ▪ Long term pricing consistent with the mine life of 21 years 200 ha

Slide 13: Port of Saguenay MOU
Port of Saguenay MOU Port Development Collaboration Voyager and the Port of Saguenay Sign MOU to Support Development Mont Sorcier Project Key Terms ➢ Memorandum of Understanding signed August 2021 ➢ Federally owned Port planned as primary stockpiling and export location for Mont Sorcier concentrate

Slide 14: Moving Mont Sorcier Forward
Moving Mont Sorcier Forward Unlocking the Value of Mont Sorcier Voyager’s Plan to deliver a Feasibility Study for Mont Soricer: ✓ Undertake Drilling Program to Upgrade Resources to M&I to support at least a 20-year mine life ✓ Undertake updated PEA focused on the North Zone Only – Completed July 202

Slide 15: Development Timeline
Moving Mont Sorcier Forward Development Timeline • Targeting Initial Production mid 2027 subject to permitting Source: Company Estimates TSX.V: VONE 15

Slide 16: Significant Re-rating Potential
Voyager Metals Significant Re-rating Potential Resource Metrics(2) M+I+I Share Price Market Cap Enterprise Value EV/Tonne Company Name Location Project Name Project Status Resource Fe Grade (%) Ore Type EV/NPV $US (MM) $US (MM) $US Fe* (MM t) Champion Iron 3.08 $1,595.2 $1,781.5 Canada Bloom Lake Pr

Slide 17: Capital Structure
Capital Structure Capital Structure Share Ownership Tickers TSXV:VONE Management & Frankfurt: 9VR1 Board 14% Share Price (as of Nov 1, 2022) C$0.10 RAB Capital Basic Shares Outstanding 93.0M 9% Options (Weighted avg. strike price of C$0.15) 9.1M Warrants (Weighted avg. strike price of C$0.41) 12.8M

Slide 18: Reasons To Invest
Reasons To Invest Voyager Metal’s team has added substantial value to the Mont Sorcier magnetite IronOre and Vanadium project since acquiring the project in September 2016 Moving towards Feasibility by the end of Q2 Globally 2023 Significant Resource 679mt High quality 65% Indicated and 596mt iron o

Slide 19: Appendix
‘VOYAGER Metals Inc.

Slide 20: Management
MANAGEMENT Clifford Hale-Sanders | President and CEO, Director Mr. Cliff Hale-Sanders is an entrepreneurial and driven mining executive, a co-founder of Ascendant Resources Inc in late 2016 and has over 20 years of capital markets experience as an Equity Mining Research Analyst. During this period M

Slide 21: Management
MANAGEMENT Michael Skutezky | Senior Legal Counsel and Corporate Secretary Mr. Michael Skutezky has had a 30 year career in the financial sector in Canada including as Assistant General Counsel of the Royal Bank of Canada focused on International and Canadian Project financing based in Montreal and

Slide 22: Board of Directors
BOARD OF DIRECTORS Mark Brennan | Chairman Mr. Brennan is Executive Chairman of Voyager Metals. He is a Founding Partner and Executive Chairman of Ascendant Resources Inc. and Cerrado Gold’s CEO and Co-Chairman, and has more than 30 years of financial and operating experience in the Americas and Eur

Slide 23: Advisory Board
ADVISORY BOARD Norman Steinberg Mr. Steinberg is a highly distinguished Quebec based lawyer and an esteemed member of the Quebec business & philanthropic community. Mr. Steinberg served as Global Chairman of Norton Rose Fulbright, one of the world’s top 10 legal firms, which combined with Ogilvy Ren

Slide 24: Glencore Support and Offtake
Glencore Support and Offtake Long Term Relationship to Support Development Voyager and Glencore have entered into agreements to support the long term development of the Mont Sorcier project Financial Assistance Agreement • Glencore to assist Voyager Metals in raising not less than US$10 million, eit

Slide 25: Historical Drill and Recent Drill Locations
Mont Sorcier Project Historical Drill and Recent Drill Locations TSX.V: VONE

Slide 26: The Mont Sorcier Project
THE MONT SORCIER PROJECT PROJECT HISTORY Ownership • 100% owned by Voyager Metals Location • 1,919 ha property located 18 km east of the city of Chibougamau Québec • Excellent regional infrastructure, including access to rail, airports, seaports and low-cost hydro power Deposits • Bulk tonnage magne

Slide 27: Conceptual Flow Sheet
Conceptual Flow Sheet Standard Magnetic Separation Design TSX.V: VONE 27

Slide 28: Ready Market for Concentrate
MONT SORCIER PROJECT READY MARKET FOR CONCENTRATE Potential Ready Market for Mont Sorcier’s Unique Low Titanium Concentrate Potential Blast Furnace-ready Mont Sorcier Iron-Vanadium Concentrate Existing Vanadium Existing Steel Slag Producers Co-producers • Low Titanium content (<2%) means concentrate

Slide 29: Technical Disclosure
Technical Disclosure *Qualified Persons Statements The July 25, 2022 PEA and other scientific and technical information contained in this news release were prepared by various “qualified persons” in accordance with the Canadian regulatory requirements set out in NI 43-101. The content has been revie

Slide 30: Contact Us
CONTACT US Cliff Hale-Sanders Chief ExecutiveOfficer Cell: +1 (416) 819-8558 Email:csanders@voyagermetals.com Website: www.voyagermetals.com 125 Rue des Forces Armées Chibougamau, QC Canada G8P 3A1 TSXV: VONE 501 – 110 YongeStreet FRANKFURT: 9VR1 Toronto, ON Canada M5C 1T4 22
Source: Internet Archive copy of voyagermetals.com