Pge Polska Grupa Energetyczna — Technical Presentation (March 2026)

43 slides from Pge Polska Grupa Energetyczna's technical presentation, March 2026

  1. Slide 1: Offshore Wind 2026+: Global Trends, PGE Baltica Portfolio and Financial Model Insights

    Offshore Wind 2026+: Global Trends, PGE Baltica Portfolio and Financial Model Insights 1 March 2026

  2. Slide 2: Today’s presenters

    Today’s presenters Bartosz Fedurek Łukasz Gołaszewski CEO CFO ▪ Experience: over 20 years in the energy sector, shaping ▪ Experience: 20 years of experience in corporate finance, development strategies and delivering large-scale energy funding, debt structuring, financial analysis, controlling and p

  3. Slide 3: Table of contents

    Table of contents 1. PGE Baltica portfolio 2. Global trends 3. Key business case assumptions 4. Financial model insights – project perspective 5. Financial model insights – equity perspective 3

  4. Slide 4: PGE Baltica portfolio

    1 PGE Baltica portfolio 4

  5. Slide 5: PGE Baltica leads Poland’s offshore wind sector

    PGE Baltica leads Poland’s offshore wind sector, turning Baltic wind into value for the energy system, the economy and society. Our values: Trust I Responsibility I Courage I Collaboration I Efficiency 5 Confidential

  6. Slide 6: PGE pipeline [MW]

    PGE pipeline [MW] Note: Baltica 2 and Baltica 3 are owned by PGE (50%) and Orsted (50%) 6

  7. Slide 7: PGE Baltica manages the largest offshore wind portfolio in Poland

    Following the December 2025 CfD auction, PGE Baltica manages the largest offshore wind portfolio in Poland CfD-awarded project capacity [GW] 3,8 Baltica 9+, 1.3 GW FEW Baltic II, 0.35 GW 3,0 Baltica 9, 0.975 GW Bałtyk III, 0.75 GW 2,1 Baltica 3, 1.0 GW (50/50 JV with Ørsted) Bałtyk II, 0.75 GW Balti

  8. Slide 8: PGE Baltica serves as the PGE Group’s offshore competence center

    PGE Baltica serves as the PGE Group’s offshore competence center, supported by HQ expertise in specific domains PGE Baltica’s Project Origination Construction O&M Decommissioning competences development Core competence areas of PGE Baltica: Sector analyses, portfolio Stakeholder Procurement Project

  9. Slide 9: A journey of intensive knowledge growth and capability-building achievements

    A journey of intensive knowledge growth and capability-building achievements • Setting up PGE Baltica • Signing of the final 50/50 • Final Investment • Acquisition of RWE’s Polish Baltica 9+ to lead PGE Group’s joint venture agreement Decision (FID) for 1.5 offshore assets offshore wind strategy wit

  10. Slide 10: Disclaimer

    Disclaimer The results, forecasts and model outputs presented herein do not represent, reflect or imply the financial performance or technical assumptions of any existing or planned projects of PGE Polska Grupa Energetyczna. All values and model parameters shown in this presentation have been prepar

  11. Slide 11: Global trends

    2 Global trends 11

  12. Slide 12: China and the UK are the largest offshore wind players

    China and the UK are the largest offshore wind players Source: PGE estimates based on publicly available data 12

  13. Slide 13: Top countries for offshore wind (operational projects) worldwide [MW]

    Top 10 countries for offshore wind (operational projects) worldwide [MW] Source: PGE estimates based on publicly available data 13

  14. Slide 14: Market downturn (2022-2024)

    Market downturn (2022-2024) 14

  15. Slide 15: 2025/2026 Breakthrough – The Great Comeback

    2025/2026 Breakthrough – The Great Comeback 15

  16. Slide 16: Comparison of support levels [PLN’25/MWh]

    Comparison of support levels [PLN’25/MWh] Note: Where applicable, prices have been estimated using capacity-weighted averages 16

  17. Slide 17: The future of offshore wind worldwide

    The future of offshore wind worldwide Source: PGE estimates based on publicly available data 17

  18. Slide 18: Global offshore wind development trends

    Global offshore wind development trends 18

  19. Slide 19: Offshore Wind – the ultimate renewable energy source

    Offshore Wind – the ultimate renewable energy source Characterizes with highest capacity factors among renewable sources Productivity corelated with demand seasonally, peak performance during winter when energy is most needed Lowest volatility of production among renewable sources The most stable re

  20. Slide 20: Offshore Wind – the ultimate renewable energy source

    Offshore Wind – the ultimate renewable energy source 20

  21. Slide 21: Key business case assumptions

    3 Key business case assumptions 21

  22. Slide 22: Key offshore wind regulations in Poland

    Key offshore wind regulations in Poland Key highlights OWF support scheme ▪ The legal framework regulating and supporting the offshore wind sector in Poland is set out in the Act on Promoting Phase I Phase II Electricity Generation in Offshore Wind Farms, which entered into force in 2021 and was sub

  23. Slide 23: CfD support scheme – main regulations

    CfD support scheme – main regulations CfD contract is granted for 25 years from the first generation and introduction to the grid of electricity generated in an OWF or part thereof, based on the granted license. Electricity volume under CfD is limited up to 100 000 hours of generation at full capaci

  24. Slide 24: Capital expenditures for offshore projects in Poland

    Capital expenditures for offshore projects in Poland • We assumed approximately PLN 19m per MW of total CAPEX and DEVEX for the offshore wind Baltica 2 Baltic Power Bałtyk 2&3 project based on data for Polish projects. • These assumptions were nominalised using five years of annual inflation to refl

  25. Slide 25: Data sources for UK benchmarks

    Data sources for UK benchmarks • The Arup’s Cost of Electricity Report Update 2024 is an update of cost and technical assumptions for offshore wind prepared for DESNZ. It is based primarily on developer surveys, complemented by a literature review and Arup’s own benchmarks. The data were collected a

  26. Slide 26: CAPEX for offshore wind projects in the UK

    CAPEX for offshore wind projects in the UK [PLNm, real 2023] CAPEX/MW CAPEX breakdown 25 Package Share 21,76 Turbine supply 25% 20 Power export infrastructure 24% 17,23 Foundation supply 11% 15 14,17 Other Costs 11% Transport & Installation 10% 10 Offshore substation EPC 9% Cables supply 6% Pre-deve

  27. Slide 27: Development and capital spend profiles

    Development and capital spend profiles This table applies the scenario-specific development and capital spend profiles recommended by the Peer Review for modelling purposes. Spend profile Year Scenario category 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Development High 2% 2% 2% 2% 2% 5% 5% 5% 5% 10% 10% 1

  28. Slide 28: Combined PL-specific CAPEX spend profile

    Combined PL-specific CAPEX spend profile The chart below shows the consolidated expenditure spend profile (Peer Review-adjusted medium scenario) applied in the modeling: • Combined CAPEX: Development (4 years) + Capital (3 years) • Total of 7 years as per the Offshore Wind Act (from CfD award to fir

  29. Slide 29: OPEX for offshore wind projects in the UK

    OPEX for offshore wind projects in the UK [PLNm, real 2023] OPEX breakdown OPEX/MW/a 0,40 0,371 Package Share 0,35 Turbine maintenance and service 40% 0,30 0,275 Balance of plant maintenance and service 14% 0,25 Insurance 13% 0,192 0,20 Logistics (onshore & offshore) 10% 0,15 Admin and support staff

  30. Slide 30: DECEX for offshore wind projects in the UK

    DECEX for offshore wind projects in the UK [PLNm, real 2023] DECEX/MW DECEX breakdown 3 Package Share 2,53 2,5 Cable decommissioning 36% Foundation decommissioning 31% 2 Turbine decommissioning 25% Substation decommissioning 8% 1,5 1,27 Source: based on BVG Associates. Guide to an Offshore Wind Farm

  31. Slide 31: Load factor

    31 Load factor Average capacity factor for Polish part of Baltic Sea 45% Results of the capacity factor assesment Current areas 42.7% 474% Potential areas 42.5% 48.5% © The capacity factor shows significant spatial variability and is determined by a range of factors, including local wind conditions,

  32. Slide 32: WACC for an EUR denominated project

    WACC for an EUR denominated project 32

  33. Slide 33: IRR to WACC premium assumed by leading offshore wind developers

    IRR to WACC premium assumed by leading offshore wind developers 33

  34. Slide 34: Financial model insights – project perspective

    4 Financial model insights – project perspective 34

  35. Slide 35: Simplified financial model will be a base for further simulations

    Simplified financial model will be a base for further simulations Summary of main assumptions for financial model Operational lifetime 35 years P50 Capacity Factor 45% P90 Capacity Factor 40,5% Start of operational period 2033 Development & Construction period 2025-2032 DECEX 1,27 mPLN’25/MW CAPEX&D

  36. Slide 36: P50 Revenues

    P50 Revenues Revenues [bPLN] 4,5 4,0 3,5 3,0 2,5 4,0 4,2 2,0 4,0 3,8 3,9 3,6 3,7 3,4 3,5 3,2 3,3 3,1 3,2 1,5 2,9 2,9 3,0 2,7 2,8 2,6 2,7 2,5 2,5 2,3 2,4 2,4 1,0 1,9 1,9 1,9 1,9 1,9 1,9 1,9 1,9 1,9 1,9 0,5 0,0 Conservative approach was adopted and Revenues from Guarantees of Origin have not been take

  37. Slide 37: P50 EBITDA and EBIT

    P50 EBITDA and EBIT EBITDA & EBIT [bPLN] 4 3,5 3,5 3,4 3,3 3,3 3 3,2 3,1 3,0 3,0 2,9 2,8 2,7 2,5 2,7 2,6 2,5 2,5 2,4 2,4 2,3 2,2 2,3 2 2,1 2,0 2,1 1,9 2,0 1,5 2,9 2,7 2,8 2,6 2,7 2,4 2,5 2,3 2,3 2,1 2,2 1,3 1,3 1,2 1 2,0 2,1 1,2 1,2 1,2 1,2 1,9 1,9 1,2 1,1 1,1 1,8 1,8 1,6 1,7 1,5 1,5 1,6 1,3 1,4 1,4

  38. Slide 38: P50 Sensitivity analyses

    P50 Sensitivity analyses EBITDA [mPLN] 4000 3500 3000 2500 2000 1500 1000 500 0 2030 2035 2040 2045 2050 2055 2060 2065 -500 P50 Base Case 500 Negative Hours Electricity price after 25 years -25% OPEX indexation larger by 1% than CPI -1000 Case FCFF IRR P50 Base Case 7,8% 500 Negative Price Hours vs

  39. Slide 39: Strike Price vs LCOE

    Strike Price vs LCOE Strike Price - represents the per-unit electricity price bid under a CfD scheme, ensuring the investor achieves the expected rate of return. The CfD rules applicable to this price include, among others, the contract duration and indexation mechanisms. Merchant tail revenues also

  40. Slide 40: Financial model insights – equity perspective

    5 Financial model insights – equity perspective 40

  41. Slide 41: Debt service, CFADS vs debt payments

    Debt service, CFADS vs debt payments CFADS vs Debt Repayment [mPLN] 3 000 2 500 2 000 1 500 1 000 500 0 -500 -1 000 Repayment Interest paid CFADS Period 2033-2055 2056 Debt Service Cover Ratio 1,34 1,40 For Project Financing following assumptions have been adopted: • 80% levarage (D/(D+E)) • 5,7% co

  42. Slide 42: Sensitivity analyses for bank case P90

    Sensitivity analyses for bank case P90 CFADS [mPLN] 3000 2500 2000 1500 1000 500 0 2020 2025 2030 2035 2040 2045 2050 2055 2060 2065 2070 P90 c Case P50 Base 500 Negative Price Hours vs 200 Negative Price Hours Electricity price after 25 years -25% OPEX indexation larger by 1% than CPI Case DSCR P90

  43. Slide 43: Thank you

    Thank you 43