Aurelia Metals Limited · ASX:AMI
Aurelia Metals — Corporate Update (May 2024)
20 slides from Aurelia Metals's corporate update, May 13, 2024
Slide 1: May 2024 CCC Presentation
May 2024 CCC Presentation 13th May 2024 January – March 2024 Peak/NCC CCC Presentation ASX Code: AMI
Slide 2: Acknowledgement of Country
2 Acknowledgement of Country May 2024 CCC Presentation • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to
Slide 3: Peak Project CCC Presentation April–June 2023
April – June 2023 Peak Project CCC September 2023 5 Presentation CCC Presentation 4 September 2023
Slide 4: Work, Health & Safety
3 Work, Health & Safety January - March 24
Slide 5: Performance summary
4 Presentation September 2023 CCC • Group TRIFR reduced from 8.6 to 7.6 across the quarter • Protocols adapted to manage risk of Omicron remain effective • Reduced workforce availability (approximately 20% across the Performance group) saw modest throughout and production impacts • Group gold produc
Slide 6: Safety is at the core of our business
6 Safety is at the core of our business May 2024 CCC Presentation Peak Work, Health and Safety January - March 24 1 Positive activity • Lead indicator activity by departments for the period was at full practical compliance • Mines Rescue recruited 4 x new members • Mines Rescue team prepared for the
Slide 7: Safety is at the core of our business
7 Safety is at the core of our business May 2024 CCC Presentation Work, Health and Safety January - March 24 3 Health and Safety • Review of health and emergency medical/first aid capability completed. Continuing implementation of key priorities in process with review & sourcing of new medical equip
Slide 8: Environment & Community
8 Environment & Community January - March 24
Slide 9: Social licence to operate
9 Social licence to operate May 2024 CCC Presentation Seeking to deliver mutual benefit January - March 24 Community a critical stakeholder • Aurelia is the sole sponsor of the Annual Arts Exhibition by supporting it with a $2500 donation • The Annual Golden Clay & Junior Masters prizes were funded
Slide 10: Environmental Incidents, Complaints & Initiatives
10 Peak Mine May 2024 CCC Presentation Environmental Incidents, Complaints & Initiatives January - March 24 Complaints • No complaints were received during the period. January - March 2024 Peak Project CCC 13 May 2024 Presentation
Slide 11: Peak Mine Environmental Monitoring
January - March 2024 Peak Project CCC 11 May 2024 CCC Presentation Presentation 13 May 2024 Peak Mine Environmental Monitoring January - March 24
Slide 12: Dust Deposition Gauges (EPL)
12 Peak Mine May 2024 CCC Presentation January - March 2024 Dust Deposition Gauges (EPL) 4.5 4 3.5 Insoluble Solids (g/m2/month) 3 2.5 2 1.5 1 0.5 0 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Axis Title January - March 2024 Peak Project CCC DM1 DM2 DM3 DM4 Bi
Slide 13: Dust Deposition Gauges April 2023 - March 2024
13 Peak Mine May 2024 CCC Presentation April 2023 - March 2024 Dust Deposition Gauges 9 8 7 Insoluble solids (g/m2/month) 6 5 4 3 2 1 0 January - March 2024 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23 Nov-23 Dec-23 Jan-24 Feb-24 Mar-24 Peak Project CCC GC1 GC2 GC3 GC4 GC1 annual Ave GC2 Annual
Slide 14: January - March 2024 Blast Vibration
January - March 2024 Peak Project CCC 14 May 2024 CCC Presentation Presentation 13 May 2024 mm/s 0 2 4 6 8 10 1/1/2024 1/3/2024 1/5/2024 1/7/2024 Peak Mine 1/9/2024 1/11/2024 1/13/2024 1/15/2024 1/17/2024 below the 5% EPL limit. Sal ty 1/19/2024 New Occ 1/21/2024 1/23/2024 1/25/2024 1/27/2024 1/29/2
Slide 15: Projects Update
15 Projects Update aurelia “3-
Slide 16: July–September 2023 Peak Project CCC
July – September 2023 Peak Project CCC 16 December 2023 CCC Presentation Presentation 11 December 2023
Slide 17: Federation Approval Road Upgrades
17 Federation Approval Road Upgrades May 2024 CCC Presentation • Road access upgrades at Peak/ Kidman Way intersection to begin mid- late Q1 2024 • Required under Federation Approval • All licenses and approvals and the construction will be managed by Federation team January - March 2024 Peak Projec
Slide 18: Golden Walk
18 Golden Walk April 2023 May 2024 CCC Presentation • The Golden Walk at Peak has been a tourist attraction for many years however it requires major upgrades due to dated material and public safety. • Peak has found multiple tourist vehicles on site despite increased signage and information given to
Slide 19: New Occidental Review of Environmental Factors Bulk Sample
19 New Occidental Review of Environmental Factors (REF) Bulk Sample May 2024 CCC Presentation REF submitted to Resources Regulator February 2024 for a bulk sample of the Northern and Southern New Occidental Tailings. Purpose is to assess quality of material and future rehabilitation pathways. • 20,0
Slide 20: Contact
CONTACT T: +61 7 3180 5000 E: office@aureliametals.com.au Level 17, 144 Edward Street BRISBANE QLD 4000 GPO Box 7 BRISBANE QLD 4001 aureliametals.com.au