  1. Slide 1: Southern Natural Gas Company 2020 Outage Review WebEx

    Southern Natural Gas Company 2020 Outage Review WebEx March 18, 2020

  2. Slide 2: Welcome

    Southern Natural Gas Company, L.L.C. Welcome

  3. Slide 3: Agenda

    Agenda • Review of current and upcoming notable Outages – March/April/May/June • Unscheduled outages • North System • South System • SESH system • South Louisiana • EEC 2020 • Next WEBEX will be 4-15-20 • Contacts 3

  4. Slide 4: Disclaimers

    Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas

  5. Slide 5: Color Key for Maps

    Color Key for Maps • Yellow – Restrictions are possible – With extended duration, restrictions could be necessary from time to time – Lower than normal pressures may be experienced – Meter(s) affected are noted with (PIN #) • Red – Restrictions are probable 5

  6. Slide 6: Southern Natural Gas Pipeline

    Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS McConnells Tarrant Bell Mills Atlanta Aiken Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Trinity Bie

  7. Slide 7: Southern Natural Gas Pipeline Unscheduled Outage Update

    Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba

  8. Slide 8: SNG North System Pigging Review March/April/May/June

    SNG North System Pigging Review March/April/May/June Chattanooga Pigging on 2ndNML Pigging on 2ndNML Huntsville5-12-20 to 5-14-20 5-5-20 to 5-7-20 Pro.5202-West of Tarrant Rome Pro. 4753-East of McConnells AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Provi

  9. Slide 9: SNG North System Maint. Review March/April/May/June

    SNG North System Maint. Review March/April/May/June Chattanooga Huntsville Rome AL Muldon Shut-in test Muldon Storage Bear Creek Shut-in test Atlanta 3-31-20 to 4-6-20 Tarrant Bell Mills 4-14-20 to 9 AM on 4-21-20 DIQ and DWQ allocated 64% MS DIQ and DWQ allocated 36% McConnells Pell City Reform DeA

  10. Slide 10: SNG South System Pigging Review March/April/May/June

    SNG South System Pigging Review March/April/May/June Pigging on SM3rdLL 5-5-20 to 5-7-20 MS Pro. 5649-East of Selma Pigging on SM2ndLL Hartwell 5-19-20 to 5-21-20 Pigging on Mont. Col. line Pro. 4863-East of Ocmulgee 4-14-20 to 4-15-20 Atlanta Aiken Pigging on GPLL Pro. 5199-West of Auburn 3-17-20 t

  11. Slide 11: SNG South System Maint. Review March/April/May/June

    SNG South System Maint. Review March/April/May/June Valve repair on SM3rdLL Unit overhaul 4-4-20 to 4-9-20 3-30-20 to 4-22-20 At Wrens Station MS At Thomaston Station Seg. 490 cap. of 1547 Mdth/d Seg. 560 Cap. of 680 Mdth/d impacted 505 Mdth/d Hartwell impacted 102 Mdth/d Aiken Atlanta Unit Maint. W

  12. Slide 12: SESH System Maint. Review March/April/May/June

    SESH System Maint. Review March/April/May/June MS SESH maintenance SESH maintenance 3-27-20 & 3-28-20 Hartwell 3-21-20 –Seg. 380 Seg. 380 Cap. of 507 Mdth/d Cap. of 507 Mdth/d Atlanta Aiken reduced to 449 Mdth/d reduced to 426 Mdth/d SESH maintenance Wrens 3-20-20 –Seg. 380 GA Cap. of 507 Mdth/d Ocm

  13. Slide 13: SNG South Louisiana System Pigging Review March/April/May/June

    SNG South Louisiana System Pigging Review March/April/May/June Gwinville Pearl River MS LA Franklinton Pigging on MPFLL 3-17-20 to 3-26-20 Pro. 5990-North of Toca West PiggingLeg on MPF2ndLL White Castle 6-11-20 to 6-15-20 Pro. 5610 south of Pigging on MPFL Lacombe Toca 3-19-20 to 4-2-20 Pro. 6139-N

  14. Slide 14: SNG South Louisiana System Maint. Review March/April/May/June

    SNG South Louisiana System Maint. Review March/April/May/June Gwinville Pearl River Remediation on DLFL Sea Robin SS-28 line Pressure 4-13-20 to 5-8-20 Test. 5-4-20 to 5-18-20 Segment 340 capacity of 701 Line will be out of service Mdth/d impacted as much as MS Meters affected LA 194 Mdth/d Franklin

  15. Slide 15: EEC line March/April/May/June

    EEC line March/April/May/June Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Logansport Elba Rankin Bay Springs Selma

  16. Slide 16: SNG North System Maint. Review remainder of year

    SNG North System Maint. Review remainder of year Chattanooga Pigging on NML Pigging on NMLL 8-4-20 to 8-6-20 9-15-20 to 9-16-20 Huntsville Pigging on NMLL Pro. 5555 east of Onward Pro. 9405 west of Providence 9-15-20 to 9-18-20 Pro. 37017Rome west of Tarrant Muldon Shut-in test AL 10-6-20 to 10-12-2

  17. Slide 17: SNG South System Maint. Review Remainder of 2020

    SNG South System Maint. Review Remainder of 2020 MS Hartwell Pigging on GPLL Aiken Atlanta 8-17-20 to 8-19-20 Pro. 4854 south of Pickens Remediation on SML Wrens 11-28-20 to 12-31-20 GA Pro. TBD7 east of Selma Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Pigging on WSLL 7-14-20 to 7-16-20 Elba Ga

  18. Slide 18: SNG South Louisiana System Maint. review Remainder of year

    SNG South Louisiana System Maint. review Remainder of year Gwinville Pearl River Pigging on FG2ndLL MS 8-17-20 to 8-20-20 LA Franklinton Pro. 8927 north of Franklinton West Leg White Castle Toca East Leg White Castle and Shadyside Shadyside unit maintenance 9-1-20 to 10-31-20 Segment 340 capacity of

  19. Slide 19: EEC line 2020

    EEC line 2020 Chattanooga Pigging on Elba Express 8-18-20 to 8-18-20 Rome Pro. 4710-north of Rincon Hartwell SC Muldon North System BellPigging on Elba Express GA MS McConnells Mills Tarrant 8-20-20 to 8-25-20 Atlanta Aiken Reform Pro. 9913-South of Hartwell DeArmanville Providence Pell City Hall Ga

  20. Slide 20: Gas Control Contacts

    Gas Control Contacts Reese Hart – Manager – (713) – 420 – 4774 (office) – (832) – 248-2937 (cell) – Maurice_hartIII@kindermorgan.com Kal Dankovich – Outage Coordinator – (713) – 420 – 7522 (office) – kalman_dankovich@kindermorgan.com Jimmy Reese – Lead Controller – (713) – 420 – 7310 (office) – jimm

  21. Slide 21: Questions?

    Questions? Southern Natural Gas y, LLC. 21