Gwr — Golden West Resources — Investor Presentation (June 2010)

16 slides from Gwr's investor presentation, Jun 3, 2010

  1. Slide 1: Investor Presentation news release

    NEWS RELEASE 3 June 2010 INVESTOR PRESENTATION Please find attached the presentation to be made by Chief executive officer, Mark Hine and Executive director, John Lester, to investors in Sydney on 3 June 2010 and Melbourne on 4 June 2010. The presentation sets out the Company’s Development Strategy.

  2. Slide 2: Investor Presentation June 2010

    Investor Presentation June 2010 Wiluna West Iron Ore Project – A Sound Investment

  3. Slide 3: Overview

    Overview David Sanders (Non Executive Chairman) 15 years experience in corporate and resources law John Lester (Executive Director) 35 years international stockbroking experience and corporate adviser Mick Wilson (Executive Director) 25 years exploration geologist in Australia and SE Asia, discovere

  4. Slide 4: Development Strategy

    Development Strategy       Resource Large Enough to Underpin Successful Commercial Development

  5. Slide 5: Stage I: Short Term Strategy

    Stage I: Short Term Strategy         Tonnes Fe % SIO2 % Al2O3 P % LOI %  (Mt) %  IND 9.9 63.9 3.5 1.8 0.03 2.4 INF 8.9 62.6 4.4 1.9 0.04 2.4  TOTAL 18.8 63.3 3.9 1.9 0.04 2.4 Stage I Delivers Strong Margins While Demonstrating The Quality of The Resource

  6. Slide 6: Esperance: Unlocking Immediate Value

    Esperance : Unlocking Immediate Value         Spur or Public Total Port Road Rail (km) (km) (km) Oakajee 230 400 630 Esperance 320 650 970 Esperance Option – Infrastructure Backbone in Place

  7. Slide 7: Stage II: Medium Term Strategy

    Stage II: Medium Term Strategy          Stage II Enhances Project Economics while Long Term Infrastructure Developed

  8. Slide 8: Stage III: Long Term Strategy

    Stage III: Long Term Strategy          Project Scale Underpinned by Quality of Resource and Support of Off-take Partner

  9. Slide 9: Stage III: Long Term Strategy

    Stage III: Long Term Strategy          Spur or Public Total Port Road Rail (km) (km) (km) Oakajee 230 400 630 Esperance 320 650 970 Project Scale Underpinned by Quality of Resource and Support of Off-take Partner

  10. Slide 10: Project Costs: Wiluna West

    Project Costs: Wiluna West Development Strategy GWR Infrastructure Mine Mine Wiluna West Project Mine Capex Capex Opex Output ($’Mil) ($’Mil) ($/t) (Mtpa) Stage I* 1.0 10 5 80 Stage II# 3.0 75+ 15 70 Stage III – Oakajee# 10.0 500+ 350 50 Stage III – Esperance# 10.0 600+ 350 60 *Capex and Opex estima

  11. Slide 11: Market Outlook

    Market Outlook @i) GoldenWest RESOURCES LIMITED > Chinese Steel Consumption forecast to double over next 10 years. > Iron Ore Market to remain in tight supply until 2013. > China is experiencing a remarkable demographic transition. > China now the Worlds largest Automobile Manufacturer. Calendar Yea

  12. Slide 12: Investment Metrics

    Investment Metrics   Hematite Iron Ore Resources A$/t EV per Resource Tonnes 14 13 with infrastructure sol'n 12  11 10 without infrastructure sol'n 9 8 7 6  5 4 3 2 1  0 GWR TLM AQD GIR WPG IOH POL/MIN BRM FRS AGO CUL HLX BCI MGX UMC FMG RHI FMS MMX Wiluna West is a High Quality Asset

  13. Slide 13: Key Project Milestones

    Key Project Milestones Milestone Target Date Status Native Title Agreement Jul 2010 Commercial terms agreed 60 Mt Reserve Dec 2010 Advanced Stage I Mining Approval Dec 2010 Application lodged Stage I Rail and Port Agreements Dec 2010 Initiated Stage I Mining Apr 2011 Mine Approval Dependent Stage II

  14. Slide 14: Summary

    Summary          Wiluna West Iron Ore Project – A Robust Development Strategy

  15. Slide 15: Regulatory and Compliance

    Regulatory and Compliance Gy GoldenWest RESOURCES LIMITED Disclaimer This presentation contains reference to certain plans of Golden West Resources Limited which may or may not be achieved. The performance and operations of Golden West Resources Limited may be influenced by a number of factors, unce

  16. Slide 16: Thank You

    Thank You Wiluna West Iron Ore Project – A Sound Investment